Infrastructure Delivery Plan Interim Update<br />

December 2013


INFRASTRUCTURE DELIVERY PLAN: CONTENTS<br />

1. Introduction<br />

Introduction to Infrastructure Delivery Plan ····························································· 4<br />

Purpose of Infrastructure Delivery Plan ···································································· 4<br />

Completed projects since March 2012 ······································································ 5<br />

2. Position Statements<br />

2.1 Enterprising City Programme<br />

Digital Infrastructure Network ·················································································· 8<br />

Enterprise Centres for Creative and Cultural Industries ············································ 9<br />

Vacant Commercial Premises ··················································································· 10<br />

2.2 Learning City Programme<br />

Primary Schools ········································································································ 12<br />

Secondary Schools ··································································································· 14<br />

Special Schools ········································································································ 15<br />

University Centre Croydon ······················································································ 16<br />

2.3 Creative City Programme<br />

Libraries ···················································································································· 18<br />

Fairfield Halls ··········································································································· 19<br />

2.4 Connected City Programme<br />

East Croydon Station ································································································ 21<br />

West Croydon Station ····························································································· 22<br />

Station Improvement Programme ··········································································· 23<br />

Rail Capacity Increases ···························································································· 24<br />

Street Lighting ·········································································································· 30<br />

Parking ····················································································································· 31<br />

Street wayfinding and signage ················································································· 32<br />

Purley Town Centre ·································································································· 33<br />

Bus System ··············································································································· 34<br />

Cycling Infrastructure ······························································································ 36<br />

Freight and Deliveries ······························································································ 38<br />

Taxis ·························································································································· 39<br />

2.5 Sustainable City Programme<br />

‘Parks to be proud of’ Projects ················································································ 41<br />

Play Areas ················································································································· 42<br />

Sports Pitches ·········································································································· 43<br />

Public Realm Improvements ···················································································· 44<br />

Urban Woodland and Trees ····················································································· 46<br />

Walking and Cycling on Greenways ·········································································· 47<br />

Mayor of London– Access to Nature ······································································· 48<br />

Mayor of London– Capital Growth ·········································································· 49<br />

Mayor of London Green Grid– London Downlands Partnership ····························· 50<br />

Allotments ··············································································································· 51<br />

Mayor of London’s Blue Ribbon Network ······························································· 52<br />

Mayor of London’s Street Tree Programme ···························································· 53<br />

Electricity Substations ······························································································ 54<br />

Tramlink ··················································································································· 26<br />

Road Network ·········································································································· 28<br />

2


INFRASTRUCTURE DELIVERY PLAN: CONTENTS<br />

Sustainable Energy ·································································································· 55<br />

Water ······················································································································· 56<br />

Sewerage ················································································································· 58<br />

Electricity Supply ····································································································· 59<br />

Regeneration of New Addington ············································································· 60<br />

East Croydon Masterplan ························································································ 61<br />

West Croydon Masterplan ······················································································· 62<br />

Fairfield Masterplan ································································································ 63<br />

Mid-Croydon Masterplan ························································································ 64<br />

Old Town Masterplan ······························································································ 65<br />

Connected Croydon ································································································· 66<br />

Croydon Arena ········································································································· 68<br />

Sports and Leisure Facilities ···················································································· 69<br />

London Fire Brigade Facilities ················································································· 81<br />

3. Schedule<br />

Enterprising City Schedule ························································································ 82<br />

Learning City Schedule ····························································································· 83<br />

Creative City Schedule ····························································································· 84<br />

Connected City Schedule ·························································································· 85<br />

Sustainable City Schedule ························································································ 88<br />

Caring City Schedule ································································································· 93<br />

Critical Provision Schedule ······················································································· 95<br />

Necessary Provision Schedule ················································································· 99<br />

Contributory Provision Schedule ············································································ 103<br />

Schedule by Location– 16 Places of Croydon ························································· 105<br />

Identified Costs ······································································································· 116<br />

Sports and Swimming Facilities (Academies) ·························································· 70<br />

2.6 Caring City Programme<br />

Woodside Health Centre ························································································· 72<br />

New Addington Health Centre ················································································· 73<br />

Croydon University Hospital ···················································································· 74<br />

Purley Hospital ········································································································· 75<br />

Burial Ground ·········································································································· 76<br />

Supported Housing Facilities ·················································································· 77<br />

Metropolitan Police Facilities ················································································· 78<br />

Ambulance Service Facilities ···················································································· 80<br />

3


INFRASTRUCTURE DELIVERY PLAN: INTRODUCTION<br />

Introduction<br />

The Croydon Infrastructure Delivery Plan (IDP) commenced in October 2009.<br />

Subsequently, it has been updated as a live document on several occasions to<br />

support the Croydon Local Plan: Strategic Policies and the Corporation Capital<br />

Programme development. More recently, the IDP has been integral to informing<br />

the role and functions of the Infrastructure Finance Group (IFG).<br />

It was originally produced in response to PPS12 which advised the IDP to identify<br />

the <strong>infrastructure</strong> needs and costs, phasing and funding sources and<br />

responsibilities for <strong>delivery</strong> of the <strong>infrastructure</strong> necessary to support the<br />

development growth outlined in the Local Plan. The National Planning Policy<br />

Framework (NPPF) replaced PPS12 in March 2012 - and continues to emphasise<br />

that planning should be a creative exercise “proactively driving and supporting<br />

sustainable economic development”. It foresees the need to remove potential<br />

barriers to development, including the lack of <strong>infrastructure</strong>. Paragraph 162 of the<br />

NPFF states that Local Planning Authorities should work with other authorities and<br />

providers to assess the quality and capacity of <strong>infrastructure</strong> for transport, water<br />

supply, wastewater and its treatment, energy, telecommunications, utilities, waste,<br />

health, social care, education, flood risk and coastal change management, and its<br />

ability to meet forecast demands. Local Planning Authorities should also take<br />

account of the need for strategic <strong>infrastructure</strong>, including nationally significant<br />

<strong>infrastructure</strong>, within their areas.<br />

This iteration of the IDP is in the form of a partial update to the March 2012 IDP.<br />

regarding Croydon’s <strong>infrastructure</strong> status, needs, costs and phasing and as an aid to<br />

coordinating <strong>infrastructure</strong> <strong>delivery</strong>. The mention of a project in the Infrastructure<br />

Delivery Plan is seen as a pre-requisite to prioritisation of <strong>infrastructure</strong> projects by<br />

the Council and third parties.<br />

Finally, it will inform the role and functions of the Infrastructure Finance Group in<br />

prioritising and determining bids for Section 106 monies and Community<br />

Infrastructure Levy (CIL) income.<br />

Purpose<br />

This document does not represent a full update of the IDP. Its purpose is to provide<br />

an update to the ‘Infrastructure Delivery Schedule’ set out in the March 2012 IDP.<br />

As such it provides on-going support to the Croydon Local Plan - both the Strategic<br />

Policies and the Detailed Policies and Proposals Development Plan Documents<br />

(DPD), providing the evidence on social, physical and green <strong>infrastructure</strong> required<br />

to support the <strong>delivery</strong> of the Plan. An up to date, robust and credible IDP is a vital<br />

supporting document to ensure DPD soundness.<br />

It also assists the Council in maintaining as up to date information as possible<br />

Infrastructure Delivery Plan March 2012<br />

4


INFRASTRUCTURE DELIVERY PLAN: COMPLETED PROJECTS<br />

Provision<br />

Lead<br />

Partner<br />

Delivery Partners/<br />

Stakeholders<br />

Delivery Mechanisms/<br />

Funding Source<br />

Cost (if known) Location 2011-<br />

2015<br />

2016<br />

-<br />

2020<br />

2021- Relationship to CLP Strategic Policies:<br />

(3) Critical, (2) Necessary, (1)<br />

Contributory<br />

University Centre Croydon<br />

Croydon<br />

College<br />

LBC, GLA, HE Partner,<br />

Croydon College<br />

TBC<br />

Croydon<br />

Opportunity Area<br />

Y<br />

3<br />

East Croydon Station: Provision of 2nd<br />

access bridge, improved concourse and<br />

platform congestion improvements<br />

Network Rail LBC, Network Rail, private<br />

sector<br />

£6m from LBC Capital Budget<br />

2011/12–2015/16<br />

£20m COA Y<br />

3<br />

West Croydon Station: improved<br />

interchange 2nd station entrance<br />

Network Rail TfL, Network Rail, adjacent<br />

landowners<br />

TfL, Network Rail, adjacent<br />

landowners<br />

£15m COA Y<br />

2<br />

Walking and Cycling on Greenways:<br />

Greenway sections 1-9 have been<br />

completed.<br />

LBC TfL, PCT, Sustrans TfL, LBC Capital Programme,<br />

S106<br />

TBC Borough-wide Y<br />

2<br />

Road Network: 12 public electric vehicle<br />

charging points installed.<br />

TBC<br />

Tramlink: Line 4 between Elmers End<br />

and Therapia Lane introduced, with 6<br />

additional trams<br />

TfL LBC, TfL TfL, LBC, CIL TBC Borough-wide Y<br />

3<br />

Legible London LBC LBC, The Greater London<br />

Authority, TfL<br />

Croydon Capital Programme,<br />

TfL Local Implementation Plan<br />

£531,207 COA and District<br />

Centres<br />

Y Y Y<br />

1<br />

Parks to be Proud of: Improvements of<br />

Croydon’s parks and green spaces<br />

Play Areas: improvements at Thornton<br />

Heath Recreation Ground, Wandle Park,<br />

Milne Park and Addington Vale, Westow<br />

Park<br />

LBC LBC, GLA LBC, GLA £1.5m 9 specific locations,<br />

borough-wide<br />

LBC LBC, DCSF DCSF, LBC Capital<br />

Programme, S106, HLF and<br />

other funding streams<br />

£2.4m Borough-wide Y Y<br />

Public realm improvements: Purley LBC LBC, TfL TfL £2,333,914 Purley Y<br />

3<br />

Y<br />

2<br />

2<br />

Public realm improvements: New<br />

Addington Phase 1<br />

Public realm improvements:<br />

Addiscombe<br />

LBC LBC, GLA, TfL GLA, TfL £696,869 New Addington Y<br />

LBC TfL TfL, LBC £1,583,177 Addiscombe Y<br />

3<br />

3<br />

5


INFRASTRUCTURE DELIVERY PLAN: COMPLETED PROJECTS<br />

Provision<br />

Lead<br />

Partner<br />

Delivery Partners/<br />

Stakeholders<br />

Delivery Mechanisms/<br />

Funding Source<br />

Cost (if known) Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to CLP Strategic Policies:<br />

(3) Critical, (2) Necessary, (1)<br />

Contributory<br />

Public realm improvements: Wandle<br />

Park<br />

LBC<br />

LBC, S106 receipts,<br />

Heritage Lottery Fund, GLA,<br />

Environment Agency<br />

£3,839,00 Croydon<br />

Opportunity Area<br />

Y<br />

3<br />

Access to Nature: improvements and<br />

works at Addiscombe Railway Park,<br />

Wandle Park and Waddon Ponds<br />

GLA LBC, Mayor of London Mayor of London, LDA TBC Borough-wide Y Y Y<br />

1<br />

New “wet and dry” leisure centre LBC LBC LBC Capital Budget (£3.5m) £13m Waddon Y<br />

3<br />

Water: Phase 2 of upgrade of<br />

treatment works at Bough Beech<br />

completed<br />

Sutton and<br />

East Surrey<br />

Water<br />

LBC Highways, TfL<br />

Thames Water Asset<br />

Management Plan and<br />

funding<br />

TBC Borough-wide Y<br />

2<br />

NHS Croydon Capital Programme:<br />

Redevelopment and refurbishment of<br />

NHS<br />

Croydon<br />

NHS Croydon, LBC,<br />

Healthcare for London<br />

LIFT, planning obligations,<br />

DoH NHS allocations<br />

£11m Purley Hospital Y<br />

3<br />

Total value of projects completed (where costs identified) since March 2012 IDP: £71.88m<br />

6


ENTERPRISING CITY PROGRAMME<br />

7


ENTERPRISING CITY PROGRAMME: DIGITAL INFRASTRUCTURE NETWORK<br />

What?<br />

Wi-Fi / Broadband enhancement<br />

Where?<br />

The initial focus will be on Croydon Opportunity Area, with improvements sought<br />

across the whole borough.<br />

When?<br />

By 2015<br />

Why?<br />

A modern, reliable, high quality digital <strong>infrastructure</strong> would dramatically enhance<br />

Croydon’s reputation and capability as a location for business, and improve its<br />

competitive advantage. Policy SP8.5 from the Croydon Local Plan: Strategic Policies<br />

outlines the Council’s support to improving the borough’s Wi-Fi, fibre optic<br />

broadband and mobile broadband. The provision also accords with the Council’s<br />

Economic Strategy Refresh.<br />

Stakeholder Engagement Since March 2012:<br />

Members of Croydon’s Economic Development team have met with representatives<br />

of the Croydon Tech City network to discuss key issues surrounding digital<br />

connectivity faced by SMEs in Croydon, and potential solutions to enhance the<br />

<strong>infrastructure</strong> and take up.<br />

Progress Since March 2012:<br />

Members of Croydon’s Economic Development team have met with relevant<br />

officers from the GLA to discuss digital connectivity for the Town and District<br />

centres and other business locations across the borough. A Digital Strategy is being<br />

developed, and as a result, Croydon will be one of the 6 ‘phase 1’ projects across<br />

London to offer broadband connectivity vouchers of up to £3,000 to local<br />

businesses (this will run from November 2013 to March 2014). The Council has<br />

recently commissioned a piece of work to determine digital <strong>infrastructure</strong> coverage<br />

within the Opportunity Area Planning Framework area.<br />

Risks:<br />

The scope of this piece of <strong>infrastructure</strong> is not quantified so there is a risk<br />

that stakeholder expectations may differ.<br />

May not be delivered by 2015.<br />

Mitigation:<br />

<br />

<br />

Delivery partners and stakeholders need to quantify what represents ‘Wi-Fi’/<br />

Broadband Enhancement.<br />

Work collaboratively with GLA and BDUK to ensure Croydon benefits most<br />

before March 2015.<br />

Planned Provision<br />

Lead<br />

Partner<br />

Delivery Partners/Stakeholders<br />

Delivery<br />

Mechanism/<br />

Funding Source<br />

Cost (if<br />

known)<br />

Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to CLP Strategic<br />

Policies: (3) Critical, (2)<br />

Necessary, (1) Contributory<br />

Wi-Fi/ Broadband enhancement LBC LB Croydon, GLA, BT, CCURV,<br />

Croydon BID, Croydon College<br />

LBC Capital<br />

Programme<br />

£1.9<br />

million<br />

COA and<br />

then<br />

across the<br />

whole<br />

borough<br />

Y<br />

3<br />

8


ENTERPRISING CITY PROGRAMME: ENTERPRISE CENTRES FOR CREATIVE AND CULTURAL INDUSTRIES<br />

What?<br />

Delivery of Creative and Cultural Industries Enterprise Centres at 4 locations across<br />

Croydon with the one in Croydon Metropolitan Centre (CMC) to act as a flagship.<br />

Where?<br />

CMC, Crystal Palace, Portland Road/South Norwood District Centre and Purley.<br />

When?<br />

By 2015 for CMC and by 2021 for the other 3 centres.<br />

Why?<br />

The vision from Croydon’s Sustainable Community Strategy states ‘We will be<br />

London’s most enterprising borough – a city that fosters ideas, innovation and<br />

learning and provides skills, opportunity and a sense of belonging for all’. A network<br />

of Enterprise Centres focusing on cultural and creative industries and innovation will<br />

be pursued across the borough as part of realising this vision.<br />

Stakeholder Engagement Since March 2012:<br />

The Council’s Plan Making team has had discussions with a number of potential<br />

providers in addition to the <strong>delivery</strong> partners and stakeholders already identified.<br />

expand its offer in ways that make it the natural centre for this area. The Council is<br />

working closely with the Stanley People’s Initiative to explore the scope for Stanley<br />

Halls to act as the centre for the South Norwood area and continues to work with<br />

the land owners in Purley to identify a suitable site for this part of the borough.<br />

Risks:<br />

<br />

If the full complement of centres is not established by 2021, the increased<br />

diversity of the local economy and associated benefits will not be realised.<br />

Mitigation:<br />

<br />

The Council’s Plan Making Team will continue to work with a number of<br />

potential providers for CMC and Purley where a specific site has not yet been<br />

identified.<br />

Progress Since March 2012:<br />

Following detailed consideration of numerous potential centres for CMC, three<br />

options are being progressed further. Antenna Studios in Crystal Palace continues to<br />

Matthew’s Yard has emerged as a valued asset for CMC. The idea of using the empty commercial<br />

space in neighbouring Exchange Square to support their activities is one option being considered.<br />

Planned Provision<br />

Lead<br />

Partner<br />

Delivery Partners/Stakeholders<br />

Delivery Mechanism/Funding<br />

Source<br />

Cost (if<br />

known)<br />

Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to CLP Strategic<br />

Policies: (3) Critical, (2) Necessary,<br />

(1) Contributory<br />

Enterprise centres for<br />

creative and cultural<br />

industries<br />

LBC<br />

LBC, ACAVA, CCURV, ACME,<br />

Croydon College<br />

LBC Capital<br />

Programme,<br />

S106, CIL<br />

TBC<br />

CMC, Crystal Palace, Portland Road/<br />

South, Norwood and Purley<br />

Y<br />

Y<br />

2<br />

9


ENTERPRISING CITY PROGRAMME: MAKING BETTER USE OF VACANT COMMERCIAL SPACE<br />

What?<br />

Working to bring vacant commercial and retail premises into productive use<br />

through:<br />

Creative and Cultural Industries<br />

Urban greening projects<br />

Urban agriculture<br />

Community groups<br />

Where?<br />

Borough-wide<br />

When?<br />

On-going<br />

Why?<br />

Across Croydon, but particularly within Croydon Metropolitan Centre, there are<br />

substantial amounts of underused sites/buildings. This usually corresponds with<br />

sites that are pending development. The Council considers such sites lying dormant<br />

a potential opportunity. Organisations within this sector such as ACAVA (Association<br />

for Cultural Advancement through Visual Art) and ACME (providing artists with<br />

affordable studio and living space) are experts at making temporary use of such<br />

space.<br />

Stakeholder Engagement Since March 2012:<br />

Members of Croydon’s Economic Development Team have met with a number of<br />

stakeholders including Develop Croydon and London and Partners to explore the<br />

possibility of delivering a number of innovative ideas, such as business touch down<br />

space in the CMC. Another concept is to explore a meanwhile use for a theatre<br />

company that has expressed an interest.<br />

Progress Since March 2012:<br />

The touch down space is being developed. Information of potential locations have<br />

been provided and the company has been invited to do a site visit. A pop-up shop<br />

has been established in Old Town with a second in planning.<br />

Risks:<br />

<br />

<br />

<br />

Not being able to secure suitable premises for the touchdown space.<br />

Not being able to secure <strong>delivery</strong> partner to manage it.<br />

Not enough interest in<br />

meanwhile use.<br />

Mitigation:<br />

<br />

<br />

<br />

Increase scope of search across<br />

CMC.<br />

Early engagement with potential<br />

<strong>delivery</strong> partners.<br />

Publicise meanwhile use across<br />

London.<br />

Empty shop unit in central Croydon<br />

Planned Provision<br />

Lead<br />

Partner<br />

Delivery Partners/Stakeholders<br />

Delivery Mechanism/Funding<br />

Source<br />

Cost (if<br />

known)<br />

Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to CLP Strategic<br />

Policies: (3) Critical, (2) Necessary,<br />

(1) Contributory<br />

Bringing vacant commercial and retail premises<br />

into productive use.<br />

LBC<br />

LBC, ACAVA, Village Underground,<br />

Meanwhile Space CIC<br />

LBC Capital<br />

funding,<br />

S106, CIL<br />

TBC<br />

Boroughwide<br />

Y Y Y<br />

2<br />

10


LEARNING CITY PROGRAMME<br />

11


LEARNING CITY PROGRAMME: PRIMARY SCHOOLS BUILDING PROGRAMME<br />

What?<br />

Primary Schools Building Programme<br />

Where?<br />

Borough-wide<br />

When?<br />

By 2015<br />

Why?<br />

Local Authorities are advised to maintain approximately 5% surplus places to<br />

accommodate in-year movement of families in and out of the borough. There is<br />

currently a shortfall of 25 forms of entry (FE) in primary schools between 2013 and<br />

2018 on a medium growth scenario and a shortfall of 35FE on a high growth<br />

scenario. The demand for primary school places will remain at its most intense in<br />

the north west and the centre of the borough. From 2015 onwards, the pattern of<br />

demand will shift in line with housing and regeneration projects within the strategic<br />

plan. Demand will become more intense in Coulsdon and the centre of Croydon. A<br />

major housing development is to take place in the West Coulsdon ward at Cane Hill,<br />

with the new total demand for school places between 2015-16 and 2017-18<br />

education years being estimated at 151 places in the primary phase.<br />

Stakeholder Engagement Since March 2012:<br />

The January 2013 Cabinet report agreed for a series of consultations on school<br />

expansions and new schools to take place, as well as a call for providers to express<br />

an interest in running the new schools.<br />

Howard Primary — one of the borough’s schools set for expansion<br />

Progress Since March 2012:<br />

Planning pre-applications have been submitted for the new schools at the<br />

Westways Centre, Aberdeen Road, West Thornton Primary Academy and Kingsley<br />

Primary. A feasibility study has been completed for Ryelands Primary School and a<br />

feasibility study has been instructed from the architect for St Joseph’s Catholic<br />

Infants School.<br />

12


LEARNING CITY PROGRAMME: PRIMARY SCHOOLS BUILDING PROGRAMME<br />

Planned Provision Lead Partner Delivery<br />

Delivery<br />

Cost (if known) Location 2011-<br />

2016-<br />

2021- Relationship to<br />

Partners/<br />

Mechanism/<br />

2015<br />

2020<br />

CLP Strategic<br />

Stakeholders<br />

Funding Source<br />

Policies: (3)<br />

Critical, (2)<br />

Necessary, (1)<br />

Contributory<br />

New school at Westways<br />

Centre (3FE)<br />

LBC, CFL LBC Education<br />

Estates Strategy<br />

TBC<br />

Broad Green and<br />

Selhurst<br />

Y<br />

3<br />

New school at Aberdeen<br />

Road (2FE)<br />

LBC, CFL LBC Education<br />

Estates Strategy<br />

TBC<br />

Croydon Opportunity<br />

Area<br />

Y<br />

3<br />

Ryelands Primary School–<br />

relocation of existing school<br />

(2FE)<br />

LBC, CFL LBC Education<br />

Estates Strategy<br />

TBC<br />

South Norwood and<br />

Woodside<br />

Y<br />

3<br />

West Thornton Primary<br />

Academy– new annexe<br />

(2FE)<br />

LBC, CFL LBC Education<br />

Estates Strategy<br />

TBC<br />

Broad Green and<br />

Selhurst<br />

Y<br />

3<br />

St Joseph’s Catholic Infants<br />

and Juniors (1FE)<br />

LBC, CFL LBC Education<br />

Estates Strategy<br />

TBC<br />

Crystal Palace and<br />

Upper Norwood<br />

Y<br />

3<br />

Ark Oval– expansion (1FE) LBC, CFL LBC Education<br />

Estates Strategy<br />

TBC Addiscombe Y<br />

3<br />

Kingsley Primary–<br />

expansion (1FE)<br />

LBC, CFL LBC Education<br />

Estates Strategy<br />

TBC<br />

Broad Green and<br />

Selhurst<br />

Y<br />

3<br />

13


LEARNING CITY PROGRAMME: SECONDARY SCHOOLS BUILDING PROGRAMME<br />

What?<br />

Development of secondary school at Croydon Arena<br />

Where?<br />

South Norwood and Woodside<br />

When?<br />

August 2015<br />

Why?<br />

Demand for places are projected to increase, and projections indicate that demand<br />

for a further 10FE will be needed from 2015. This growth is concentrated in the<br />

north and central parts of the borough.. A major housing development is to take<br />

place in the West Coulsdon ward at Cane Hill, with the new total demand for school<br />

places between 2015-16 and 2017-18 education years being estimated at 72 in the<br />

secondary phase.<br />

Stakeholder Engagement Since March 2012:<br />

The consultation period took place between 6th February to 28th March 2013, with<br />

an additional public meeting also taking place. In addition to these public meetings,<br />

officers met with key sports provider to understand their requirements from the<br />

project and gain their input.<br />

Progress Since March 2012:<br />

Feasibility study due to be complete in October 2013.<br />

Risks:<br />

<br />

<br />

<br />

This project is dependant on the relocation of Ryelands primary school as the<br />

utilisation of the existing Ryelands building would allow education provision<br />

to continue as planned.<br />

There is also issues regarding opposition of the respondents of the public<br />

consultation, as concerns were raised over the perceived impact on residents,<br />

traffic congestion and people movement.<br />

Issues were also raised regarding the encroachment onto the Metropolitan<br />

Open Land.<br />

Mitigation:<br />

<br />

Croydon Council is commissioning a full traffic impact study to identify how<br />

best to minimise the impact of any increased traffic movements.<br />

Planned Provision<br />

Lead<br />

Partner<br />

Delivery Partners/Stakeholders<br />

Delivery Mechanism/Funding<br />

Source<br />

Cost (if<br />

known)<br />

Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to CLP Strategic<br />

Policies: (3) Critical, (2) Necessary,<br />

(1) Contributory<br />

Croydon Arena- (6FE) LBC CFL Education Estates Strategy TBC £29.3m South<br />

Norwood<br />

and<br />

Woodside<br />

14<br />

Y<br />

3


LEARNING CITY PROGRAMME: SPECIAL SCHOOLS BUILDING PROGRAMME<br />

What?<br />

Provision of a new school and expansion of resource bases.<br />

Where?<br />

Borough-wide<br />

children and young people with mental health needs, attention deficit hyperactivity<br />

disorder or challenging behaviour with disabilities. Croydon requires a new flexible<br />

approach by our specialist provision in meeting a broad range of need around SEN;<br />

this means flexibility around numbers to be admitted to any particular provision,<br />

better joint multi-agency working in finding solutions to the provision of education<br />

and care and more responsive services to meeting needs.<br />

When?<br />

By 2015<br />

Why?<br />

The incidence of children and young people with special educational needs is on the<br />

increase both locally and nationally. Croydon’s Joint Strategic Needs Assessment<br />

identifies the need to increase capacity to support children and young people with,<br />

Autistic Spectrum Disorders (ASD), Behavioural, Emotional and Social Difficulties<br />

(BESD), Complex Needs, Profound and Multiple Learning Difficulties (PMLD), Speech,<br />

Language and Communication Needs (SLCN) and Severe Learning Difficulties (SLD).<br />

There is also the challenge of meeting the needs of an increasing incidence of<br />

Stakeholder Engagement Since March 2012:<br />

Consultation will take place on establishing a resource base at Courtwood Primary<br />

School.<br />

Progress Since March 2012:<br />

An architect has been instructed to help SEN and inclusion team to develop a<br />

scheme for a new school. At Cabinet in June 2013, delegation was given to the<br />

Lead Member to proceed with the consultation on establishing a resource base for<br />

pupils with Asperger's syndrome at Courtwood Primary School for September 2014.<br />

Planned Provision Lead Partner Delivery<br />

Partners/<br />

Stakeholders<br />

Delivery<br />

Mechanism/<br />

Funding Source<br />

Cost (if known) Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to CLP<br />

Strategic Policies: (3)<br />

Critical, (2) Necessary,<br />

(1) Contributory<br />

Expansion of Resource Base 1<br />

at Croydon Arena– 10 to 15<br />

places<br />

LBC, CFL LBC Education<br />

Estates Strategy<br />

TBC<br />

South Norwood<br />

and Woodside<br />

Y<br />

1<br />

Expansion of Resource Base 2<br />

at Croydon General Hospital<br />

site– 15 places<br />

LBC, CFL LBC Education<br />

Estates Strategy<br />

£780,000 Croydon<br />

Opportunity Area<br />

Y<br />

1<br />

Expansion of Resource Base 3-<br />

15 places<br />

LBC, CFL LBC Education<br />

Estates Strategy<br />

TBC TBC Y<br />

1<br />

New school at Tennison Road–<br />

50 places<br />

LBC, CFL LBC Education<br />

Estates Strategy<br />

£7m South Norwood<br />

and Woodside<br />

Y<br />

3<br />

15


LEARNING CITY PROGRAMME: UNIVERSITY CENTRE CROYDON<br />

What?<br />

A partnership approach will be adopted to forge links with the Higher Education<br />

sector with a view to attracting a university presence in the Borough. This will be<br />

progressed by Croydon College in partnership with the Council.<br />

Where?<br />

Croydon Opportunity Area<br />

When?<br />

On-going<br />

Why?<br />

As a key part of the vision for the COA area, and as an asset for South London, a<br />

new university presence is required. It would help innovation, stimulate the<br />

economy and give opportunity to raise skills levels to degree level over a wider<br />

range of disciplines and raise the profile of Croydon.<br />

Progress Since March 2012:<br />

As well as the opening of the University<br />

Centre Croydon, discussion is now on- going<br />

to develop higher (Masters) provision in the<br />

University Centre. The Council is working<br />

with Sussex University and the GLA to open<br />

an Innovation Centre in Croydon.<br />

Stakeholder Engagement Since March 2012:<br />

As agreed with the Council in 2011, the aim was rescoped to build upon an existing<br />

strong partnership with Sussex University and gain approval to use the title<br />

University Centre. University Centre Croydon was formally opened in April 2012 by<br />

the Mayor of London.<br />

University Centre Croydon<br />

Planned Provision<br />

Lead<br />

Partner<br />

Delivery Partners/Stakeholders<br />

Delivery<br />

Mechanism/<br />

Funding Source<br />

Cost (if<br />

known)<br />

Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to CLP Strategic<br />

Policies: (3) Critical, (2)<br />

Necessary, (1) Contributory<br />

Masters provision at the University Centre<br />

Partnership with Sussex University to open an Innovation<br />

Centre<br />

Croydon<br />

College<br />

Croydon<br />

College<br />

LBC, GLA, HE Partner, Croydon College TBC TBC Croydon<br />

Opportunity<br />

Area<br />

Croydon College, Sussex University, GLA TBC TBC Croydon<br />

Opportunity<br />

Area<br />

Y Y Y<br />

Y Y Y<br />

3<br />

3<br />

16


CREATIVE CITY PROGRAMME<br />

17


CREATIVE CITY PROGRAMME: FAIRFIELD HALLS<br />

What?<br />

Renewed and modernised Fairfield Halls complex to bring real quality and lasting<br />

benefits to the borough over the next 50 years.<br />

Where?<br />

Croydon Opportunity Area<br />

When?<br />

By early 2018<br />

Why?<br />

The Fairfield Halls have been Croydon’s principal cultural venue and community<br />

meeting place for almost 50 years. It hosts a range of local, regional and national<br />

events; concerts, plays, ballet, opera and pantomimes. The building is locally listed<br />

and a good example of post war civic architecture in the mould of the Royal Festival<br />

Hall. However parts of the building are in need of investment and nearing the end of<br />

their useful life. The inflexibility of the spaces makes the venue increasingly difficult<br />

for it to remain economically viable.<br />

Stakeholder Engagement Since March 2012:<br />

On-going engagement with Fairfield Halls in relation to the <strong>delivery</strong> of the project<br />

and the nature of the business following completion of the project. There has been<br />

further engagement with the business and local businesses and suppliers in the<br />

development of an Economic Impact Assessment in 2013.<br />

Progress Since March 2012:<br />

The Client Requirements for the project have been agreed, along with Cabinet<br />

endorsement for the enhanced scheme. There has been New Audio equipment in<br />

the Concert Hall and upgrades in Aschroft theatre and Amhem Gallery. Business<br />

critical items have been addressed.<br />

Risks:<br />

<br />

<br />

<br />

Funding will be withdrawn– the project will stall again and Fairfield Halls will<br />

struggle to operate.<br />

Project not delivered to specification and client requirements.<br />

Project goes over budget, impacting the council capital programme and other<br />

capital schemes.<br />

Mitigation:<br />

<br />

<br />

Move project forward as approved to create momentum and confidence.<br />

Clear scope and specification and tight project management. Appointment of<br />

professional project design team.<br />

Robust scope and specification and project management/change<br />

management processes and early appointments.<br />

Fairfield Halls<br />

Planned Provision<br />

Lead<br />

Partner<br />

Delivery Partners/Stakeholders<br />

Delivery<br />

Mechanism/<br />

Funding Source<br />

Cost (if<br />

known)<br />

Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to CLP Strategic<br />

Policies: (3) Critical, (2)<br />

Necessary, (1) Contributory<br />

Renewed Fairfield Halls complex LBC LBC, Fairfield Halls LBC Capital<br />

Budget<br />

2011/12-<br />

2017/18<br />

£33.7m<br />

Croydon<br />

Opportunity<br />

Area<br />

Y<br />

Y<br />

3<br />

18


CREATIVE CITY PROGRAMME: LIBRARIES MODERNISATION PROGRAMME<br />

What?<br />

Libraries Modernisation Programme<br />

Where?<br />

Borough-wide<br />

When?<br />

On going<br />

Why?<br />

Although the library service has a high level of customer satisfaction and is highly<br />

valued by its users and the general public, adult usage is in decline. The current<br />

library <strong>infrastructure</strong> needs updating in order to meet the needs of a modern service<br />

and the service offer needs to change and expand to meet changing<br />

demands. Changes in population driven by the interrelated factors of migration,<br />

birth rates, housing numbers and housing occupancy will generate their own<br />

requirements for the future. Additionally, with changes to work patterns such as<br />

extended working hours, libraries will have to transform the way they deliver their<br />

service.<br />

involving the introduction of new technology for the benefit of both staff and<br />

customers. This will include self-service, Wi-Fi and the very latest innovations in<br />

online resources and e-books.<br />

CIS will work closely with local communities to improve the way library services are<br />

delivered. There will also be new local business opportunities and good prospects<br />

for employment, volunteering and apprenticeships.<br />

Risks:<br />

<br />

The rationale set out for this project is based upon the evidence from the<br />

Council’s library service. However, the service is now managed by CIS who<br />

may identify a different approach and priorities for investment.<br />

Mitigation:<br />

<br />

Continue to regularly monitor the project to ensure consistency between the<br />

priorities of the library service and the Infrastructure Delivery Plan.<br />

Stakeholder Engagement Since March 2012:<br />

The Council has considered a number of mechanisms to safeguard the borough’s<br />

libraries in challenging economic times.<br />

Progress Since March 2012:<br />

The future of the borough's libraries is assured with the signing of an eight-year<br />

contract by Croydon Council and John Laing Integrated Services (JLIS), now Carillion<br />

Integrated Services (CIS). The new arrangements started on 1 October 2013, when<br />

CIS took over the running of the service. It represents good value for taxpayers as it<br />

will save the authority significant amounts of money, and at the same time ensure<br />

all of the council's 13 libraries remain open and face no reductions in opening hours.<br />

The contract will see the service undergo a major modernisation programme,<br />

Croydon’s Central Library<br />

19


CONNECTED CITY PROGRAMME<br />

20


CONNECTED CITY PROGRAMME: EAST CROYDON STATION<br />

What?<br />

Provision of 2 nd access bridge, additional platforms and other improvements.<br />

Where?<br />

East Croydon Station<br />

When?<br />

By 2020<br />

2013. Station concourse works have been completed with new accessible ticket<br />

windows in the booking office and a new gateline behind Costa Coffee.<br />

Risks:<br />

<br />

Two new platforms are being looked at for <strong>delivery</strong> in the early 2020s but<br />

would require extensive remodelling of current Platforms 1&2– this is subject<br />

to further funding and development.<br />

Mitigation:<br />

<br />

Early development of Brighton Mainline Capacity Improvement Scheme will<br />

help to deliver the extra platforms in early Control Period 6 (2019-2024).<br />

Why?<br />

A fundamental principle is to make best use of the extensive railway system in the<br />

borough and to invest in its long term future. Action is required both in the long and<br />

short terms to increase the capacity of Croydon’s two principal stations: East and<br />

West Croydon. East Croydon needs to be re-configured to provide a second access<br />

bridge, enlarge space in the concourse for passenger circulation and subsequently<br />

to provide at least two more platforms.<br />

Stakeholder Engagement Since March 2012:<br />

Regular meetings are held with the London Borough of Croydon and Network Rail’s<br />

Sussex Route and London and South East Strategic Planning teams.<br />

Progress Since March 2012:<br />

The new footbridge has been installed and opened for cross-platform interchange.<br />

A new exit, on the Dingwall Road-side of the station, is due to be opened in late<br />

Newly opened access from East Croydon Station to Lansdowne Road<br />

Planned Provision Lead Partner Delivery Partners/<br />

Stakeholders<br />

Delivery<br />

Mechanism/<br />

Funding Source<br />

Cost (if known) Location 2011-<br />

2015<br />

Additional platforms Network Rail Network Rail £80m COA Y Y<br />

21<br />

2016-<br />

2020<br />

2021- Relationship to CLP<br />

Strategic Policies:<br />

(3) Critical, (2)<br />

Necessary, (1)<br />

Contributory<br />

2


CONNECTED CITY PROGRAMME: WEST CROYDON STATION<br />

What?<br />

Improved interchange - 2nd station entrance<br />

Where?<br />

West Croydon Station<br />

When?<br />

By 2020<br />

Why?<br />

A fundamental principle is to make best use of the extensive railway system in the<br />

borough and to invest in its long term future. Action is required both in the long<br />

and short terms to increase the capacity of Croydon’s two principal stations: East<br />

and West Croydon. At West Croydon the need is to improve interchange between<br />

rail and all other forms of transport and to improve passenger access whilst<br />

regenerating the surrounding area and public realm.<br />

Stakeholder Engagement Since March 2012:<br />

Regular meetings are held with the London Borough of Croydon and Network Rail’s<br />

Sussex Route and London and South East Strategic Planning teams.<br />

Progress Since March 2012:<br />

Second entrance has been opened but further work is required to make the station<br />

accessible for all.<br />

Risks:<br />

<br />

The station is unable to cope with the increase in passenger numbers as a<br />

result of improvements to Central Croydon’s retail offer.<br />

Mitigation:<br />

<br />

Network Rail is looking to work with London Overground (the station<br />

operator), Westfield and Hammerson, and Croydon Council to plan future<br />

improvements.<br />

22


CONNECTED CITY PROGRAMME: STATION IMPROVEMENT PROGRAMME<br />

What?<br />

Improvement of stations<br />

Where?<br />

Selhurst, Sanderstead, Norwood Junction and other stations.<br />

When?<br />

By 2020<br />

Why?<br />

Many stations in the borough, including Croydon’s principal stations Selhurst,<br />

Sanderstead and Norwood Junction, need improvements in access including that<br />

for the disabled, and more secure and better signed way marking.<br />

Stakeholder Engagement Since March 2012:<br />

No update available for this project.<br />

Progress Since March 2012:<br />

No update available for this project.<br />

Planned Provision<br />

Lead<br />

Partner<br />

Delivery Partners/Stakeholders<br />

Delivery Mechanism/Funding<br />

Source<br />

Cost (if<br />

known)<br />

Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to CLP Strategic<br />

Policies: (3) Critical, (2) Necessary,<br />

(1) Contributory<br />

Improvement of Selhurst, Sanderstead and<br />

other stations<br />

Network<br />

Rail<br />

TfL<br />

Network Rail/<br />

TfL, LBC<br />

£400k Boroughwide<br />

Y<br />

Y<br />

1<br />

23


CONNECTED CITY PROGRAMME: RAIL CAPACITY INCREASES<br />

What?<br />

<br />

<br />

<br />

12 coach trains on central London - Brighton line<br />

More frequent services, or more capacity on existing services<br />

Railtrack junction improvements and by-passes<br />

Where?<br />

Borough-wide<br />

When?<br />

As indicated in the table below<br />

Why?<br />

During this period 2011-2016 the capacity of the mainline Central London to<br />

Brighton railway through East Croydon will be increased by the introduction of the<br />

first phase of new Thameslink trains. Additional 12 coach trains will be introduced<br />

and timetabled as from December 2012. These measures will relieve overcrowding<br />

but will not fully resolve the problem at peak times. Further measures will be<br />

needed in the longer term.<br />

In the medium term, the capacity of the rail network needs to be enlarged further<br />

through more frequent trains including Thameslink. The government announced the<br />

approval of the full Thameslink programme of investment in November 2010 for<br />

completion in 2018. This enhancement is also necessary to retain convenient and<br />

reliable linkage to the City, Docklands and Gatwick.<br />

East Croydon Station<br />

Progress Since March 2012:<br />

No update available for this project.<br />

24


CONNECTED CITY PROGRAMME RAIL CAPACITY INCREASES<br />

Planned Provision Lead Partner Delivery<br />

Delivery<br />

Cost (if known) Location 2011-<br />

2016-<br />

2021- Relationship to<br />

Partners/<br />

Mechanism/<br />

2015<br />

2020<br />

CLP Strategic<br />

Stakeholders<br />

Funding Source<br />

Policies: (3)<br />

Critical, (2)<br />

Necessary, (1)<br />

Contributory<br />

12 coach trains on Central<br />

London– Brighton line<br />

Thames-link/<br />

Southern<br />

Railway<br />

Network Rail,<br />

Thameslink<br />

Thameslink<br />

Investment<br />

Programme<br />

TBC Borough-wide Y<br />

2<br />

More frequent services, or<br />

more capacity on existing<br />

services<br />

Thames-link/<br />

Southern<br />

Railway<br />

Network Rail,<br />

Thameslink<br />

Thameslink<br />

Investment<br />

Programme<br />

Current best estimates: up to £1bn Borough-wide Y Y<br />

2<br />

Strategic<br />

Business Plan,<br />

London and<br />

South East Rail<br />

Utilisation<br />

Study,<br />

Operational<br />

Business Plans<br />

Railtrack junction<br />

improvements and bypasses<br />

Thames-link/<br />

Southern<br />

Railway<br />

Network Rail,<br />

Thameslink<br />

Thameslink<br />

Investment<br />

Programme<br />

Current best estimates: up to £1bn Borough-wide Y Y<br />

2<br />

Strategic<br />

Business Plan,<br />

London and<br />

South East Rail<br />

Utilisation<br />

Study,<br />

Operational<br />

Business Plans<br />

25


CONNECTED CITY PROGRAMME: TRAMLINK<br />

What?<br />

<br />

<br />

<br />

Infrastructure improvements will be implemented to allow the increased<br />

service level and increase resilience; this includes an additional platform at<br />

Wimbledon and twin tracking between Beddington Lane and Mitcham<br />

Junction.<br />

4 additional trams have been ordered to arrive in early 2016. This will allow<br />

the Line 4 service (Elmers End to Therapia Lane) to be extended to<br />

Wimbledon.<br />

The tram stop on George Street will be relocated and increased in capacity as<br />

part of the town centre improvements.<br />

in June 2012, reducing severe tram overcrowding in the Arena to Sandilands area.<br />

This was undertaken by introducing six additional trams and a number of<br />

<strong>infrastructure</strong> modifications which has resulted in the number of trams using the<br />

Croydon Loop increasing from 18 trams per hour to 22.<br />

Risks:<br />

<br />

<br />

Changes within Wimbledon Station need to be approved by Network Rail and<br />

the Train Operating Companies which could affect cost and programme.<br />

The significant amount of <strong>infrastructure</strong> works currently being undertaken<br />

may result in a lack of industry interest in undertaking these works.<br />

Where?<br />

North of the borough<br />

When?<br />

Feburary 2015: Additional platform at Wimbledon and additional twin tracking<br />

handed over into operation.<br />

Feburary 2016: Extended Line 4 timetable to be introduced.<br />

Mitigation:<br />

<br />

<br />

Working closely with NR and SWT to agree changes at the Wimbledon station<br />

and to define ways of working during construction.<br />

Early contractor engagement, currently out to tender for <strong>infrastructure</strong><br />

package.<br />

Why?<br />

Croydon’s tram system, Tramlink, is owned and operated by TfL. It has proved<br />

highly successful and now reaches capacity at the peak hours over several stretches<br />

of the existing route; this will further increase capacity over this section by 50%.<br />

Stakeholder Engagement Since March 2012:<br />

A stakeholder event took place in October 2013 to launch the Wimbledon<br />

Enhancement scheme. On-going officer level discussions are held regularly to<br />

discuss specific technical issues. Engagement with South London Partnerships and<br />

local Resident Groups have taken place to raise awareness of Tramlink, the services<br />

operated and the upcoming works.<br />

Progress Since March 2012:<br />

Line 4, a 15 minute service between Elmers End and Therapia Lane was introduced<br />

26<br />

Existing Tramlink route to New Addington


CONNECTED CITY PROGRAMME: TRAMLINK<br />

Planned Provision Lead Partner Delivery<br />

Delivery<br />

Cost (if known) Location 2011-<br />

2016-<br />

2021- Relationship to<br />

Partners/<br />

Mechanism/<br />

2015<br />

2020<br />

CLP Strategic<br />

Stakeholders<br />

Funding Source<br />

Policies: (3)<br />

Critical, (2)<br />

Necessary, (1)<br />

Additional Rolling Stock (up<br />

to 4 units planned)<br />

TfL LBC, TfL TfL, LBC, CIL £20m N/A Y Y<br />

Tram stop improvements TfL LBC, TfL TfL, LBC, CIL £2.5m Borough-wide Y Y<br />

Track capacity<br />

TfL LBC, TfL TfL, LBC, CIL £2.5m Borough-wide Y<br />

improvements<br />

Dingwall Road Loop TfL LBC, TfL TfL, LBC, CIL £21m Croydon Opportunity<br />

Y<br />

Area<br />

Tramlink extensions to TfL LBC, TfL TfL, LBC, CIL £150m North Y Y<br />

Crystal Palace<br />

3<br />

2<br />

2<br />

2<br />

1<br />

27


CONNECTED CITY PROGRAMME: ROAD NETWORK<br />

What?<br />

<br />

<br />

<br />

<br />

<br />

Bridge strengthening on Network Rail bridges<br />

Providing a programme of anti-flood measures on highways<br />

Progressing smart traffic management/light coordination<br />

Minor highways improvements<br />

Electric Car Infrastructure<br />

Where?<br />

Borough-wide<br />

When?<br />

On-going<br />

Why?<br />

Future investment in Croydon’s road network will require careful judgement on two<br />

key issues:<br />

The apportionment of capital investment between maintaining and<br />

improving the existing asset and investing very selectively in new road<br />

capacity to ease bottlenecks.<br />

The apportionment of new capacity between different modes of transport.<br />

The enhancements required in Croydon to ease bottlenecks and make the whole<br />

existing network more efficient in handling flows require improvements at the<br />

junctions listed in the Transport Strategy. Other investments are required to<br />

achieve continuous improvement to road safety. Such a programme would in part<br />

draw upon Croydon’s Local Implementation Plan (LIP). Improvements to the road<br />

system and associated <strong>infrastructure</strong> can assist other elements of the Local Plan,<br />

reducing journey lengths, aiding pedestrian accessibility and fostering use of electric<br />

cars and other environmentally friendly transport.<br />

Stakeholder Engagement Since March 2012:<br />

<br />

<br />

Traffic Management: members, residents and residents associations.<br />

Electric car <strong>infrastructure</strong>: Where electric vehicle charging points have been<br />

installed as part of a wider scheme, such as Addiscombe Road, they are<br />

<br />

<br />

included in design and planning consultations.<br />

Bridge strengthening: Stakeholder engagement with members, local resident<br />

associations and residents, London Bridges Engineering Group (LoBEG), TfL,<br />

Tramlink and Network Rail.<br />

Anti-flood measures: Stakeholder engagement with Envrionment Agency,<br />

London Drainage Engineering Group, Thames Water, Purley Community Flood<br />

Group and Internal Flood Group.<br />

Progress Since March 2012:<br />

<br />

<br />

<br />

<br />

Risks:<br />

<br />

<br />

<br />

Traffic Management: Signal controlled pedestrian facilities have been<br />

introduced at Brighton Road/ Warham Road and at Chipstead Valley Road/<br />

Lion Green Road which aim to improve road safety. A number of zebra<br />

crossings have also been introduced across the borough to provide a safe<br />

place for pedestrians to cross the road and thus encourage walking as a<br />

sustainable and healthy travel choice.<br />

Electric Car Infrastructure: A dozen public electric vehicle charging points<br />

have been installed, mainly in council surface car parks. Plans are in place for<br />

a further 10-20 points in public sector staff car parks because of government<br />

grants and a long term commitment from manufacturers.<br />

Bridge strengthening: Bridge strengthening of Coombe Road Bridge<br />

completed. Croham Road refurbishment of three bridges. Goat House Bridge<br />

(Penge Road) strengthening currently in progress for completion by February<br />

2014. On-going talks with bridge strengthening for Spring Lane Bridge,<br />

Spurgeon’s and Windmill Bridges (St. James Road) for 2014-17. New road<br />

bridge construction in Tennison Road for 2014-2015.<br />

Anti-flood measures: Cleaned 601 soakaways, 27102 gullies/chamber cleaned<br />

and 425 defective gullies repaired.<br />

Electric car <strong>infrastructure</strong>: Limited purchase of electronic vehicles due to the<br />

short range and higher price and different types of charging socket requiring<br />

different electronic vehicle charging points.<br />

Bridge strengthening: Bridge failure with risk to Tram, Rail and Highway<br />

networks.<br />

Anti-flood measures: Failure to the drainage system may result in flooding.<br />

28


CONNECTED CITY PROGRAMME: ROAD NETWORK<br />

Mitigation:<br />

<br />

<br />

<br />

Electric car <strong>infrastructure</strong>: Government continuing £5000 discount and<br />

mainstream manufacturers attractive vehicles with options such as leasing<br />

the battery or memberships of car club for longer journeys. Installing more<br />

charging points which include two types of sockets to overcome this, as well<br />

as British Gas and others offering reduced price home charging kits.<br />

Bridge strengthening: Trief kerbs in areas of bridge weakness with imposition<br />

of weight restrictions<br />

Anti-flood measures; Clean gullies and soakaways effectively and implement<br />

new drainage measures where applicable.<br />

Planned Provision Lead Partner Delivery<br />

Partners/<br />

Stakeholders<br />

Delivery Mechanism/<br />

Funding Source<br />

Cost (if known) Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to<br />

CLP Strategic<br />

Policies: (3)<br />

Critical, (2)<br />

Necessary, (1)<br />

Contributory<br />

Bridge Strengthening Network Rail/ LBC, TfL, LoBEG, TfL (LoBEG), CIL £750k per year Borough-wide Y<br />

LBC<br />

Network Rail<br />

Soakaway Maintenance and LBC<br />

LBC, TfL, £1.7m from LBC Capital £1.75m Borough-wide Y<br />

Replacement– Highways<br />

Environment Budget 2011/12-2015/16<br />

Drainage<br />

Agency<br />

Congestion relief measures LBC, TfL LBC, TfL TfL, CIL, LBC funding (TBC) £1.8m Borough-wide Y Y<br />

Minor highway<br />

LBC LBC, TfL Capital Programme, CIL £250k per year Borough-wide Y Y Y<br />

improvements<br />

Electric car <strong>infrastructure</strong> LBC, TfL LBC, TfL Mayor’s Transport Strategy £5k per station (estimated Borough-wide Y Y Y<br />

capital costs)<br />

29<br />

2<br />

2<br />

2<br />

1<br />

1


CONNECTED CITY PROGRAMME: STREET LIGHTING<br />

What?<br />

A joint project between the London Borough of Croydon and the London Borough<br />

of Lewisham to replace the ageing street lighting stock.<br />

Where?<br />

Borough-wide<br />

When?<br />

2011-2016 with a 25 year maintenance and repair programme.<br />

Progress Since March 2012:<br />

The programme began in New Addington in 2011. The work will progress on a<br />

street –by-street, ward-by-ward basis.<br />

Year One: New Addington, Fieldway, Shirley and Ashburton<br />

Year Two: South Norwood, Upper Norwood, Norbury, Thornton Heath, West<br />

Thornton, Broad Green and Waddon<br />

Year Three: Bensham Manor, Selhurst, Addiscombe, Woodside and Fairfield<br />

Why?<br />

The Croydon and Lewisham Street Lighting PFI includes the replacement of<br />

approximately 46,000 street light and traffic signs over a five year period, with ongoing<br />

maintenance and repairs for 25 years. The scope of the project will deliver a<br />

number of benefits:<br />

Positive impact on fear of crime and public perception of risk.<br />

Improved street safety and reduction in road traffic accidents.<br />

Delivery of significant efficiency savings in capital replacement and<br />

maintenance terms.<br />

Allows service management objectives to include sustainability goals for the<br />

first time.<br />

Stakeholder Engagement Since March 2012:<br />

Consultation with staff providing the existing street lighting service is on-going. Key<br />

stakeholders, including neighbourhood forums and crime and safety partnerships,<br />

will be consulted before and during service <strong>delivery</strong>.<br />

Planned Provision<br />

Lead<br />

Partner<br />

Delivery Partners/Stakeholders<br />

Delivery Mechanism/<br />

Funding Source<br />

Cost (if<br />

known)<br />

Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to CLP Strategic<br />

Policies: (3) Critical, (2) Necessary, (1)<br />

Contributory<br />

Street lighting PFI programme LBC LBC/ London Borough of<br />

Lewisham and Skanska<br />

Infrastructure Services<br />

PFI for street lights £40m<br />

capital<br />

Boroughwide<br />

Y<br />

Y<br />

1<br />

30


CONNECTED CITY PROGRAMME: PARKING<br />

What?<br />

Car parking improvements and rationalisation<br />

Where?<br />

Croydon Opportunity Area<br />

When?<br />

On-going<br />

Why?<br />

In the Croydon Opportunity Area there are approximately 7,150 public off-street<br />

publicly usable car spaces, including surface, multi-storey and underground car<br />

parks. These car parks vary widely in quality, accessibility for both cars and<br />

pedestrians and tariff structure. Improvements need to be made to the major car<br />

parks and enhancements will include the removal of poor quality surplus places and<br />

redeployment of some sites to other uses as there are currently 3,000 underused<br />

spaces.<br />

2) Or an alternative parking arrangement if there is no significant<br />

redevelopment.<br />

Based on these two scenarios, the OAPF sets out four principles to be followed in<br />

guiding the future design and location of public off street parking in the COA.<br />

Progress Since March 2012:<br />

Chapter 8 of the Croydon Opportunity Area Framework (OAPF) sets out the parking<br />

strategy for the Croydon Opportunity Area. An objective of the OAPF is to not allow<br />

an increase in the overall number of 7,150 publicly usable off-street COA car parking<br />

spaces. It also sets out the need to increase the number of good quality and well<br />

located parking spaces. The OAPF sets out two parking scenarios for the next 20<br />

years:<br />

1) what could happen should there be a large scale redevelopment in the central<br />

area of the COA around the Retail core, Mid Croydon and Fairfield, New Town<br />

and East Croydon;<br />

Poor quality, under-used public car park in central Croydon<br />

Planned Provision<br />

Lead<br />

Partner<br />

Delivery Partners/Stakeholders<br />

Delivery Mechanism/Funding<br />

Source<br />

Cost (if<br />

known)<br />

Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to CLP Strategic<br />

Policies: (3) Critical, (2)<br />

Necessary, (1) Contributory<br />

Car park improvements and rationalisation LBC NCP/ private sector LBC Transport<br />

Strategy<br />

TBC<br />

Boroughwide<br />

Y Y Y<br />

2<br />

31


CONNECTED CITY PROGRAMME: STREET WAYFINDING AND SIGNAGE<br />

What?<br />

Consolidation of and improvements to street wayfinding and signage.<br />

Where?<br />

Borough-wide. The Legible London programme has been focussed in the Croydon<br />

Metropolitan Centre and District Centres.<br />

When?<br />

On-going<br />

Why?<br />

Carefully sited signage and wayfinding can play an important role in ensuring<br />

Croydon’s streets and footways are safe, accessible and legible. The objectives of<br />

the Legible London system is to address the lack of clear, consistent and<br />

coordinated on-street information in Central Croydon. It also helps visitors,<br />

residents and workers find their way to our key destinations.<br />

Stakeholder Engagement Since March 2012:<br />

No public consultation events have taken place. However, the Croydon Public<br />

Realm Design Guide was consulted on internally and was approved by Cabinet.<br />

Progress Since March 2012:<br />

Croydon Public Realm Design Guide was approved by Cabinet on 23rd April 2012<br />

and provides general guidelines on signs and wayfinding and details on street name<br />

plates, traffic signs, Legible London signs, advertising, welcome signs and<br />

information boards.<br />

Risks:<br />

Doubling up of signage and the creation of street clutter.<br />

Mitigation:<br />

<br />

An inventory is to take place of current signage to determine what can be<br />

consolidated, removed and replaced.<br />

Planned Provision<br />

Lead<br />

Partner<br />

Delivery Partners/Stakeholders<br />

Delivery<br />

Mechanism/<br />

Funding Source<br />

Street wayfinding and signage LBC TfL Public Realm<br />

Strategy<br />

32<br />

Cost (if<br />

known)<br />

Location 2011-<br />

2015<br />

2016-<br />

2020<br />

£3m COA Y Y Y<br />

New wayfinding signage<br />

2021- Relationship to CLP Strategic<br />

Policies: (3) Critical, (2) Necessary, (1)<br />

Contributory<br />

1


CONNECTED CITY PROGRAMME: PURLEY TOWN CENTRE<br />

What?<br />

<br />

<br />

Change to gyratory.<br />

Road network and public realm enhancements.<br />

Where?<br />

Purley<br />

When?<br />

By 2020<br />

Why?<br />

To improve the road network and public realm in Purley town centre. The Council<br />

has identified improvements being required at Purley Gyratory part of the<br />

Transport for London Road Network (TLRN).<br />

Progress Since March 2012:<br />

There has been no commitment from either the Council or TfL to invest in the<br />

improvements at the gyratory at this stage and no work has been undertaken. TfL is<br />

reviewing its highway portfolio as part of the Roads Task Force and will look at<br />

Purley Gyratory as part of an A23 corridor study but does not currently have a<br />

scheme of works or any funding allocated. Public Realm works in Purley High Street<br />

were substantially completed in February 2012.<br />

Risks:<br />

No commitment from either the Council or TfL.<br />

Mitigation:<br />

<br />

TfL would support use of Borough CIL and will seek s106 contributions, as<br />

well as encouraging the council to seek LIP funding.<br />

Purley Gyratory<br />

Planned Provision<br />

Lead<br />

Partner<br />

Delivery Partners/Stakeholders<br />

Delivery<br />

Mechanism/<br />

Funding Source<br />

Cost (if<br />

known)<br />

Location 2011-<br />

2015<br />

Change to gyratory TfL LBC TfL TBC Purley Y<br />

2016-<br />

2020<br />

2021- Relationship to CLP Strategic<br />

Policies: (3) Critical, (2) Necessary, (1)<br />

Contributory<br />

2<br />

33


CONNECTED CITY PROGRAMME: BUS SYSTEM<br />

What?<br />

<br />

<br />

<br />

<br />

Accessibility and safety improvements<br />

Bus information improvements<br />

Bus priority measures<br />

Bus stands / standbys<br />

Where?<br />

Borough-wide<br />

every 30 minutes to every 20 minutes in October 2009.<br />

December 2009: Extension of route 463 to serve Coulsdon South station<br />

August 2013: Introduction of a Sunday service on route 434<br />

TfL has agreed to fund a £3m improvement to West Croydon bus station and<br />

improvements are also expected at East Croydon.<br />

When?<br />

On-going<br />

Why?<br />

Bus travel accounts for a large proportion of the journeys to work in Croydon and<br />

many school and shopping trips. With limited scope to increase the capacity of the<br />

road network, the efficiency, convenience and punctuality of public transport needs<br />

to improve. The bus system is critical to this endeavour, especially for sub-regional<br />

and local transport.<br />

Stakeholder Engagement Since March 2012:<br />

Improvements will continue to be made across the borough through the<br />

consultation process. Where appropriate, TfL will seek s106 funding to meet<br />

demand, particularly in the COA.<br />

Progress Since March 2012:<br />

There have been significant improvements in Excess Waiting Time and On Time<br />

(punctuality) improvements over the last 10 years. Since 2012, there have been<br />

frequency enhancements and structural changes day and night to improve a more<br />

efficient and convenient service.<br />

August 2012: Introduction of N64 and and N109, which brought previously<br />

unserved areas of Croydon onto the night bus network (Selsdon) and<br />

increased night frequency to other areas (Thornton Heath-Croydon).<br />

<br />

October 2009: Increase of evening and Sunday frequency on route 407 from<br />

34


CONNECTED CITY PROGRAMME: BUS SYSTEM<br />

Planned Provision Lead Partner Delivery<br />

Partners/<br />

Stakeholders<br />

Delivery<br />

Mechanism/<br />

Funding Source<br />

Cost (if known) Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to<br />

CLP Strategic<br />

Policies: (3)<br />

Critical, (2)<br />

Necessary, (1)<br />

Contributory<br />

Accessibility and safety<br />

improvements<br />

TfL<br />

Bus operators<br />

and TfL<br />

Bus operator<br />

plans, Mayor’s<br />

Transport<br />

Strategy and<br />

Revenue<br />

Programme<br />

£100k per year Borough-wide Y Y Y<br />

Bus information<br />

TfL TfL Borough £250k Borough-wide Y<br />

improvements<br />

Transport<br />

Strategy,<br />

Mayor’s<br />

Transport<br />

Strategy<br />

Bus priority measures TfL LBC, TfL TfL £1.9m Borough-wide Y Y Y<br />

Bus stands/standbys TfL,LBC LBC, TfL TfL £3m per year COA Y Y<br />

Improvements to West TfL TfL TfL £3m COA Y Y<br />

Croydon bus station<br />

2<br />

2<br />

2<br />

2<br />

2<br />

35


CONNECTED CITY PROGRAMME: CYCLING INFRASTRUCTURE<br />

What?<br />

<br />

<br />

<br />

<br />

<br />

<br />

Refurbishment of London cycling network<br />

Cycling provision at major stations<br />

Completion of Connect 2 and Greenway routes<br />

Cycling measures at key junctions<br />

Other cycle links<br />

Quietways<br />

Where?<br />

Borough-wide<br />

When?<br />

On-going.<br />

Why?<br />

The Council sees the encouragement and promotion of cycling in the Borough as<br />

part of the thrust toward smarter travel. Generally it is an environmentally sound<br />

means of transport and one that assists the promotion of good health. As part of<br />

the Transport Strategy, a capital programme of <strong>infrastructure</strong> for cycling is<br />

required.<br />

Stakeholder Engagement Since March 2012:<br />

No information available for this update.<br />

Progress Since March 2012:<br />

An audit of signing for the London Cycling Network around the Croydon<br />

Metropolitan Centre has been undertaken and a re-signing schedule has been<br />

prepared. New connections are being made as part of Connected Croydon<br />

programme. A design of a cycle hub at East Croydon Station has been completed.<br />

Proposals for a series of Quietways are currently being prepared, as well as<br />

proposals for addressing difficult junctions.<br />

Existing cycling <strong>infrastructure</strong><br />

36


CONNECTED CITY PROGRAMME: CYCLING INFRASTRUCTURE<br />

Planned Provision Lead Partner Delivery Delivery Cost (if known) Location 2011- 2016-<br />

Partners/ Mechanism/<br />

2015 2020<br />

Stakeholders Funding Source<br />

Refurbishment of London<br />

cycling network and<br />

provision of Quietways<br />

TfL LBC, TfL Borough<br />

Transport<br />

Strategy,<br />

Mayor’s Vision<br />

for Cycling, LIP<br />

TBC Borough-wide Y<br />

Cycling provision at major Network Rail LBC, TfL, Master Plans, TBC Borough-wide Y Y<br />

stations<br />

Network Rail Public Realm<br />

Strategy,<br />

Planning<br />

Obligations,<br />

Mayor’s Vision<br />

for Cycling, LIP,<br />

TOCs, National<br />

Rail<br />

Completion of Connect 2 TfL<br />

LBC, TfL, TfL, LBC, CIL TBC Borough-wide Y Y<br />

and Greenway routes<br />

Sustrans<br />

Cycling measures at key TfL/LBC LBC, TfL, TfL, LBC, CIL TBC Borough-wide Y Y<br />

junctions<br />

Sustrans<br />

Other cycle links LBC LBC, TfL, LIP2 or Connect TBC through LIP2 or Conenct 2 Borough-wide Y Y<br />

Sustrans 2 programme programme<br />

2021- Relationship to<br />

CLP Strategic<br />

Policies: (3)<br />

Critical, (2)<br />

Necessary, (1)<br />

Contributory<br />

2<br />

2<br />

2<br />

2<br />

2<br />

37


CONNECTED CITY PROGRAMME: FREIGHT & DELIVERIES<br />

What?<br />

Freight consolidation centre<br />

Where?<br />

South of the borough.<br />

When?<br />

By 2015<br />

Why?<br />

An efficient and convenient freight system with minimal environmental impact is an<br />

important part of a vibrant and enterprising city. Currently the future needs of such<br />

a system of distribution are being assessed as part of the Transport Strategy.<br />

However, needs already emerging include depots in support of a centralised waste<br />

collection and recycling system in the COA area and other principal District Centres.<br />

For the COA area, there also needs to be assessed the viability of a complementary<br />

centralised <strong>delivery</strong> service.<br />

Mitigation:<br />

<br />

The Council will work with neighbouring boroughs to identify a site should a<br />

suitable site in Croydon not be found.<br />

Stakeholder Engagement Since March 2012:<br />

The Council’s Pollution Team have been in discussion with Westfield and<br />

Hammerson to see if a short-term consolidation centre for the town centre<br />

regeneration can be accommodated.<br />

Progress Since March 2012:<br />

The search for a possible site in the south of the borough for a freight consolidation<br />

centre is pending agreement on the costing of the project and funding source.<br />

Risks:<br />

<br />

It will be difficult to identify a site in the south of the borough that is large<br />

enough to perform this function.<br />

Freight movement on the A23<br />

Planned Provision<br />

Lead<br />

Partner<br />

Delivery Partners/Stakeholders<br />

Delivery Mechanism/Funding<br />

Source<br />

Cost (if<br />

known)<br />

Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to CLP Strategic<br />

Policies: (3) Critical, (2) Necessary,<br />

(1) Contributory<br />

Freight consolidation centre LBC Private sector Private sector,<br />

CIL<br />

South of the<br />

borough<br />

Y<br />

1<br />

38


CONNECTED CITY PROGRAMME: TAXIS<br />

What?<br />

East Croydon - Lansdowne Road Taxi Rank<br />

Where?<br />

Croydon Opportunity Area<br />

When?<br />

By 2015<br />

Why?<br />

Ensuring adequate taxi provision is important in encouraging the reduction of<br />

private transportation.<br />

Risks:<br />

<br />

Delay in completion which does not coordinate with the opening of the<br />

footbridge and pedestrian walkway on 28th November. This is due to utility<br />

service connection issues and finalising legal agreements with Ruskin Square<br />

Development.<br />

Mitigation:<br />

<br />

The Billington Hill rank will remain open and signage for the taxi rank on<br />

Lansdowne Road will only be installed when it is opened.<br />

Stakeholder Engagement Since March 2012:<br />

Public consultation took place in November 2012 which comprised of widespread<br />

promotion of proposals via the Council website, press releases, a targeted letter to<br />

key stakeholders including TfL public carriage office and a presentation to TfL and<br />

Taxi representatives.<br />

Progress Since March 2012:<br />

The design was finalised in December and the construction was tendered in July<br />

2013. The taxi rank and adjoining disabled parking bay is to be constructed in late<br />

2013 or early 2014.<br />

Existing taxi rank in Croydon<br />

Planned Provision<br />

Lead<br />

Partner<br />

Delivery Partners/Stakeholders<br />

Delivery Mechanism/Funding<br />

Source<br />

Cost (if<br />

known)<br />

Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to CLP Strategic<br />

Policies: (3) Critical, (2) Necessary,<br />

(1) Contributory<br />

East Croydon– Lansdowne Road Taxi Rank LB Croydon Private external TfL £100K COA Y<br />

1<br />

39


SUSTAINABLE CITY PROGRAMME<br />

40


SUSTAINABLE CITY PROGRAMME: 'PARKS TO BE PROUD OF' PROJECTS<br />

What?<br />

Improvements at:<br />

Norbury Park<br />

Thornton Heath Recreation Ground<br />

South Norwood Country Park<br />

Waddon Ponds<br />

Wandle Park<br />

Lloyd Park<br />

Milne Park and Addington Vale<br />

Sanderstead Recreation Ground<br />

Coulsdon Memorial Ground<br />

Where?<br />

Borough-wide<br />

When?<br />

By 2014<br />

<br />

<br />

<br />

<br />

<br />

<br />

Thornton Heath Recreation Ground: Installation of outdoor gym and<br />

refurbishment of playground.<br />

South Norwood Country Park: New kiosk for refreshments and hire of pitch<br />

and putt equipment. Toilets refurbished.<br />

Waddon Ponds: Toilets refurbished and new facilities installed for disabled<br />

users.<br />

Lloyd Park: New footpath network.<br />

Milne Park and Addington Vale: Playground refurbished in Milne Park and<br />

Queen Elizabeth’s Drive. A new rock play feature in Addington Vale.<br />

Coulsdon Memorial Ground– Café and toilets completely refurbished. Bowls<br />

Pavillion refurbished to enable new Friends group to manage the bowling<br />

green.<br />

Why?<br />

Parks to be Proud Of (PTBPO) was a £1.5million scheme to improve Croydon’s parks<br />

and green spaces. The scheme was designed to improve customer experience and<br />

satisfaction, increase usage and help deliver LAA targets. The scheme was designed<br />

to make a targeted approach with specific support at nine key locations in order to<br />

make a strategic transformation rather than trying to spread the resource across<br />

129 spaces in the borough.<br />

Stakeholder Engagement Since March 2012:<br />

Learning and Volunteer Officer appointed for Wandle Park to engage with local<br />

residents, which is on-going.<br />

Progress Since March 2012:<br />

Norbury Park: Improved entrance and signage.<br />

41


SUSTAINABLE CITY PROGRAMME: PLAY AREAS<br />

What?<br />

There are 53 play areas within the borough’s parks and open spaces and 21 play<br />

areas on housing land. A project is proposed in 2014 to refurbish Little Road<br />

Playground.<br />

Where?<br />

Borough-wide<br />

When?<br />

By 2020<br />

Why?<br />

Croydon Council was one of the first London Boroughs to develop a play strategy<br />

and has since produced a further two play strategies to ensure that play remains a<br />

priority across the Council and the community. Play has many impacts on children’s<br />

lives, including physical, emotional, mental and social benefits. The objectives of<br />

the play provision across Croydon is to ensure:<br />

1) Children feel physically and emotionally healthier through play.<br />

2) Children enjoy a rich and varied play experience in Croydon.<br />

3) Children enjoy diverse and stimulating environments for play throughout<br />

Croydon’s public spaces.<br />

A hierarchy of play facilities is to be developed to support applications for S106 and<br />

CIL funding.<br />

Stakeholder Engagement Since March 2012:<br />

No stakeholder engagement has taken place since 2012 but external grant sources<br />

are to be identified by working in conjunction with Friends and stakeholder groups.<br />

Progress Since March 2012:<br />

<br />

<br />

<br />

<br />

Thornton Heath Recreation Ground: refurbishment of playground<br />

Wandle Park: whole park refurbishment including new play facilities, which<br />

was delivered with funding from a number of sources.<br />

Milne Park and Addington Vale: Playground refurbished in Milne Park and<br />

Queen Elizabeth’s Drive. A new rock play feature in Addington Vale.<br />

Westow Park: refurbishment of play ground with funding secured by Friends<br />

of Westow Park working in conjunction with Green Spaces.<br />

Risks:<br />

No budgets secured for future replacement of play facilities.<br />

Mitigation:<br />

<br />

Hierarchy of play facilities to be prepared to prioritise the removal of old play<br />

facilities to ensure an even spread of facilities across the borough.<br />

Planned Provision<br />

Lead<br />

Partner<br />

Delivery Partners/<br />

Stakeholders<br />

Delivery Mechanism/Funding<br />

Source<br />

Cost (if<br />

known)<br />

Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to CLP Strategic<br />

Policies: (3) Critical, (2) Necessary, (1)<br />

Contributory<br />

TBC<br />

Refurbishment of Little Road Playground LB Croydon LB Croydon, DCSF DCSF, LBC<br />

Capital Programme,<br />

S106, HLF,<br />

other funding<br />

streams<br />

Boroughwide<br />

Y<br />

Y<br />

2<br />

42


SUSTAINABLE CITY PROGRAMME: SPORTS PITCHES<br />

What?<br />

Programme based on co-location with schools and greenspaces. The Green Spaces<br />

Service currently have the following provision:<br />

Football:<br />

Junior Pitches– 16<br />

7-A-Side pitches– 14<br />

Senior Pitches– 31<br />

Cricket: 10 pitches<br />

The programme includes the upgrade of football pitches and facilities in Wandle<br />

Park, as well as the provision of junior and mini football pitches and privately owned<br />

outdoor facilities including tennis, football, cricket, rugby, golf and athletic clubs.<br />

Where?<br />

Borough-wide<br />

When?<br />

By 2015<br />

Why?<br />

Community access to outdoor sport and recreation facilities in Croydon is a key<br />

requirement for achieving targets set out by the Government and Sport England.<br />

Croydon Council needs to rectify identified inadequacies and meet identified<br />

shortfalls through improvements to the current pitch stock and ancillary facilities. It<br />

is important that the levels of pitch provision are protected, maintained and<br />

enhanced to secure provision now and in the future. (LONDON BOROUGH OF<br />

CROYDON , OPEN SPACE NEEDS ASSESSMENT FINAL REPORT AUGUST 2009)<br />

Progress Since March 2012:<br />

From 2014 Wandle Park will accomdate 1 junior pitch and 2 7-a-side pitches.<br />

Planned Provision<br />

Lead<br />

Partner<br />

Delivery Partners/Stakeholders<br />

Delivery Mechanism/Funding<br />

Source<br />

Cost (if<br />

known)<br />

Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to CLP Strategic<br />

Policies: (3) Critical, (2) Necessary,<br />

(1) Contributory<br />

Programme based on co-location with schools<br />

and greenspaces. It includes: Wandle Park upgrade<br />

of football pitches and facilities. Play<br />

Green: provision of junior and mini football<br />

pitches. Privately owned outdoor facilities including<br />

tennis, football, cricket, rugby, golf and<br />

athletic clubs<br />

TBC<br />

LBC DCSF DCSF, LBC<br />

Capital Programme,<br />

S106, HLF and<br />

other funding<br />

streams<br />

Boroughwide<br />

Y<br />

2<br />

43


SUSTAINABLE CITY PROGRAMME: PUBLIC REALM IMPROVEMENTS<br />

What?<br />

Public realm improvements at the following locations:<br />

Purley<br />

New Addington- Phase1 and 2<br />

<br />

Addiscombe<br />

Legible London- Phase 1<br />

<br />

<br />

Wandle Park<br />

‘Parks to be Proud of’ project<br />

Connect 2<br />

<br />

East Croydon Bridge<br />

Wellesley Road- Phase 1<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

Wellesley Road- Phase 2 (Lansdowne Road)<br />

College Green Paving<br />

West Croydon Public Realm<br />

East Croydon Public Realm<br />

High Streets – South End<br />

High Streets (London Road, Old Town, Central)<br />

George Street tram stop<br />

South Norwood Public Realm<br />

Billinton Hill – Eastern Link<br />

Wandle Road Bus Stand<br />

Future Tier 2 to include Wandle Park pavilion, COA subway removal, cycle<br />

projects, district centres and future Legible London future phases.<br />

Where?<br />

Borough-wide<br />

When?<br />

2015<br />

Why?<br />

In order to achieve Croydon’s vision to be London’s most, enterprising borough it is<br />

essential that Croydon’s public realm reflects this aspiration and is welcoming,<br />

simple, clean, accessible, sustainable, well managed and maintained. To encourage<br />

a new residential community and business to the Croydon Opportunity Area and<br />

District Centres, the public realm needs to be improved.<br />

Stakeholder Engagement Since March 2012:<br />

Formal public consultation has been undertaken for a number of individual<br />

Connected Croydon projects in design, including South End, West Croydon, East<br />

Croydon and Lansdowne Road. Continual stakeholder engagement takes place<br />

through project design and <strong>delivery</strong>. Connected Croydon Summit 2013, as well as<br />

the establishment of Connected Croydon microsite. Engagement has taken place<br />

with Develop Croydon, Live Croydon etc.<br />

Progress Since March 2012:<br />

A number of projects have been completed:<br />

Purley<br />

New Addington Phase 1<br />

Addiscombe<br />

Legible London Phase 1<br />

Wandle Park<br />

A number of projects are on site and the project design and consultation is<br />

underway on a number of projects.<br />

Risks:<br />

Construction logistics and disruption<br />

Large of number of projects to be delivered by March 2015<br />

Risk to quality given timeframes and budgets<br />

Mitigation:<br />

<br />

<br />

Construction logistics party set up by Tony Antoniou, Director of Regeneration<br />

Improve resource efficiency and resources are directed to quality and design.<br />

44


SUSTAINABLE CITY PROGRAMME: PUBLIC REALM IMPROVEMENTS<br />

Planned Provision<br />

Lead<br />

Partner<br />

Delivery Partners/<br />

Stakeholders<br />

Delivery Mechanism/ Funding Source Cost (if known) Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to CLP Strategic<br />

Policies: (3) Critical, (2)<br />

Necessary, (1) Contributory<br />

Connect 2, Wandle Park to Lloyd Park LBC Sustrans, TfL LBC, TfL, Sustrans £3,303,104 COA and<br />

surrounding<br />

East Croydon Bridge<br />

Network<br />

Rail<br />

LBC, Network Rail,<br />

private sector<br />

LBC, Network Rail, private sector<br />

£6m (LBC contribution<br />

to £20m total)<br />

Wellesley Road Phase 1 LBC TfL, MoL TfL, MoL, S106 £4,535,524 COA Y<br />

Wellesley Road Phase 2 (Lansdowne Road) LBC MoL MoL £1,750,000 COA Y<br />

College Green Paving LBC Croydon College LBC Capital Programme, CIL £553,986 COA Y<br />

West Croydon Public Realm LBC TfL, MoL LBC Capital Programme, CIL £4,934,060 COA Y<br />

Phase 2/3 public realm improvements LBC LBC, MRF, Network<br />

Rail and TfL<br />

LBC, MRF, Network Rail and TfL £14.1m (approx) COA Y<br />

East Croydon Public Realm LBC TfL, MoL LBC Capital Programme, CIL, TfL, MoL £5,546,429 COA Y<br />

East Croydon Phase 2/3 public realm improvements LBC LBC, Network Rail<br />

and private sector<br />

Mayor Scheme funding, MRF, CIL,<br />

Capital Programme, NR, private sector<br />

High Streets (South End) LBC TfL, MoL LBC Capital Programme, CIL, GAF,<br />

MoL, TfL<br />

COA<br />

£13.7m COA Y<br />

£2,934,711 COA Y<br />

High Streets (London Road, Old Town, Central) LBC TfL, MoL MoL £6,156,480 COA Y<br />

New Addington Central Parade Phase 2 LBC TfL, MoL MoL £864,000 Addington Y<br />

George Street tram stop LBC TfL, MoL MoL £878,620 COA Y<br />

South Norwood Public Realm LBC TfL TfL £241,005 S Norwood &<br />

Woodside<br />

Billington Hill – Eastern Station Link LBC LBC, Network Rail,<br />

private sector<br />

LBC, Network Rail, private sector £3.4m COA Y<br />

Wandle Road bus stand LBC TfL TfL £1.22m COA Y<br />

Future Tier 2 including Wandle Park pavilion, North End,<br />

COA subway removal, mini-hollands / cycle projects, district<br />

centres and future Legible London Future Phases<br />

£68m (approx) Boroughwide<br />

Y<br />

Y<br />

Y<br />

Y Y Y<br />

3<br />

3<br />

3<br />

3<br />

2<br />

3<br />

3<br />

3<br />

3<br />

3<br />

3<br />

3<br />

3<br />

3<br />

3<br />

2<br />

3<br />

45


SUSTAINABLE CITY PROGRAMME: URBAN WOODLAND AND TREES<br />

What?<br />

As part of the Woodland and Tree Management Plan, highway tree inspection and<br />

works, woodland health and safety inspection, tree planting and woodland<br />

inspection and works will take place.<br />

Where?<br />

Borough-wide<br />

When?<br />

By 2015<br />

Why?<br />

For all other deficient areas, gaps should be met by increasing the “naturalness” of<br />

existing areas of formal open space (e.g. through woodland planting). Meeting<br />

deficiencies as identified above will also go some way towards meeting the Natural<br />

England Local Nature Reserve Standard, which highlights a shortfall of 181.5<br />

hectares in Croydon. The Council and its partners will also maximise opportunities<br />

for street tree planting to assist urban cooling in a changing climate.<br />

to tree planting, over 500 replacement trees were planted during the winter of<br />

2012/13 and over 700 trees were planted in existing parks and woodlands. A new<br />

woodland has been created in Rowdown Field, New Addington, in partnership with<br />

the Woodland Trust.<br />

Risks:<br />

<br />

<br />

Spread of pathogens and pests such as Ash Dieback and Oak Processionary<br />

Moth.<br />

Further reduction in budgets.<br />

Mitigation:<br />

Management of budget to allow the continuation of existing programmes.<br />

Stakeholder Engagement Since March 2012:<br />

No information available for this update.<br />

Progress Since March 2012:<br />

Maintenance work is carried out via various programmes and is on-going. In regards<br />

Planned Provision<br />

Lead<br />

Partner<br />

Delivery Partners/<br />

Stakeholders<br />

Delivery<br />

Mechanism/<br />

Funding Source<br />

Cost (if<br />

known)<br />

Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to CLP Strategic<br />

Policies: (3) Critical, (2)<br />

Necessary, (1) Contributory<br />

Woodland and Tree Management Plan: Highway tree<br />

inspection and works, Woodland Health and Safety<br />

Inspection, Tree planting, Woodland inspection and works.<br />

LBC LBC LBC £690,000 Boroughwide<br />

Y<br />

1<br />

46


SUSTAINABLE CITY PROGRAMME: WALKING AND CYCLING ON GREENWAYS<br />

What?<br />

Connect 2<br />

National Cycling Network 21<br />

N-S link Norbury-Kenley, Addington<br />

Emerad Neckless, South Norwood Greenways<br />

Other lower priority routes<br />

Where?<br />

Borough-wide<br />

Stakeholder Engagement Since March 2012:<br />

No information available for this update.<br />

Progress Since March 2012:<br />

Greenway section 1 to 9 have been completed. The feasibility study for the Croydon<br />

to Orpington Greenway is nearing completion. Sustrans are developing proposals to<br />

enhance the Wandle links Greenway. Greenway section 10 is awaiting confirmation<br />

to change in cycling by-laws in parks. Proposals for NCN232 to become a Quietway.<br />

When?<br />

After 2021<br />

Why?<br />

Urban realm improvements to increase walking and cycling are priorities within the<br />

South sub-regional transport plan. The Council and its partners will improve<br />

conditions for walking and enhance the pedestrian experience by enhancing<br />

footpaths, strategic walking routes and links through green spaces to ensure a<br />

coherent pedestrian network; promoting the identification and implementation of<br />

accessible, safe, visible and convenient direct cycle and walking routes.<br />

Planned Provision<br />

Lead<br />

Partner<br />

Delivery Partners/Stakeholders<br />

Delivery<br />

Mechanism/<br />

Funding Source<br />

Cost (if<br />

known)<br />

Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to CLP Strategic<br />

Policies: (3) Critical, (2)<br />

Necessary, (1) Contributory<br />

Connect 2, National Cycling Network 21, N-S<br />

link Norbury– Kenley Addington, other lower<br />

priority routes and Emerald Necklace, South<br />

Norwood Greenways<br />

LBC TfL, PCT, Sustrans TfL, LBC<br />

Capital<br />

Programme,<br />

S106<br />

Boroughwide<br />

Y<br />

2<br />

47


SUSTAINABLE CITY PROGRAMME: MAYOR OF LONDON – ACCESS TO NATURE<br />

What?<br />

To improve access to nature across London. These areas include Queens Road<br />

Cemetery, Melfort Avenue Recreation Ground, Norbury Hall Park, Addiscombe<br />

Railway Park, Purley Way East Playing Fields, Pollards Hill, Haling Grove, Wandle<br />

Park, Duppas Hill, Norbury Park and Brook, Cane Hill Hospital West and Waddon<br />

Ponds.<br />

Where?<br />

Borough-wide<br />

When?<br />

By 2021 and beyond.<br />

Why?<br />

GLA Access to Nature mapping shows a good distribution of natural and seminatural<br />

greenspace provision in the south of the Borough where the larger sites are<br />

located. Due to land availability there are significant gaps in provision in the<br />

northern parts of the borough, particularly in Thornton Heath and Central Croydon.<br />

Sites are needed in north and central Croydon to reduce the area of deficit in access<br />

to nature. Land availability issues means that it is unlikely new natural sites can be<br />

provided in these areas.<br />

Stakeholder Engagement Since March 2012:<br />

No information available for this update.<br />

Progress Since March 2012:<br />

1) Addiscome Railway Park: meadow grasslands continue to develop, hedges<br />

have been planted and wetlands are good for amphibians.<br />

2) Wandle Park: river restoration and pond have been completed along with the<br />

meadows. The pond life is very good for such a new habitat.<br />

3) Waddon Ponds: The naturalisation of pond edges is proceeding although<br />

there are some issues with the establishment of aquatic vegetation. The<br />

phase 2 work is to be implemented by the end of March 2014.<br />

Planned Provision<br />

Lead<br />

Partner<br />

Delivery Partners/Stakeholders<br />

Delivery<br />

Mechanism/<br />

Funding Source<br />

Cost (if<br />

known)<br />

Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to CLP Strategic<br />

Policies: (3) Critical, (2)<br />

Necessary, (1) Contributory<br />

To improve access to nature across London.<br />

These areas include Queens Road Cemetery,<br />

Melfort Avenue Recreation Ground, Norbury<br />

Hall Park, Addiscombe Railway Park, Purley<br />

Way East Playing Fields, Pollards Hill, Haling<br />

Grove, Wandle Park, Duppas Hill, Norbury Park<br />

and Brook, Cane Hill Hospital West and<br />

Waddon Ponds.<br />

GLA LB Croydon, Mayor of London Mayor of<br />

London, LDA<br />

N/A<br />

Boroughwide<br />

Y Y Y<br />

1<br />

48


SUSTAINABLE CITY PROGRAMME: MAYOR OF LONDON– CAPITAL GROWTH<br />

What?<br />

Community food/flower growing initiatives:<br />

New Addington: The introduction of a productive landscape including<br />

growing/cooking training tools.<br />

Park Hill Recreation Ground: the introduction of charity based initiatives e.g.<br />

gardening to improve social skills/inclusion.<br />

Wandle Park: setting up community garden encouraging local residents<br />

including charity based groups.<br />

Progress Since March 2012:<br />

Feasibility schemes to encourage gardening and productive landscapes within social<br />

and private residential landscapes. Grown Green initiatives within places of<br />

education including learning tools to attract grants and support for the introduction<br />

of urban agricultural schemes. Greening ‘Brown Fields’ initiative including the<br />

setting up of a borough-wide database of temporary lease sites, including landlocked<br />

sites. Initiatives related to ‘productive’ landscapes within new housing<br />

schemes to be considered at pre-application advice.<br />

Where?<br />

Borough-wide<br />

When?<br />

By 2020<br />

Why?<br />

The Borough is committed to the Mayor of London’s Capital Growth Scheme and<br />

has pledged to increase the number of growing spaces in the borough . An analysis<br />

of existing Green Infrastructure suggests food production and productive landscapes<br />

provision is available throughout the borough. However, accessibility to facilities<br />

such as ‘productive’ landscapes are poor borough wide.<br />

Stakeholder Engagement Since March 2012:<br />

No information available for this update.<br />

Planned Provision<br />

Lead<br />

Partner<br />

Delivery Partners/<br />

Stakeholders<br />

Delivery<br />

Mechanism/<br />

Funding Source<br />

Cost (if<br />

known)<br />

Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to CLP Strategic<br />

Policies: (3) Critical, (2)<br />

Necessary, (1) Contributory<br />

Community food and flower growing initiatives LBC Mayor of London Mayor of<br />

London, LBC<br />

N/A<br />

Boroughwide<br />

Y<br />

1<br />

49


SUSTAINABLE CITY PROGRAMME: LONDON DOWNLANDS PARTNERSHIP<br />

What?<br />

Management of the rare chalk downland, development of an extensive series of<br />

trails, woodland management and pond restoration.<br />

Where?<br />

Borough-wide<br />

When?<br />

On going<br />

Why?<br />

The Downlands Green Grid initiative (Area 7) relates to projects for the<br />

improvement and creation of new green areas and connections between them in<br />

the London Downlands area. It is supported and defined through a cross borough<br />

initiative between Croydon, Sutton and Bromley. The group’s vision covers the area<br />

where the countryside of the North Downs meets the urban edge and is punctuated<br />

by river valleys which spring from the chalk downs and the vestiges of the Great<br />

Northwood.<br />

Stakeholder Engagement Since March 2012:<br />

There is on-going liaison with <strong>delivery</strong> partners, Natural England, London Wildlife<br />

Trust and community partners, including local housing associations. Regular open<br />

days have taken place, as well as events to engage with the local people.<br />

Progress Since March 2012:<br />

On-going management at the chalk grasslands sites in the London Borough of<br />

Croydon and other local areas including Hutchinson’s Bank, Featherbed Lane Verge,<br />

Happy Valley, Sanderstead to Whyteleafe Countryside Area and Foxley Woods<br />

Meadows. On-going management of woodlands and ponds and maintenance of<br />

trails, including the LOOP and Downlands Circular Walks. There has also been a<br />

Capital Downs bid to HLF, which was unsuccessful on this occasion.<br />

Risks:<br />

<br />

<br />

<br />

Lack of funding<br />

Cuts to local authority funding<br />

Unsuccessful grant bids<br />

Mitigation:<br />

Exploration of different funding streams, including smaller grant funds.<br />

Planned Provision<br />

Management of the rare chalk<br />

downland, development of an<br />

extensive series of trails, woodland<br />

management and pond restoration<br />

Lead<br />

Partner<br />

London<br />

Downland<br />

Partnership<br />

Delivery Partners/<br />

Stakeholders<br />

LBC, LB Sutton, Surrey<br />

County Council, Corporation<br />

of London, Reigate &<br />

Banstead Borough Council,<br />

Tandridge District Council,<br />

Countryside Agency<br />

Delivery Mechanism/<br />

Funding Source<br />

LBC, LDA, TfL, Network Rail,<br />

GAF, private developers<br />

Cost (if known) Location 2011-<br />

2015<br />

Boroughwide<br />

2016-<br />

2020<br />

Y Y Y<br />

2021- Relationship to CLP Strategic<br />

Policies: (3) Critical, (2) Necessary,<br />

(1) Contributory<br />

1<br />

50


SUSTAINABLE CITY PROGRAMME: ALLOTMENTS<br />

What?<br />

Feasibility programme to re-open sites at South Norwood Lake and Pollards Hill,<br />

including upgrade of existing allotment facilities.<br />

‘Champion’ the use of Community Infrastructure Levy to introduce or improve<br />

allotment opportunities.<br />

Where?<br />

Borough-wide<br />

When?<br />

By 2020<br />

Why?<br />

Croydon has 18 allotments located within the Borough; six of which are managed by<br />

the Council, whilst the remainder sites are managed as private ownership or<br />

‘leased’ (direct management). There is a general shortage of allotments throughout<br />

the borough which has resulted in waiting lists. The specific areas of high demand<br />

for additional allotments are located within the north of the borough, particularly in<br />

the dense housing area of Upper Norwood where residential gardening<br />

opportunities are limited due to lack of green space.<br />

Progress Since March 2012:<br />

A feasibility programme is underway to re-open sites at South Norwood Lake and<br />

Pollards Hill. Preparation of upgrade programme of existing allotment facilities.<br />

Broomhall Road Allotments in South Croydon<br />

Planned Provision<br />

Lead<br />

Partner<br />

Delivery Partners/<br />

Stakeholders<br />

Delivery Mechanism/<br />

Funding Source<br />

Cost (if known) Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to CLP Strategic<br />

Policies: (3) Critical, (2)<br />

Necessary, (1) Contributory<br />

Re-opening of sites at South Norwood<br />

Lake and Pollards Hill, including upgrade<br />

of existing allotment facilities.<br />

LBC<br />

LBC, owners and<br />

occupiers<br />

LBC Capital funding,<br />

owners and occupiers<br />

Boroughwide<br />

Y<br />

1<br />

51


SUSTAINABLE CITY PROGRAMME: MAYOR OF LONDON’S BLUE RIBBON NETWORK<br />

What?<br />

Surface Water Management Plan & Extensive Soakaway & Ancillary Drainage<br />

Cleaning Programme.<br />

Where?<br />

Borough-wide<br />

When?<br />

On-going<br />

Why?<br />

The Flood and Water Management Act 2010 and Flood Regulations 2009 place<br />

responsibility on Lead Local Flood Authorities, which includes Croydon, to prepare<br />

and coordinate a strategy for the prevention of flooding.<br />

A full Surface Water Management Plan (SWMP) for the Borough has been prepared<br />

which details critical drainage areas in light of surface water flood risk throughout<br />

the borough. This work supplements the borough’s Level 1 and Level 2 Strategic<br />

Flood Risk Assessment (SFRA) which details fluvial, groundwater, and sewer flooding<br />

issues in the borough.<br />

Authorities.<br />

Progress Since March 2012:<br />

1) Working to ensure that all our drainage assets (i.e. gullies, soakaways, pumps)<br />

are maintained effectively.<br />

2) Working with other boroughs to develop a Local Flood Risk Management<br />

strategy.<br />

3) Working with the Environment Agency to improve maintenance to the<br />

Caterham Bourne.<br />

4) Commissioned a detailed modelling study of flooding in Brighton/A23 through<br />

to Purley.<br />

5) Completed a number of tasks in accordance with the FWMA 2010.<br />

Risks:<br />

Failure to maintain the drainage system may result in flooding.<br />

Mitigation:<br />

<br />

Clean gullies and soakaways effectively and implement new drainage<br />

measures where applicable.<br />

Stakeholder Engagement Since March 2012:<br />

Stakeholder engagement has taken place with the Environment Agency, London<br />

Drainage Engineering Group, Thames Water, Purley Community Flood Group, LBC<br />

Internal Flood Group, TfL, Councillors, MPs and other Flood Risk Management<br />

Planned Provision<br />

Surface Water Management Plan and<br />

Extensive Soakaway and Ancillary<br />

Drainage Cleaning Programme<br />

Lead<br />

Partner<br />

LBC<br />

Delivery Partners/<br />

Stakeholders<br />

LBC, Environment Agency<br />

and Croydon Fire Brigade<br />

Delivery Mechanism/<br />

Funding Source<br />

Cost (if known) Location 2011-<br />

2015<br />

DEFRA TBC Boroughwide<br />

2016-<br />

2020<br />

Y Y Y<br />

2021- Relationship to CLP Strategic<br />

Policies: (3) Critical, (2)<br />

Necessary, (1) Contributory<br />

1<br />

52


SUSTAINABLE CITY PROGRAMME: MAYOR OF LONDON’S STREET TREE PROGRAMME<br />

What?<br />

Mayor of London’s Street Tree Programme<br />

Where?<br />

Borough-wide<br />

When?<br />

By 2015<br />

Why?<br />

Maintaining the borough’s stock of street trees is one element of the Green<br />

Corridors concept which forms part of Croydon’s green <strong>infrastructure</strong>.<br />

Stakeholder Engagement Since March 2012:<br />

No information is available for this update.<br />

Progress Since March 2012:<br />

An application was submitted in July 2013 for 100 street trees to be planted in<br />

Broad Green ward and for 25 trees to be planted on the Holmsdale Road council<br />

estate. This application was successful and a total of £14, 375 has been awarded.<br />

Risks:<br />

The trees will die or be vandalised.<br />

Mitigation:<br />

A programme of replacement for dead or vandalised trees.<br />

Trees along the A23<br />

Planned Provision<br />

Mayor of London’s Street Tree<br />

Programme<br />

Lead<br />

Partner<br />

LBC<br />

Delivery Partners/<br />

Stakeholders<br />

LBC and Mayor of<br />

London<br />

Delivery Mechanism/<br />

Funding Source<br />

Cost (if known) Location 2011-<br />

2015<br />

Mayor of London £500k Boroughwide<br />

Y<br />

2016-<br />

2020<br />

2021- Relationship to CLP Strategic<br />

Policies: (3) Critical, (2)<br />

Necessary, (1) Contributory<br />

1<br />

53


SUSTAINABLE CITY PROGRAMME: ELECTRICITY SUBSTATIONS<br />

What?<br />

Delivery of an additional substation.<br />

Where?<br />

To be located in the Croydon North Area.<br />

When?<br />

Dependent on load demand justifications and availability of suitable land for a<br />

substation.<br />

Risks:<br />

No available site<br />

Mitigation:<br />

<br />

Ensure communication between Develop Croydon and Master Planning team<br />

to ensure availability of suitable land.<br />

Why?<br />

UK Power Networks advise that the additional primary grid substation will be<br />

required for any demand beyond the existing capacities of Croydon Grid, Croydon A,<br />

Croydon Central and East Croydon due to regeneration with the Croydon<br />

Metropolitan Centre.<br />

Stakeholder Engagement Since March 2012:<br />

UK Power have attended a number of meetings with Croydon Council regarding the<br />

development of electricity <strong>infrastructure</strong> development plans.<br />

Progress Since March 2012:<br />

Feasibility tests have taken place which suggests that the additional substation can<br />

be provided from the Ashburton Grid.<br />

Planned Provision<br />

Lead<br />

Partner<br />

Delivery Partners/<br />

Stakeholders<br />

Delivery<br />

Mechanism/<br />

Funding Source<br />

Cost (if<br />

known)<br />

Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to CLP Strategic<br />

Policies: (3) Critical, (2)<br />

Necessary, (1) Contributory<br />

Delivery of an additional substation<br />

UK Power<br />

Networks<br />

UK Power Networks<br />

UK Power<br />

Networks and<br />

developers<br />

TBC<br />

Boroughwide<br />

Y<br />

3<br />

54


SUSTAINABLE CITY PROGRAMME: SUSTAINABLE ENERGY<br />

What?<br />

Croydon Opportunity Area District Heating, CHP related to energy centres on NHS<br />

Capital Programme<br />

Where?<br />

Borough-wide<br />

When?<br />

By 2020<br />

Why?<br />

The strategic direction for provision of energy set by the Mayor requires that at least<br />

25% of London’s energy needs are provided by low carbon and decentralised energy<br />

sources by 2025. Croydon accepts and will make provision for this through provision<br />

of district energy schemes and other sources including solar photovoltaic, wind and<br />

other forms of renewable energy generation.<br />

Progress Since March 2012:<br />

Technical and commercial feasibility study completed for ‘core’ scheme comprising<br />

key public sector buildings. Key development sites have adopted centralised heating<br />

designs that are ‘connected ready’ for any future area wide heat network.<br />

Risks:<br />

<br />

Financial return of ‘core’ public scheme is currently marginal. No suitable site<br />

(or sites) has been allocated or identified to host an energy centre that would<br />

have capacity to supply a town centre scheme. Individual development sites<br />

most likely to proceed with site based energy provision and no<br />

interconnection.<br />

Mitigation:<br />

Council and GLA to continue to champion area-wide heat network.<br />

Stakeholder Engagement Since March 2012:<br />

The council engaged with GLA “Decentralised Energy Programme Delivery Unit” on<br />

scheme feasibility.<br />

Planned Provision<br />

COA District Heating, CHP related<br />

to energy centres on NHS Capital<br />

Programme<br />

Lead<br />

Partner<br />

LBC<br />

Delivery Partners/<br />

Stakeholders<br />

NHS, LDA, HCA,<br />

landowners and<br />

businesses<br />

Delivery Mechanism/<br />

Funding Source<br />

UK Power Networks<br />

and developers<br />

Cost (if known) Location 2011-<br />

2015<br />

£0.5m identified from<br />

LBC/external sources from<br />

2015/2016. other sources:<br />

energy service company,<br />

developers, investors,<br />

funding institutions, NHS<br />

Croydon Capital<br />

Capital Budget 2011/12-<br />

Boroughwide<br />

Y<br />

2016-<br />

2020<br />

Y<br />

2021- Relationship to CLP Strategic<br />

Policies: (3) Critical, (2)<br />

Necessary, (1) Contributory<br />

2<br />

55


SUSTAINABLE CITY PROGRAMME: WATER<br />

What?<br />

Reinforcement of strategic supplies and continuous renewal of water supply.<br />

Where?<br />

Borough-wide<br />

When?<br />

On-going<br />

Why?<br />

The supply of secure, safe and reliable water supply to Croydon for the period to<br />

2031 to meet the needs of the existing community and new growth is primarily the<br />

responsibility of two regulated water companies: Thames Water and Sutton and<br />

East Surrey Water PLCs. Both bring forward 5 year business plans for the conduct<br />

of and investment in their business. The companies through private investment,<br />

water pricing and rates (for unmetered supply) are confident that sufficient good<br />

water can be supplied to the Borough for the foreseeable future subject to the<br />

continuing approval of their Business Plans by Ofwat.<br />

Stakeholder Engagement Since March 2012:<br />

Sutton and East Surrey Water commenced work on its draft Water Resources<br />

Management Plan (WRMP) in 2012, which looks at the planning of Water Resources<br />

for the period 2015-2040. Up until March 2013, stakeholder engagement was<br />

limited to regular meetings with the Environment Agency’s local team and the<br />

Water Resources in the South East Group (WRSE). Members of the WRSE Group are<br />

DEFRA, The Environmental Agency, The Water Services Authority (Ofwat), Consumer<br />

Council for Water, Affinty Water, Portsmouth Water, South East Water, Southern<br />

Water, Sutton and East Surrey Water and Thames Water. The WRMP was<br />

published for comment on 12th May 2013 for a 12 week public consultation and as<br />

part of this consultation, a stakeholder workshop on 25th June 2013 took place to<br />

present the plan. The company is currently preparing a ‘Statement of Reponse’ to<br />

representations received as part of this consultation, which will be sent to the<br />

Secretary of State on 9th November 2013.<br />

Sutton and East Surrey Water commenced work on its Strategic Direction Statement<br />

and its draft business plan in late 2011. A Customer Challenge Group (CCG),<br />

responsible for ensuring that the Company is properly consulting with its customers<br />

was formed in 2012. The CCG includes the Environmental Agency, The Drinking<br />

Water Inspectorate, Natural England, Consumer Council for Water, local authority<br />

representation, business representation and the Customer Advisory Bereau.<br />

Stakeholder engagement has included regular meetings with the CCG, six customer<br />

focus groups in September 2012, online panels, presentations to local authorities<br />

and comments on the Draft Business Plan.<br />

Progress Since March 2012:<br />

Sutton and East Surrey Water is two thirds of the way through its AMP5 plan. With<br />

regards to water resources:<br />

Phase 2 of the uprating of the treatment works at Bough Beech was<br />

completed in April 2013.<br />

The Company is on programme to complete its AMP5 metering programme of<br />

32,000 meters by April 2015.<br />

The Company has already reached its water efficiency target for the AMP6<br />

period.<br />

Leakage has been maintained at, or below, the Ofwat target of 24.5 Ml/d,<br />

which is below the economic level of 27.3 Ml/d.<br />

Risks:<br />

<br />

<br />

Water Resource Management Plan: Secretary of State could not accept the<br />

Statement of Response to the representations made on the draft WRMP and<br />

the plan goes to public inquiry. This is a financial risk rather than a risk to<br />

water resources development, but could cause a delay in implementing the<br />

AMP6 (2015-20) programme.<br />

Periodic Review 2014– Business Plan: Ofwat may not accept the price<br />

increase proposed in the Final Business Plan. The most likely outcome of this<br />

would be the reduction in the proposed AMP6 programme.<br />

56


SUSTAINABLE CITY PROGRAMME: WATER<br />

Mitigation:<br />

<br />

<br />

Water Resources Management Plan: Sutton and East Surrey Water has<br />

attempted to ensure the plan is accepted. However, the risk is principally<br />

financial due to additional work and the possibility of a public inquiry. Any<br />

delays to the AMP6 programme would be inconvenient but should not affect<br />

the ability to supply as there is currently a surplus.<br />

Periodic Review 2014– Business Plan: If Ofwat does not accept the proposed<br />

price structure, there would be a need to re-prioritise expenditure to ensure<br />

the continued supply of a sufficient supply of safe, high quality drinking water.<br />

The risk to levels of service would increase marginally.<br />

Planned Provision<br />

Water supply reinforcement of strategic<br />

supplies and continuous renewal<br />

Lead<br />

Partner<br />

Thames Water,<br />

Sutton and<br />

East Surrey<br />

Water<br />

Delivery Partners/<br />

Stakeholders<br />

LBC Highways, TfL<br />

Delivery Mechanism/<br />

Funding Source<br />

Thames Water Asset<br />

Management Plan and<br />

funding, Sutton and East<br />

Surrey Asset<br />

Management Plan and<br />

funding<br />

Cost (if known) Location 2011-<br />

2015<br />

Costs are not available<br />

until the final<br />

determination by<br />

Ofwat is made public<br />

Boroughwide<br />

2016-<br />

2020<br />

Y Y Y<br />

2021- Relationship to CLP Strategic<br />

Policies: (3) Critical, (2)<br />

Necessary, (1) Contributory<br />

2<br />

57


SUSTAINABLE CITY PROGRAMME: SEWERAGE<br />

What?<br />

Maintenance/renewal where needed of sewerage <strong>infrastructure</strong>.<br />

Where?<br />

Borough-wide<br />

When?<br />

On-going<br />

Why?<br />

A systematic pattern of renewal will be needed for the sewerage network.<br />

Croydon’s waste water is treated at three major sewage works:<br />

1) Beddington treats 65% of flow. These works are fit for purpose although prior<br />

to 2015 investment in sludge de watering will take place.<br />

2) Long Reach on the Thames at Dartford takes 30% of the flow and has recently<br />

been subject to major upgrade. A sludge treatment upgrade to the STW is in<br />

the process of being delivered.<br />

3) Crossness in Bexley takes the majority of other flows and it will also see<br />

investment in dewatering plant. The Thames Tideway Quality Improvements<br />

upgrade is nearing completion and a sludge treatment upgrade is also being<br />

delivered.<br />

Stakeholder Engagement Since March 2012:<br />

During September 2013 consultation took place on the draft five year business plan<br />

for domestic customers, businesses and organisations. Thames Water have spoken<br />

to over 10,000 customers to get their feedback, through focus groups, online and<br />

telephone surveys and in-depth interviews. Proposals are also shared with an<br />

independent customer challenge group, which includes regulators and<br />

representatives from business, local government and organisations such as Age UK<br />

and the Consumer Council for Water.<br />

Progress Since March 2012:<br />

Since 2010, 44 miles of worn-out sewers have been replaced across London. A<br />

£40million upgrade is currently underway at Long Reach Sewage works, which will<br />

enable the site to deal with the increased sewage resulting from population growth<br />

up until 2021. A £220m upgrade at Crossness is due to be completed in 2014. A<br />

£250million programme started in 2012 to modernise and enhance sludge<br />

treatment at a number of sewage works, including Crossness and Beddington.<br />

Risks:<br />

<br />

<br />

<br />

Heavy rain periods can lead to unexpected sewerage flooding.<br />

Increased population growth and associated new housing developments will<br />

put increased pressure on sewers and sewage works.<br />

Aging equipment will increase maintenance requirements.<br />

Mitigation:<br />

<br />

<br />

<br />

Ensure sewers can cope as well as possible with heavy rainfall.<br />

Maintain upgrade programmes at sewerage works to be able to deal with<br />

increased populations.<br />

Managing the rate at which assets deteriorate and effect on customer service.<br />

Planned Provision<br />

Maintenance/renewal where needed of<br />

sewerage <strong>infrastructure</strong> and new<br />

sewerage <strong>infrastructure</strong> to support<br />

growth<br />

Lead<br />

Partner<br />

Thames Water<br />

Delivery Partners/<br />

Stakeholders<br />

LBC Highways, TfL,<br />

Developers<br />

Delivery Mechanism/<br />

Funding Source<br />

Thames Water Asset<br />

Management Plan and<br />

funding<br />

Developer funding<br />

Cost (if known) Location 2011-<br />

2015<br />

TBC<br />

Boroughwide<br />

2016-<br />

2020<br />

Y Y Y<br />

2021- Relationship to CLP Strategic<br />

Policies: (3) Critical, (2)<br />

Necessary, (1) Contributory<br />

2<br />

58


SUSTAINABLE CITY PROGRAMME: ELECTRICITY SUPPLY<br />

What?<br />

Maintenance, renewal and replacement where needed of electricity supply<br />

<strong>infrastructure</strong>.<br />

Where?<br />

Borough-wide<br />

When?<br />

On-going with projects scheduled up to 2023.<br />

Why?<br />

The local network of supply for electricity is owned and operated under licence by<br />

UK Power Networks. According to UK Power Networks, the adoption of Croydon<br />

Local Plan: Strategic Policies and the proposed regeneration of the Croydon<br />

Opportunity Area is expected to result in 22MW of new demand. A further feature<br />

of the supply network over the period of the plan will be the introduction of local<br />

generation on homes and commercial building through local wind turbines and<br />

photovoltaic systems.<br />

Progress Since March 2012:<br />

Four projects have been approved and are in progress or complete:<br />

Replacement of GT3 and GT4 at Beddington 132/33kV is now complete.<br />

Purley Local T1 and T2 replacement is now complete.<br />

Cable installation is complete and the switchroom construction is in progress<br />

for Coulsdon ITC.<br />

The Norbury Primary transfer load to Croydon B is to be completed by 2014.<br />

Further projects are scheduled up to 2023 across the Borough.<br />

Risks:<br />

Further assessts will be identified as having poor health.<br />

Mitigation:<br />

<br />

Future projects should be continued to be identified by UK Power Networks<br />

in their Regional Development Plan.<br />

Stakeholder Engagement Since March 2012:<br />

UK Power have attended a number of meetings with Croydon Council regarding the<br />

development of electricity <strong>infrastructure</strong> development plans.<br />

Planned Provision<br />

Lead<br />

Partner<br />

Delivery Partners/<br />

Stakeholders<br />

Delivery<br />

Mechanism/<br />

Funding Source<br />

Cost (if<br />

known)<br />

Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to CLP Strategic<br />

Policies: (3) Critical, (2)<br />

Necessary, (1) Contributory<br />

Maintenance/renewal where needed of electricity supply<br />

<strong>infrastructure</strong><br />

UK Power<br />

Networks,<br />

National<br />

Grid<br />

LBC Highways, TfL<br />

UK Power<br />

Networks<br />

Capital<br />

Programme<br />

TBC<br />

Boroughwide<br />

Y Y Y<br />

3<br />

59


SUSTAINABLE CITY PROGRAMME: REGENERATION OF NEW ADDINGTON<br />

What?<br />

Rationalisation of public sector assets, new community centre, library relocation,<br />

leisure facilities and public realm enhancements.<br />

Where?<br />

New Addington<br />

When?<br />

By 2020<br />

Why?<br />

The area is one of the most deprived in Croydon (in the top 2% IMD nationally) and<br />

has been included in the London Plan as a strategic area for regeneration. In the<br />

long term, New Addington has enormous potential to develop as a future urban<br />

core, co-existing with and complementing the economy of the main town centre. Its<br />

transport <strong>infrastructure</strong>, reasonable rents and proximity to Biggin Hill Airport and<br />

aerospace industry supply chain in Surrey make it a future contender for growth. In<br />

the short term, it is anticipated that modest improvements will trigger the<br />

momentum required for sustainable economic growth.<br />

Stakeholder Engagement Since March 2012:<br />

An informal public consultation leaflet was issued in early 2013 to gauge the<br />

public’s opinion of the public realm enhancements to Central Parade undertaken<br />

under the Outer London Fund (OLF) and the initial proposals for further public realm<br />

works to Central Parade through Mayor’s Regeneration Funding (MRF) which has<br />

been secured.<br />

Progress Since March 2012:<br />

The OLF works have been completed and MRF has been secured to undertake<br />

further public realm enhancement works at Central Parade. Funding has also been<br />

secured to undertake a feasibility study of the entire Central Parade environment,<br />

including the leisure provision and community uses on the western side of Central<br />

Parade and the row of shops and parking on the Eastern side.<br />

Risks:<br />

<br />

<br />

Town and village green cannot be reorganised, limiting the potential of the<br />

site.<br />

Limited support by the community.<br />

Mitigation:<br />

<br />

<br />

London Borough of Croydon will seek legal advice regarding TVG<br />

reorganisation.<br />

A very thorough engagement programme will take place.<br />

Planned Provision<br />

Rationalisation of public sector assets,<br />

new community centre, library relocation<br />

and public realm enhancements<br />

Lead<br />

Partner<br />

Delivery Partners/<br />

Stakeholders<br />

LBC GLA, LBC LBC- £30K<br />

Delivery Mechanism/<br />

Funding Source<br />

GLA MRF– £800K<br />

GLA OLF- £500K<br />

Cost (if known) Location 2011-<br />

2015<br />

£1.330m Addington Y<br />

2016-<br />

2020<br />

2021- Relationship to CLP Strategic<br />

Policies: (3) Critical, (2)<br />

Necessary, (1) Contributory<br />

2<br />

Leisure Centre LBC LBC, Fusion LBC- £30K<br />

GLA MRF– £800K<br />

GLA OLF- £500K<br />

60<br />

£17m Addington Y<br />

2


SUSTAINABLE CITY PROGRAMME: EAST CROYDON MASTERPLAN<br />

What?<br />

Public realm enhancements<br />

Where?<br />

East Croydon<br />

When?<br />

By 2020<br />

Why?<br />

East Croydon station is Croydon's front door. It is also the busiest station in Britain<br />

outside Central London, with direct links to Gatwick Airport, London Victoria and<br />

London Bridge in 15 minutes. The East Croydon Masterplan brings together<br />

developments, including Stanhope Schroder's Ruskin Square and Menta's Cherry<br />

Orchard Road, to create a new urban quarter with an improved transport<br />

interchange and railway station. Enhanced public realm will tie together the various<br />

proposals, and connect the area with improvements planned for Wellesley Road<br />

and College Green. New station entrances to the north-west and north-east will<br />

increase capacity and better provide for Croydon’s forthcoming developments.<br />

Stakeholder Engagement Since March 2012:<br />

One formal Masterplan Implementation Group meeting has been held. Engagement<br />

and formal consultation on East Croydon Interchange public realm took place in<br />

summer 2013. A range of extensive engagement has taken place through pre-apps<br />

and <strong>delivery</strong> projects.<br />

Progress Since March 2012:<br />

East Croydon Bridge is completed and now open. New western station entrance and<br />

exit opened in summer 2013. Other stations improvements are underway. McAslan<br />

procured and public realm designs at Stage E. Stanhope’s Lansdowne Link opened in<br />

December and Lansdowne Road improvements are due to be completed in January<br />

2014. Phase 1 Ruskin Square residential reserved matters approved.<br />

Risks:<br />

<br />

<br />

<br />

Construction logistics between projects.<br />

Agreement between various TfL modes.<br />

Lose of funding or compromising quality if delayed.<br />

Mitigation:<br />

<br />

<br />

<br />

<br />

CDH undertaking logistics planning.<br />

Good programme management.<br />

Maintain good communications.<br />

Maintain design input from LBC.<br />

Planned Provision<br />

Lead<br />

Partner<br />

Delivery Partners/<br />

Stakeholders<br />

Phase 1 public realm improvements LBC LBC, Network Rail and<br />

private sector<br />

Delivery Mechanism/<br />

Funding Source<br />

Mayor Scheme funding,<br />

MRF, CIL, Capital<br />

Programme, National Rail<br />

and private sector<br />

Cost (if known) Location 2011-<br />

2015<br />

£5.4 (doesn’t include<br />

cost of bridge station<br />

improvements, public<br />

realm on private land<br />

e.g Ruskin Square)<br />

COA<br />

Y<br />

2016-<br />

2020<br />

2021- Relationship to CLP Strategic<br />

Policies: (3) Critical, (2)<br />

Necessary, (1) Contributory<br />

3<br />

Phase 2/3 public realm improvements LBC LBC, Network Rail and<br />

private sector<br />

Mayor Scheme funding,<br />

MRF, CIL, Capital<br />

Programme, National Rail<br />

and private sector<br />

£13.7m COA Y<br />

3<br />

61


SUSTAINABLE CITY PROGRAMME: WEST CROYDON MASTERPLAN<br />

What?<br />

Public realm enhancements.<br />

Where?<br />

West Croydon<br />

When?<br />

Phase 1 by 2015 and Phase 2 by 2020.<br />

Why?<br />

West Croydon has all the ingredients of being a fantastic place. Its excellent<br />

transport <strong>infrastructure</strong>, established rich mix of uses, built heritage and diverse local<br />

community - along with its adjacency to the commercial heart of central Croydon -<br />

all add up to a development area with great potential. The arrival of the East<br />

London Line in summer 2010 has put Croydon on the tube map for the first time.<br />

The West Croydon Masterplan takes a careful, coordinated approach to ensuring<br />

the <strong>delivery</strong> of a new station and interchange, optimised development potential and<br />

a transformed and well-connected public realm and provides a narrative that sets<br />

the scene for a cluster of new buildings.<br />

Stakeholder Engagement Since March 2012:<br />

One formal Masterplan Implementation Group meeting has been held. Engagement<br />

and formal consultation on West Croydon Interchange public realm took place in<br />

summer 2013. A range of extensive engagement has taken place through pre-apps<br />

and <strong>delivery</strong> projects.<br />

Progress Since March 2012:<br />

New station entrance on Station Road open.<br />

East procured and designs developed to RIBA Stage E.<br />

TfL funding secured for remodelling of bus station.<br />

Pre-app underway on Barratt station road scheme.<br />

Risks:<br />

<br />

<br />

<br />

Construction logistics between projects.<br />

Agreement between various TfL modes.<br />

Lose of funding or compromising quality if delayed.<br />

Mitigation:<br />

<br />

<br />

<br />

<br />

CDH undertaking logistics planning.<br />

Good programme management.<br />

Maintain good communications.<br />

Maintain design input from LBC.<br />

Planned Provision<br />

Phase 1 public realm<br />

improvements<br />

Lead<br />

Partner<br />

LBC<br />

Delivery Partners/<br />

Stakeholders<br />

LBC, MRF, Network Rail<br />

and TfL<br />

Delivery<br />

Mechanism/<br />

Funding Source<br />

LBC, Network Rail<br />

and TfL<br />

Cost (if known) Location 2011-<br />

2015<br />

£4.9m (not including TfL funding<br />

for bus station and public realm<br />

delivered on private land.<br />

COA<br />

Y<br />

2016-<br />

2020<br />

2021- Relationship to CLP Strategic<br />

Policies: (3) Critical, (2)<br />

Necessary, (1) Contributory<br />

3<br />

Phase 2/3 public realm<br />

improvements<br />

LBC<br />

LBC, MRF, Network Rail<br />

and TfL<br />

LBC, MRF,<br />

Network Rail and<br />

TfL<br />

£14.1m (approx) COA Y<br />

3<br />

62


SUSTAINABLE CITY PROGRAMME: FAIRFIELD MASTERPLAN<br />

What?<br />

Remodelled Fairfield Halls and a range of public realm improvements.<br />

Where?<br />

Croydon Opportunity Area<br />

When?<br />

Phase 1 by 2015 and Phase 2/3 to follow<br />

Why?<br />

The Fairfield Masterplan has been prepared jointly by Croydon Council and local<br />

stakeholders to realise the area's potential, and rediscover its role as a thriving<br />

regional destination for culture and learning. A master planning team led by Make<br />

and Kinnear Landscape Architects developed proposals through over a year of<br />

engagement and consultation with local groups. The Masterplan provides a phased<br />

long-term framework for delivering the transformation of the area. Crucially, it also<br />

involves proposals for making change happen now.<br />

Progress Since March 2012:<br />

Fairfield Masterplan has been adopted. Funding has been secured for College Green<br />

Paving improvements. Procurement of consultation team for Fairfield Halls<br />

underway but currently in abeyance pending further instruction.<br />

Risks:<br />

<br />

A large proportion relies on private or public/private developments coming<br />

forward.<br />

Mitigation:<br />

<br />

Work with the Council’s Housing Development and Regeneration Team to<br />

promote redevelopment of privately owned sites.<br />

Stakeholder Engagement Since March 2012:<br />

Regular Stakeholder Project Boards, as well as one Masterplan Implementation<br />

Group meeting held. Engagement and formal consultation on Fairfield Masterplan.<br />

A range of extensive engagement through pre-apps and <strong>delivery</strong> projects.<br />

Planned Provision<br />

Lead<br />

Partner<br />

Delivery Partners/<br />

Stakeholders<br />

Delivery Mechanism/<br />

Funding Source<br />

63<br />

Cost (if known) Location 2011-<br />

2015<br />

Phase 1– public realm improvements LBC LBC £560,000 COA Y<br />

Phase 2– public realm improvements and<br />

remodelling of Fairfield Halls<br />

LBC LBC £10.2m for public<br />

realm and<br />

£33.7m for<br />

Fairfield Halls<br />

2016-<br />

2020<br />

COA Y Y Y<br />

2021- Relationship to CLP Strategic<br />

Policies: (3) Critical, (2)<br />

Necessary, (1) Contributory<br />

3<br />

3


SUSTAINABLE CITY PROGRAMME: MID CROYDON MASTERPLAN<br />

What?<br />

A range of transport and public realm improvements.<br />

Where?<br />

Croydon Opportunity Area<br />

When?<br />

Phase 1 by 2015 and Phase 2/3 to follow.<br />

Why?<br />

The Mid Croydon area is vital to the success of regeneration plans for Croydon<br />

Metropolitan Centre and the borough as a whole. Substantial development,<br />

including up to 7,500 new homes, improved transport, and public realm<br />

improvements are expected to deliver major change. The Masterplan addresses:<br />

buildings to be retained, new buildings, housing, employment, retail, leisure,<br />

education and community, along with public realm and <strong>infrastructure</strong>.<br />

Progress Since March 2012:<br />

Connect 2 crossings on Park Lane and flyover have been implemented. Bernard<br />

Weatherhill House has been completed. Pre-app for Taberner House is underway. St<br />

George’s House L&G planning consent.<br />

Risks:<br />

<br />

<br />

Uncertainty around Minerva/ Delancey property/ development ambitions<br />

Risk of permitted development residential conversions affecting Masterplan<br />

ambitions.<br />

Mitigation:<br />

Continued dialogue with stakeholders.<br />

Stakeholder Engagement Since March 2012:<br />

One formal Masterplan implementation group meeting has been held. Pre-app and<br />

application meetings for St George’s House and Taberner House. Developer<br />

consultations on Taberner House and St George’s House.<br />

Planned Provision<br />

Lead<br />

Partner<br />

Delivery Partners/<br />

Stakeholders<br />

Phase 1 public realm improvements LBC LBC, CCURV, L&G,<br />

Minerva, Delancey and<br />

Chaseville<br />

Phase 2/3 public realm improvements LBC LBC, CCURV, L&G,<br />

Minerva, Delancey and<br />

Chaseville<br />

Delivery<br />

Mechanism/<br />

Funding Source<br />

Private sector,<br />

LBC, MRF,<br />

Sustrans, TfL<br />

Private sector,<br />

LBC, MRF,<br />

Sustrans, TfL<br />

Cost (if<br />

known)<br />

Location 2011-<br />

2015<br />

£0.9m COA Y<br />

2016-<br />

2020<br />

£21.4m COA Y Y Y<br />

2021- Relationship to CLP Strategic<br />

Policies: (3) Critical, (2)<br />

Necessary, (1) Contributory<br />

3<br />

3<br />

64


SUSTAINABLE CITY PROGRAMME: OLD TOWN MASTERPLAN<br />

What?<br />

A range of transport and public realm improvements.<br />

Where?<br />

Croydon Opportunity Area<br />

Risks:<br />

Uncertainty regarding future funding from central and local government and the<br />

Mayor of London.<br />

Mitigation:<br />

Seek out funding opportunities including CIL.<br />

When?<br />

On-going<br />

Why?<br />

The Old Town Masterplan will show how the area of Old Town could be improved<br />

for people living, working and shopping in the area over the next 20 years. It will be<br />

a supplementary planning document that sets the parameters for development of<br />

the buildings, streets and public spaces in Old Town and also look at how<br />

movement in, out and around the area could be improved by all modes of<br />

transport. It will also recommend how the heritage assets of the area can be<br />

preserved, enhanced and celebrated. The Old Town Masterplan is funded by the<br />

Mayor of London and Croydon Council.<br />

Stakeholder Engagement Since March 2012:<br />

Stakeholder Engagement has included monthly Old Town Masterplan Stakeholder<br />

Project Board meetings; an Ideas Workship in March 2013; and and Emerging Ideas<br />

Exhibition, 2013.<br />

Progress Since March 2012:<br />

£1.5million funding has been granted for High Streets Improvements.<br />

Location of Old Town in Croydon Opportunity<br />

Area<br />

Planned Provision<br />

Lead<br />

Partner<br />

Delivery Partners/<br />

Stakeholders<br />

Delivery<br />

Mechanism/<br />

Funding Source<br />

Cost (if<br />

known)<br />

Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to CLP Strategic<br />

Policies: (3) Critical, (2)<br />

Necessary, (1) Contributory<br />

A range of transport and public realm improvements LBC LBC, Stakeholder<br />

Project Board<br />

CIL/S106 £11.7m COA Y Y Y<br />

2<br />

65


SUSTAINABLE CITY PROGRAMME: CONNECTED CROYDON<br />

What?<br />

A programme of public works to improve Croydon’s streets, squares and open<br />

spaces<br />

Where?<br />

Borough-wide<br />

When?<br />

By 2015<br />

Why?<br />

The Council has successfully secured £50m of funding, including £23m from the<br />

London Mayor's Regeneration Fund, to upgrade the town centre and create the<br />

ideal conditions for investment. This will lead to a more prosperous, thriving<br />

Croydon. Connected Croydon is needed to create an attractive environment that<br />

will secure inward investment and establish the right conditions for a growing<br />

residential community, as well as for those who work in and visit Croydon.<br />

Stakeholder Engagement Since March 2012:<br />

The Connected Croydon programme is being delivered in nine distinct work<br />

streams, each with its own communication plan that states who we engage with,<br />

when and how. Key stakeholders are invited to contribute to the project’s<br />

development at a minimum of two key stages.<br />

Connected Croydon information board.<br />

Progress Since March 2012:<br />

The council’s customer engagement web-page details the extensive public<br />

involvement that has taken place. This includes eight public exhibitions, regular<br />

attendance at residents and traders group meetings, press releases, a tumblr<br />

website and information boards attached to hoardings across town.<br />

66


SUSTAINABLE CITY PROGRAMME: CONNECTED CROYDON<br />

Planned Provision<br />

Lead<br />

Partner<br />

Delivery Partners/Stakeholders<br />

Delivery Mechanism/Funding<br />

Source<br />

Cost (if<br />

known)<br />

Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to CLP Strategic<br />

Policies: (3) Critical, (2)<br />

Necessary, (1) Contributory<br />

East Croydon LBC LBC, Network London, TfL,<br />

Homes and Communities<br />

Agency, Royal Mail Group,<br />

Network Rail, LBC Capital<br />

Programme, Growth Area Fund,<br />

S106, MRF, TfL Biking Boroughs,<br />

£25,240,0<br />

00<br />

COA Y Y<br />

3<br />

Menta, Stanhope Schroders<br />

TfL LIP Major Scheme<br />

West Croydon<br />

LBC, LBC, GLA, Network Rail, TfL,<br />

Network Rail Barratt Homes, CBRE Investors,<br />

Mapeley, Portman Square<br />

Holdings, Purespace Group, St<br />

Michael and All Angels Church,<br />

Canmoor<br />

High Streets LBC LBC, GLA, TfL, Local business and<br />

communities<br />

MRF £4.9m COA Y<br />

MRF, TfL Local Implementation £10m COA Y<br />

Plan, Growth Area Fund<br />

3<br />

3<br />

Wellesley Road Crossings LBC LBC, GLA, TfL MRF, LBC Capital Programme,<br />

Growth Area Fund, S106, GLA,<br />

HPDG<br />

Connect 2 LBC LBC, TfL, Sustrans TfL LIP Greenways, LBC Capital<br />

Programme, TfL Sustrans, S106<br />

£6.3m COA Y<br />

£3.3m COA Y<br />

3<br />

3<br />

Fair Field LBC LBC, Bridgewater Property,<br />

CCURV, Croydon College,<br />

Fairfield Halls Trustees,<br />

Magistrates Court, Metropolitan<br />

Property, Network Rail, NCP,<br />

Terrace Hill, TfL<br />

LBC Capital Programme, £2.2m COA Y<br />

3<br />

67


SUSTAINABLE CITY PROGRAMME: CROYDON SPORTS ARENA<br />

What?<br />

Redevelopment of Croydon Sports Arena.<br />

Where?<br />

South Norwood and Woodside.<br />

When?<br />

After 2021.<br />

Progress Since March 2012:<br />

The Council’s Education Department has undertaken a feasibility study to determine<br />

the options for providing a new school alongside an upgraded sports arena.<br />

Risks:<br />

<br />

The available funding could be insufficient to deliver full range of<br />

improvements.<br />

Why?<br />

The borough has one athletics arena in the north of the borough ‘Croydon Sports<br />

Arena’. The arena has an 8 lane all-weather 400m running track with a centre field<br />

and training area in good condition. However, the changing accommodation is in<br />

need of an upgrade. Croydon Council needs to rectify identified inadequacies and<br />

meet identified shortfalls through improvements to the current pitch stock and<br />

ancillary facilities. It is important that the levels of pitch provision are protected,<br />

maintained and enhanced to secure provision now and in the future.<br />

Mitigation:<br />

<br />

The feasibility study should prioritise the improvement measures to ensure<br />

the most pressing are delivered.<br />

Stakeholder Engagement Since March 2012:<br />

The Council has been in discussion with both Croydon Harriers and Croydon Athletic<br />

Football Club and is undertaking a public engagement exercise to consider the<br />

possibility of providing a new school alongside an upgraded sports arena.<br />

Planned Provision<br />

Lead<br />

Partner<br />

Delivery Partners/<br />

Stakeholders<br />

Delivery<br />

Mechanism/<br />

Funding Source<br />

Cost (if<br />

known)<br />

Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to CLP Strategic<br />

Policies: (3) Critical, (2)<br />

Necessary, (1) Contributory<br />

Provision of new school and upgrading of Croydon Sports<br />

Arena<br />

LBC<br />

LBC, Croydon Harriers<br />

Athletics Club &<br />

Croydon Football Club<br />

South<br />

Norwood<br />

and<br />

Woodside<br />

Y Y Y<br />

3<br />

68


SUSTAINABLE CITY PROGRAMME: SPORTS AND LEISURE FACILITIES<br />

What?<br />

Delivery of 3 new leisure centres in the borough.<br />

Where?<br />

Waddon, New Addington and unspecified site in the south of the borough.<br />

Progress Since March 2012:<br />

The new Waddon Leisure Centre is now open. An updated needs assessment is<br />

being prepared to look at demand in the south of the borough. The proposed new<br />

leisure centre for New Addington is part of an on-going discussion relating to the<br />

redevelopment of the wider area.<br />

When?<br />

By 2020<br />

Why?<br />

The provision of swimming pools and sports hall space is part of the Council’s vision<br />

for a ‘safe, healthy and prosperous and sustainable future for the whole<br />

community’. This project is informed by the Sports Facilities Needs Assessment (May<br />

2009).<br />

Stakeholder Engagement Since March 2012:<br />

Discussions between the Council and a number of providers (including the proposed<br />

developer of the existing Purley Pool site) have taken place.<br />

Planned Provision<br />

Lead<br />

Partner<br />

Delivery<br />

Partners/<br />

Stakeholders<br />

Delivery Mechanism/<br />

Funding Source<br />

Cost (if<br />

known)<br />

Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to CLP Strategic<br />

Policies: (3) Critical, (2)<br />

Necessary, (1) Contributory<br />

New “wet and dry” leisure centre in the south of the<br />

borough<br />

LBC LBC Sport England, Capital<br />

Bids, Big Lottery Fund,<br />

Football Foundation,<br />

£14.1m<br />

South of<br />

borough<br />

Y<br />

3<br />

S106/CIL<br />

Refurbishment of New Addington Leisure Centre LBC LBC Capital programme £14.3m Addington Y<br />

3<br />

69


SUSTAINABLE CITY PROGRAMME: SPORTS AND SWIMMING FACILITIES (ACADEMIES)<br />

What?<br />

The upgrading, maintenance and improvement of the sports and swimming facilities<br />

within the borough’s Academies.<br />

Where?<br />

Borough-wide<br />

When?<br />

By 2020<br />

Why?<br />

On-going maintenance and improvement of the sports and swimming facilities<br />

within the borough’s Academies is necessary to ensure they continue to contribute<br />

to the health and well-being of children in Croydon.<br />

Stakeholder Engagement Since March 2012:<br />

Consultation has been undertaken as part of the associated planning applications in<br />

addition to discussions between the Council and the Academy Trust.<br />

Progress Since March 2012:<br />

The sports centre at Quest Academy Selsdon is being rebuilt in a partnership<br />

between the school and the Council and is due to open in September 2014.<br />

Planned Provision<br />

Lead<br />

Partner<br />

Delivery Partners/<br />

Stakeholders<br />

Delivery<br />

Mechanism/<br />

Funding Source<br />

Cost (if<br />

known)<br />

Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to CLP Strategic<br />

Policies: (3) Critical, (2)<br />

Necessary, (1) Contributory<br />

Upgrading, maintenance and improvement of the sports<br />

and swimming facilities within the borough’s Academies<br />

LBC LBC Boroughwide<br />

Y<br />

Y<br />

2<br />

70


CARING CITY PROGRAMME<br />

71


CARING CITY PROGRAMME NHS CROYDON CAPITAL PROGRAMME<br />

What?<br />

Redevelopment of Woodside Health Centre to expand services.<br />

Where?<br />

Woodside Health Centre<br />

Progress Since March 2012:<br />

The redevelopment of Woodside Health Centre is at the project definition stage of<br />

scoping and timescale.<br />

When?<br />

By 2015<br />

Why?<br />

NHS Croydon evaluated its estate in a 2009 review, and has now finalised an Estates<br />

Strategy to optimise utilisation and deliver improved facilities in line with need. In<br />

some cases this means changing the function of sites depending on the more<br />

appropriate administrative or clinical use. This is a major issue which needs<br />

addressing both internally by NHS Croydon, as well as in partnership with the<br />

Council to ensure its <strong>infrastructure</strong> needs can be integrated with the spatial planning<br />

process.<br />

Stakeholder Engagement Since March 2012:<br />

In order to undertake the Estates Strategy, the Primary Care Trust worked in<br />

partnership with the Council, South London & Maudesley Foundation Trust and<br />

Mayday Healthcare Trust to take a strategic approach to the overall estates needs<br />

of the borough.<br />

Planned Provision<br />

Lead<br />

Partner<br />

Delivery Partners/<br />

Stakeholders<br />

Delivery Mechanism/<br />

Funding Source<br />

Cost (if known) Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to CLP Strategic<br />

Policies: (3) Critical, (2)<br />

Necessary, (1) Contributory<br />

Redevelopment of Woodside Health<br />

Centre to expand services<br />

NHS Croydon<br />

NHS Croydon, LBC,<br />

Healthcare for London<br />

LIFT, planning obligations,<br />

DoH NHS allocations<br />

TBC<br />

South<br />

Norwood<br />

and<br />

Y<br />

2<br />

Woodside<br />

72


CARING CITY PROGRAMME: NHS CROYDON CAPITAL PROGRAMME<br />

What?<br />

New build New Addington GP-led Health Centre.<br />

Where?<br />

New Addington<br />

Progress Since March 2012:<br />

This site is expected to need modernisation in the 2015-2025 period and has not yet<br />

reached project initiation stage.<br />

When?<br />

By 2020<br />

Why?<br />

NHS Croydon evaluated its estate in a 2009 review, and has now finalised an Estates<br />

Strategy to optimise utilisation and deliver improved facilities in line with need. In<br />

some cases this means changing the function of sites depending on the more<br />

appropriate administrative or clinical use. This is a major issue which needs<br />

addressing both internally by NHS Croydon, as well as in partnership with the<br />

Council to ensure its <strong>infrastructure</strong> needs can be integrated with the spatial planning<br />

process.<br />

Stakeholder Engagement Since March 2012:<br />

In order to undertake the Estates Strategy, the Primary Care Trust worked in<br />

partnership with the Council, South London & Maudesley Foundation Trust and<br />

Mayday Healthcare Trust to take a strategic approach to the overall estates needs<br />

of the borough.<br />

Planned Provision<br />

Lead<br />

Partner<br />

Delivery Partners/<br />

Stakeholders<br />

Delivery Mechanism/<br />

Funding Source<br />

Cost (if known) Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to CLP Strategic<br />

Policies: (3) Critical, (2)<br />

Necessary, (1) Contributory<br />

New build New Addingotn GP-led Health<br />

Centre<br />

NHS Croydon<br />

NHS Croydon, LBC,<br />

Healthcare for London<br />

LIFT, planning obligations,<br />

DoH NHS allocations<br />

TBC Addington Y<br />

2<br />

73


CARING CITY PROGRAMME: NHS CROYDON CAPITAL PROGRAMME<br />

What?<br />

Redevelopment of Croydon University Hospital Site, with the provision of an Urgent<br />

Care Centre<br />

Where?<br />

Croydon University Hospital site.<br />

When?<br />

By 2015<br />

Why?<br />

NHS Croydon evaluated its estate in a 2009 review, and has now finalised an Estates<br />

Strategy to optimise utilisation and deliver improved facilities in line with need. In<br />

some cases this means changing the function of sites depending on the more<br />

appropriate administrative or clinical use. This is a major issue which needs<br />

addressing both internally by NHS Croydon, as well as in partnership with the<br />

Council to ensure its <strong>infrastructure</strong> needs can be integrated with the spatial planning<br />

process.<br />

Stakeholder Engagement Since March 2012:<br />

In order to undertake the Estates Strategy, the Primary Care Trust worked in<br />

partnership with the Council, South London & Maudesley Foundation Trust and<br />

Mayday Healthcare Trust to take a strategic approach to the overall estates needs<br />

of the borough.<br />

Planned Provision<br />

Lead<br />

Partner<br />

Delivery Partners/<br />

Stakeholders<br />

Delivery Mechanism/<br />

Funding Source<br />

Cost (if known) Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to CLP Strategic<br />

Policies: (3) Critical, (2)<br />

Necessary, (1) Contributory<br />

Redevelopment of Croydon University<br />

Hospital Site, with the provision of an<br />

Urgent Care Centre<br />

NHS Croydon<br />

NHS Croydon, LBC,<br />

Healthcare for London<br />

LIFT, planning obligations,<br />

DoH NHS allocations<br />

TBC<br />

Broad<br />

Green and<br />

Selhurst<br />

Y<br />

2<br />

74


CARING CITY PROGRAMME: NHS CROYDON CAPITAL PROGRAMME<br />

What?<br />

Redevelopment and refurbishment of Purley Hospital site.<br />

Where?<br />

Purley Hospital<br />

When?<br />

By 2015<br />

Why?<br />

NHS Croydon evaluated its estate in a 2009 review, and has now finalised an Estates<br />

Strategy to optimise utilisation and deliver improved facilities in line with need. In<br />

some cases this means changing the function of sites depending on the more<br />

appropriate administrative or clinical use. This is a major issue which needs<br />

addressing both internally by NHS Croydon, as well as in partnership with the<br />

Council to ensure its <strong>infrastructure</strong> needs can be integrated with the spatial<br />

planning process.<br />

Stakeholder Engagement Since March 2012:<br />

In order to undertake the Estates Strategy, the Primary Care Trust worked in<br />

partnership with the Council, South London & Maudesley Foundation Trust and<br />

Mayday Healthcare Trust to take a strategic approach to the overall estates needs<br />

of the borough.<br />

Progress Since March 2012:<br />

The refurbishment of the site began in the autumn of 2012, with the site reopening<br />

in July 2013. As part of the refurbishment a new physiotherapy and eye disease<br />

testing clinic have opened, along with an expanded imaging service.<br />

75


CARING CITY PROGRAMME: NEW BURIAL GROUND<br />

What?<br />

Provision of a new burial ground.<br />

Where?<br />

Greenlawns Cemetery in Tandridge<br />

When?<br />

By 2015<br />

Why?<br />

In 2009/10 the Council commissioned a study for future requirements and the<br />

recommendations estimate a need for 10,000 interments for the period up to 2031.<br />

Additional land is required to meet this demand. Recommendations for the location<br />

of new burial grounds within the borough were considered by the Council but were<br />

found to be unsuitable following detailed investigation regarding archaeology and<br />

groundwater. Therefore the Council is seeking to bring forward a site next to the<br />

Greenlawns Cemetery in Tandridge.<br />

Progress Since March 2012:<br />

Following the conclusion of detailed site investigations of potential new cemeteries<br />

in Croydon, the decision was taken to pursue an extension to the Council owned<br />

cemetery in the neighbouring borough of Tandridge. Pre-application enquiries have<br />

been completed and a planning application has been submitted.<br />

Risks:<br />

<br />

Planning permission for an extension to Greenlawns Cemetery may be<br />

refused.<br />

Mitigation:<br />

<br />

The Council has undertaken significant pre-application enquiries to reduce<br />

the risk of permission being refused.<br />

Stakeholder Engagement Since March 2012:<br />

Colleagues from Croydon’s Bereavement Services Team have met with officers from<br />

adjoining boroughs including Tandridge District Council to discuss the proposal and<br />

to consider the scope for cross borough burial arrangements. In September 2013,<br />

Croydon’s Chief Executive met and discussed the proposed application within the<br />

Tandridge Chief Executive.<br />

Planned Provision<br />

Provision of a new burial ground on land<br />

adjoining Greenlawns Cemetry<br />

Lead<br />

Partner<br />

LBC<br />

Delivery Partners/<br />

Stakeholders<br />

LBC, Tandridge District<br />

Council<br />

Delivery Mechanism/<br />

Funding Source<br />

£75k identified from LBC<br />

Capital Budget<br />

Cost (if known) Location 2011-<br />

2015<br />

£1.04million Tandridge Y<br />

2016-<br />

2020<br />

2021- Relationship to CLP Strategic<br />

Policies: (3) Critical, (2)<br />

Necessary, (1) Contributory<br />

1<br />

76


CARING CITY PROGRAMME: SUPPORTED HOUSING FACILITIES<br />

What?<br />

Modernisation of supported housing schemes<br />

Where?<br />

Boroughwide<br />

When?<br />

By 2015<br />

Why?<br />

Housing support enables vulnerable people to maintain their independence and to<br />

lead a normal life. It provides people with the support, skills and direction they need<br />

to help them get back on their feet and achieve and sustain independent<br />

living. Investment in housing support reduces costs in homelessness, health<br />

services, tenancy failure, crime and residential care. Housing adaptations help older<br />

people stay more healthy and mobile and help reduce admissions to, length of stay<br />

in and delayed discharge from hospital. Croydon has a range of need for supported<br />

housing services from three main groups of people:<br />

• older people<br />

• adults with support needs<br />

• adults at risk of social exclusion<br />

Progress Since March 2012:<br />

Review of the older people housing strategy has started which will set out proposals<br />

for the future of sheltered and extra care housing for older people. New supported<br />

housing scheme for people with learning disabilities and people with physical<br />

disabilities at Southbridge Road is on site and due to open in 2014. Eldon Housing<br />

Association has started the refurbishment of the Westdene extra care sheltered<br />

housing scheme. South London YMCA has commenced redevelopment of the<br />

millennium foyer site to provide new supported housing for homeless young<br />

people. South London YMCA opened Alexandra House supported housing scheme<br />

for vulnerable single people and Ingram Court supported housing schemes for<br />

homeless young people in 2012.Rolling programme of review and recommissioning<br />

of supported housing contracts has continued.<br />

Risks:<br />

<br />

Insufficient supported housing available to meet growing demands and the<br />

requirements of cost efficiency programmes .<br />

Mitigation:<br />

<br />

Identification of strategic needs, liaison with GLA to secure capital funding<br />

and liaison with registered providers to secure GLA capital funding.<br />

Stakeholder Engagement Since March 2012:<br />

1) Supporting People Provider Group and Steering Group- quarterly<br />

2) Consultation event with people with learning difficulties– July 2013<br />

Planned Provision<br />

Modernisation of support housing<br />

schemes<br />

Lead<br />

Partner<br />

Delivery Partners/<br />

Stakeholders<br />

Delivery Mechanism/<br />

Funding Source<br />

Cost (if known) Location 2011-<br />

2015<br />

LBC LBC Boroughwide<br />

Y<br />

2016-<br />

2020<br />

2021- Relationship to CLP<br />

Strategic<br />

Policies: (3) Critical, (2)<br />

Necessary, (1) Contributory<br />

2<br />

77


CARING CITY PROGRAMME: METROPOLITAN POLICE FACILITIES<br />

What?<br />

The new MOPAC/MPS Estates Strategy sets out fundamental changes to the<br />

Metropolitan Police’s property portfolio in response to new ways of delivering<br />

policing in the borough.<br />

Where?<br />

Borough-wide<br />

When?<br />

By 2016<br />

Why?<br />

The recent consultation highlighted the public’s wish to see more officers on patrol.<br />

The purpose of this strategy is to help the Metropolitan Police to do that by saving<br />

money while improving the remaining estate.<br />

Stakeholder Engagement Since March 2012:<br />

Between January 2013 and March 2013 a public consultation exercise was<br />

undertaken.<br />

Progress Since March 2012:<br />

The new MOPAC/MPS Estates Strategy for 2013 to 2016 was adopted in May 2013.<br />

Details are set out below and on the next page.<br />

Planned Provision<br />

Lead<br />

Partner<br />

Delivery<br />

Partners/<br />

Stakeholders<br />

Delivery<br />

Mechanism/<br />

Funding Source<br />

Cost (if<br />

known)<br />

Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to CLP Strategic<br />

Policies: (3) Critical, (2)<br />

Necessary, (1) Contributory<br />

Front Counters<br />

(Conventional police station Front Counters offering all<br />

policing services with secure and private facilities)<br />

Met<br />

Police<br />

Met Police,<br />

MOPAC<br />

CMC (this Front Counter will<br />

operate on a 24/7 basis)<br />

Windmill Rd Custody Centre<br />

Y<br />

Y<br />

2<br />

Contact Points<br />

(Contact Points are locations for non-urgent face-toface<br />

contact, where the public can meet their local<br />

police at regular known times)<br />

Met<br />

Police<br />

Met Police,<br />

MOPAC<br />

Norbury, Thornton Heath, New<br />

Addington, Purley, Addington and<br />

Crystal Palace<br />

Y<br />

Y<br />

2<br />

Deployment Bases<br />

(Deployment Bases are where the borough’s Safer<br />

Neighbourhood Teams, Borough Tasking Teams and/or<br />

Emergency Response and Patrol officers and PCSOs<br />

start and end their tours of duty)<br />

Met<br />

Police<br />

Met Police,<br />

MOPAC<br />

CMC, Addington and Crystal<br />

Palace<br />

Y<br />

Y<br />

2<br />

Other Safer Neighbourhood Team Locations<br />

(As well as the locations shown above, there may be<br />

other bases where the borough’s Safer Neighbourhood<br />

Met<br />

Police<br />

Met Police,<br />

MOPAC<br />

Coulsdon, Addiscombe, Selsdon,<br />

Shirley, Crystal Palace and CMC<br />

Y<br />

Y<br />

2<br />

Teams work. These will only be occupied when officers<br />

and PCSOs are not out on patrol and are not public<br />

78


CARING CITY PROGRAMME: METROPOLITAN POLICE FACILITIES (cont’d)<br />

79


CARING CITY PROGRAMME: AMBULANCE SERVICE FACILITIES<br />

What?<br />

Replacement for Croydon Ambulance Station<br />

Where?<br />

North/Central Croydon<br />

When?<br />

To be confirmed<br />

Why?<br />

The Croydon base at Primrose Lane, Shirley, includes offices, workshops and<br />

parking. Its building stock is old and held to be poorly located in relation to the<br />

principal areas of need in north and central Croydon, The operational service<br />

believes that the Croydon depot possibly merged with the South Croydon operation<br />

should be located in north/central Croydon close to a major road. Following the<br />

opening of the new Purley ambulance station, the most pressing requirement is for<br />

the replacement of the Croydon station. This will require site provision for offices,<br />

changing rooms, unit buildings, stores, garages, infection control facilities and<br />

operational and non-operational parking.<br />

Stakeholder Engagement Since March 2012:<br />

No update available for this project.<br />

Progress Since March 2012:<br />

No update available for this project.<br />

Planned Provision<br />

Lead<br />

Partner<br />

Delivery Partners/<br />

Stakeholders<br />

Delivery Mechanism/<br />

Funding Source<br />

Cost (if known) Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to CLP Strategic<br />

Policies: (3) Critical, (2)<br />

Necessary, (1) Contributory<br />

Replacement for Croydon Ambulance<br />

Station<br />

London<br />

Ambulance<br />

Service<br />

London Ambulance<br />

Service<br />

Shirley<br />

2<br />

80


CARING CITY PROGRAMME: LONDON FIRE BRIGADE FACILITIES<br />

What?<br />

Replacement for Purley Fire Station<br />

Where?<br />

Purley<br />

When?<br />

By 2015<br />

Why?<br />

There is a 10 station £57 million Private Finance Initiative (PFI) project to provide<br />

new facilities which are designed to accommodate the new generation of fire<br />

appliances and meet the current needs of the London Fire Brigade. The London Fire<br />

and Emergency Planning Authority (LFEPA) are working with the PFI model to bring<br />

additional Central Government Capital Investment into the London Fire Brigade to<br />

transform the service for flexibility in the future and upgrade some of its stations.<br />

20% of stations have been categorised as not suitable for the operational<br />

requirement of a modern emergency service. Amongst these, Purley Fire Station has<br />

been identified as a high priority for redevelopment.<br />

Stakeholder Engagement Since March 2012:<br />

London Fire Brigade have engaged with London Borough of Croydon’s ‘Call for Sites’<br />

exercise in relation to Purley Fire Station.<br />

Progress Since March 2012:<br />

Detailed planning permission has been obtained. Construction is due to start on site<br />

circa third quarter 2014 as part of phase 2 of the PFI project. Completion is<br />

estimated to be approximately 12-15 months thereafter. The new fire station is<br />

anticipated to be fully operational in the fourth quarter of 2015.<br />

Risks:<br />

The <strong>delivery</strong> of the new fire station is guaranteed under the PFI project.<br />

Mitigation:<br />

Not Applicable.<br />

Planned Provision<br />

Lead<br />

Partner<br />

Delivery Partners/<br />

Stakeholders<br />

Delivery Mechanism/<br />

Funding Source<br />

Cost (if known) Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to CLP Strategic<br />

Policies: (3) Critical, (2)<br />

Necessary, (1) Contributory<br />

Replacement for Purley Fire Station<br />

London Fire<br />

Brigade<br />

London Fire Brigade Purley Y<br />

2<br />

81


INFRASTRUCTURE DELIVERY PLAN: ENTREPRISING CITY SCHEDULE<br />

Planned Provision Lead Partner Delivery Partners/<br />

Stakeholder<br />

Delivery Mechanism/<br />

Funding Source<br />

Cost (if known) Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to CLP<br />

Strategic<br />

Policies: (3) Critical,<br />

(2) Necessary, (1)<br />

Contributory<br />

Wi-Fi Broadband<br />

enhancement<br />

LBC<br />

LBC, GLA, BT, CCURV,<br />

Croydon BID, Croydon<br />

College<br />

LBC Capital Programme £1.9million COA and then across the whole<br />

borough<br />

Y<br />

3<br />

Enterprise centres for<br />

creative and cultural<br />

industries<br />

LBC<br />

LBC, ACAVA, CCURV,<br />

ACME, Croydon College<br />

LBC Capital Programme,<br />

S106, CIL<br />

TBC<br />

COA, Crystal Palace, Portland<br />

Road/South, Norwood and Purley<br />

Y<br />

Y<br />

2<br />

Bring vacant commercial<br />

and retail premises into<br />

productive use<br />

LBC<br />

LBC, ACAVA, Village<br />

Underground,<br />

Meanwhile Space CIC<br />

LBC Capital Funding, S106,<br />

CIL<br />

TBC Borough-wide Y Y Y<br />

2<br />

Total Costs : £1.9m<br />

82


INFRASTRUCTURE DELIVERY PLAN: LEARNING CITY SCHEDULE<br />

Planned Provision Lead Partner Delivery Partners/<br />

Stakeholder<br />

Delivery Mechanism/Funding Source Cost (if known) Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to CLP<br />

Strategic<br />

Policies: (3) Critical,<br />

(2) Necessary, (1)<br />

Contributory<br />

New school at Westways Centre<br />

(3FE)<br />

New school at Aberdeen Road<br />

(2FE)<br />

Ryelands Primary School-relocation<br />

of existing school (2FE)<br />

West Thorton Primary Academ–<br />

new annexe (2FE)<br />

LBC CFL LBC Education Estates Strategy TBC Broad Green and Selhurst Y<br />

LBC CFL LBC Education Estates Strategy TBC COA Y<br />

LBC CFL LBC Education Estates Strategy TBC South Norwood and Woodside Y<br />

LBC CFL LBC Education Estates Strategy TBC Broad Green and Selhurst Y<br />

3<br />

3<br />

3<br />

3<br />

St Joseph’s Catholic Infants and<br />

Juniors– expansion (1FE)<br />

LBC CFL LBC Education Estates Strategy TBC Crystal Palace and Upper Norwood Y<br />

Ark Oval– expansion (1FE) LBC CFL LBC Education Estates Strategy TBC Addiscombe Y<br />

Kingsley Primary– expansion (1FE) LBC CFL LBC Education Estates Strategy TBC Broad Green and Selhurst Y<br />

Croydon Arena- (6FE) LBC CFL LBC Education Estates Strategy £29.3m South Norwood and Woodside Y Y<br />

Expansion at Resource Base 1 at<br />

Croydon Arena–10 to 15 places<br />

LBC CFL LBC Education Estates Strategy £780,000 South Norwood and Woodside Y<br />

3<br />

3<br />

3<br />

3<br />

1<br />

Expansion of Resource Base 2 at<br />

Croydon General Hospital Site– 15<br />

places<br />

Expansion of Resource Base 3– 15<br />

places<br />

New School at Tennison Road-50<br />

places<br />

LBC CFL LBC Education Estates Strategy TBC COA Y<br />

LBC CFL LBC Education Estates Strategy TBC TBC Y<br />

LBC CFL LBC Education Estates Strategy £7m South Norwood and Woodside Y<br />

1<br />

1<br />

3<br />

Masters provision at the University<br />

Centre<br />

Croydon College<br />

LBC, GLA, HE Partner,<br />

Croydon College<br />

TBC TBC COA Y Y<br />

3<br />

Partnership with Sussex University<br />

to open an Innovation Centre<br />

Croydon College<br />

Croydon College,<br />

Sussex University, GLA<br />

TBC TBC COA Y Y<br />

3<br />

Total Costs : £37.08m<br />

83


INFRASTRUCTURE DELIVERY PLAN: CREATIVE CITY SCHEDULE<br />

Planned Provision Lead Partner Delivery Partners/<br />

Stakeholder<br />

Delivery Mechanism/<br />

Funding Source<br />

Cost (if known) Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to CLP<br />

Strategic<br />

Policies: (3) Critical,<br />

(2) Necessary, (1)<br />

Contributory<br />

Renewed Fairfield Halls<br />

complex<br />

LBC LBC, Fairfield Halls LBC Capital Budget<br />

2011/12-2017/18<br />

£33.7m COA Y Y<br />

3<br />

Total Costs : £33.7m<br />

84


INFRASTRUCTURE DELIVERY PLAN: CONNECTED CITY SCHEDULE<br />

Planned Provision Lead Partner Delivery Partners/<br />

Stakeholder<br />

Delivery Mechanism/Funding Source Cost (if known) Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to CLP<br />

Strategic<br />

Policies: (3) Critical,<br />

(2) Necessary, (1)<br />

Contributory<br />

East Croydon Station:<br />

Additional platforms<br />

Improvement of Selhurst,<br />

Sanderstead and Norwood<br />

Junction and other stations<br />

Network Rail Network Rail £80m COA Y<br />

Network Rail TfL Network Rail, TfL, LBC £400k Borough-wide Y Y<br />

2<br />

1<br />

Rail Capacity: 12 coach<br />

trains on Central London-<br />

Brighton line<br />

Thames-link/<br />

Southern Railway<br />

Network Rail,<br />

Thameslink<br />

Thameslink Investment Programme TBC Borough-wide Y<br />

2<br />

Rail Capacity: More<br />

frequent services, or more<br />

capacity on existing<br />

services<br />

Additional rolling stock (up<br />

to 4 units planned)<br />

Rail Capacity: Railtrack<br />

junction improvements<br />

and by-passes<br />

Tramlink: Tram stop<br />

improvements<br />

Tramlink: Track capacity<br />

improvements<br />

Tramlink: Dingwall Road<br />

Loop<br />

Tramlink: extensions to<br />

Crystal Palace<br />

Road Network: Bridge<br />

Strengthening<br />

Road Network: Congestion<br />

relief measures<br />

Thames-link/<br />

Southern Railway<br />

Network Rail,<br />

Thameslink<br />

Thameslink Investment Programme<br />

Strategic Business Plan, London and<br />

South East Rail Utilisation Study,<br />

Operational Business Plans<br />

Current best estimates up to<br />

£1bn<br />

Borough-wide Y Y<br />

TfL LBC, TfL TfL, LBC, CIL £20m Borough-wide Y Y<br />

Thames-link/<br />

Southern Railway<br />

Network Rail,<br />

Thameslink<br />

Thameslink Investment Programme<br />

Strategic Business Plan, London and<br />

South East Rail Utilisation Study,<br />

Operational Business Plans<br />

Current best estimates up to<br />

£1bn<br />

Borough-wide Y Y<br />

TfL LBC, TfL TfL, LBC, CIL £2.5m Borough-wide Y Y<br />

TfL LBC, TfL TfL, LBC, CIL £2.5m Borough-wide Y<br />

TfL LBC, TfL TfL, LBC, CIL £21m COA Y<br />

TfL LBC, TfL TfL, LBC, CIL £150m North Y Y<br />

Network Rail/LBC LBC, TfL, Network Rail LIP, CIL £750k per year Borough-wide Y<br />

LBC, TfL LBC, TfL TfL, CIL, LBC funding £1.8m Borough-wide Y<br />

2<br />

3<br />

2<br />

2<br />

2<br />

2<br />

1<br />

3<br />

2<br />

85


INFRASTRUCTURE DELIVERY PLAN:CONNECTED SCHEDULE CITY SCHEDULE<br />

Planned Provision Lead Partner Delivery Partners/Stakeholder Delivery Mechanism/Funding Source Cost (if known) Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to CLP<br />

Strategic<br />

Policies: (3) Critical,<br />

(2) Necessary, (1)<br />

Contributory<br />

Road Network: Soakaway<br />

Maintenance and Replacement–<br />

Highways Drainage<br />

LBC LBC, TfL, Environment Agency £1.7m from LBC Capital Budget<br />

2011/12-2015/16<br />

£1.75m Borough-wide Y<br />

2<br />

Road Network: Minor highway<br />

improvements<br />

LBC LBC, TfL Capital Programme, CIL £250k per year Borough-wide Y Y<br />

1<br />

Road Network: Electric car<br />

<strong>infrastructure</strong><br />

LBC, TfL LBC, TfL Mayor’s Transport Strategy £5k per station<br />

(estimated capital costs)<br />

Borough-wide Y Y Y<br />

1<br />

Street lighting PFI programme LBC LBC, London Borough of<br />

Lewisham and Skanska<br />

Infrastructure Services<br />

PFI for street lights £40m Borough-wide Y Y<br />

1<br />

Car park improvements and<br />

rationalisation<br />

LBC NCP/private sector LBC Transport Strategy TBC Borough-wide Y Y Y<br />

Street waymarking and signage LBC TfL Public Realm Strategy £3m COA Y Y Y<br />

Purley Town Centre: Change to<br />

gyratory<br />

Bus system: Accessibility and safety<br />

improvements<br />

TfL LBC TfL TBC Purley Y<br />

TfL Bus operators and TfL Bus operator plans, Mayor’s<br />

Transport Strategy and Revenue<br />

Programme<br />

Bus information improvements TfL TfL Borough Transport Strategy, Mayor’s<br />

Transport Strategy<br />

£100k per year Borough-wide Y Y Y<br />

£250k Borough-wide Y<br />

Bus priority measures TfL LBC, TfL TfL £1.9m Borough-wide Y Y Y<br />

Bus stands/standbys TfL, LBC LBC, TfL TfL £3m per year COA Y Y<br />

Improvements to West Croydon bus<br />

station<br />

TfL TfL TfL £3m COA Y Y<br />

2<br />

1<br />

2<br />

2<br />

2<br />

2<br />

2<br />

2<br />

Refurbishment of London cycling<br />

network and provision of Quietways<br />

TfL LBC, TfL Borough Transport Strategy, Mayor’s<br />

Vision for Cycling, LIP<br />

TBC Borough-wide Y<br />

2<br />

Cycling provision at major stations Network Rail LBC, TfL, Network Rail Master Plans, Public Realm Strategy,<br />

Planning Obligations, Mayor’s Vision<br />

for Cycling, LIP, TOCs, National Rail<br />

86<br />

TBC Borough-wide Y Y<br />

2


INFRASTRUCTURE DELIVERY PLAN: SCHEDULE CONNECTED CITY SCHEDULE<br />

Planned Provision Lead Partner Delivery Partners/<br />

Stakeholder<br />

Delivery Mechanism/Funding<br />

Source<br />

Cost (if known) Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to CLP<br />

Strategic<br />

Policies: (3) Critical,<br />

(2) Necessary, (1)<br />

Contributory<br />

Completion of Connect 2<br />

and Greenway routes<br />

Cycling measures at key<br />

junctions<br />

TfL LBC, TfL, Sustrans TfL, LBC, CIL TBC Borough-wide Y Y<br />

TfL/LBC LBC, TfL, Sustrans TfL, LBC, CIL TBC Borough-wide Y Y<br />

2<br />

2<br />

Other cycle links LBC LBC, TfL, Sustrans LIP2 or Connect 2 programme TBC through LIP2 or<br />

Conenct 2 programme<br />

Borough-wide Y Y<br />

2<br />

Freight consolidation centre LBC Private sector Private sector, CIL TBC South of the borough Y<br />

1<br />

East Croydon– Lansdowne<br />

Road Taxi Rank<br />

Purley Town Centre: Road<br />

network and public realm<br />

LBC Private external TfL £100K COA Y<br />

LBC TfL TfL £7.4m Purley Y Y<br />

1<br />

2<br />

Total Costs : £366.45m<br />

87


INFRASTRUCTURE DELIVERY PLAN: SCHEDULE SUSTAINABLE CITY SCHEDULE<br />

Planned Provision Lead Partner Delivery Partners/<br />

Stakeholder<br />

Delivery Mechanism/Funding<br />

Source<br />

Cost (if known) Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to CLP<br />

Strategic<br />

Policies: (3) Critical,<br />

(2) Necessary, (1)<br />

Contributory<br />

Improvements to the borough’s play areas LBC LBC, DCSF DCSF, LBC Capital Programme,<br />

S106, HLF, other funding<br />

streams<br />

£2.4m Borough-wide Y Y<br />

Connect 2, Wandle Park to Lloyd Park LBC Sustrans, TfL LBC, TfL, Sustrans £3,303,104 COA and surrounding Y<br />

East Croydon Bridge Network Rail LBC, Network Rail,<br />

private sector<br />

LBC, Network Rail, private<br />

sector<br />

£6m (LBC<br />

contribution to<br />

£20m total)<br />

Wellesley Road Phase 1 LBC TfL, MoL TfL, MoL, S106 £4,535,524 COA Y<br />

Wellesley Road Phase 2 (Lansdowne Road) LBC MoL MoL £1,750,000 COA Y<br />

College Green Paving LBC Croydon College LBC Capital Programme, CIL £553,986 COA Y<br />

West Croydon Public Realm LBC TfL, MoL LBC Capital Programme, CIL £4,934,060 COA Y<br />

COA<br />

Y<br />

2<br />

3<br />

3<br />

3<br />

3<br />

2<br />

3<br />

East Croydon Public Realm LBC TfL, MoL LBC Capital Programme, CIL,<br />

TfL, MoL<br />

£5,546,429 COA Y<br />

3<br />

High Streets (South End) LBC TfL, MoL LBC Capital Programme, CIL,<br />

GAF, MoL, TfL<br />

£2,934,711 COA Y<br />

High Streets (London Road, Old Town, Central) LBC TfL, MoL MoL £6,156,480 COA Y<br />

New Addington Central Parade Phase 2 LBC TfL, MoL MoL £864,000 Addington Y<br />

George Street tram stop LBC TfL, MoL MoL £878,620 COA Y<br />

South Norwood Public Realm LBC TfL TfL £241,005 S Norwood & Woodside Y<br />

3<br />

3<br />

3<br />

3<br />

3<br />

Billington Hill – Eastern Station Link LBC LBC, Network Rail,<br />

private sector<br />

LBC, Network Rail, private<br />

sector<br />

£3.4m COA Y<br />

3<br />

88


INFRASTRUCTURE DELIVERY PLAN: SCHEDULE SUSTAINABLE CITY SCHEDULE<br />

Planned Provision Lead Partner Delivery Partners/<br />

Stakeholder<br />

Delivery<br />

Mechanism/<br />

Funding Source<br />

Cost (if known) Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021<br />

-<br />

Relationship to CLP Strategic<br />

Policies: (3) Critical, (2) Necessary, (1)<br />

Contributory<br />

Wandle Road bus stand LBC TfL TfL £1.22m COA Y<br />

2<br />

Public Realm: Future Tier 2 including Wandle Park<br />

pavilion, North End, COA subway removal, minihollands<br />

/ cycle projects, district centres and future<br />

Legible London Future Phases<br />

Woodland and Tree Management Plan: Highway tree<br />

inspection/works,woodland health/safety inspection,<br />

tree planting and woodland inspection and works<br />

£68m approx Borough-wide Y Y Y<br />

LBC LBC LBC £690,000 Borough-wide Y<br />

3<br />

1<br />

Connect 2, National Cycling Network 21, N-S link<br />

Norbury– Kenley Addington, other lower priority<br />

routes & Emerald Necklace, Sth Norwood Greenways<br />

LBC TfL, PCT, Sustrans TfL, LBC Capital<br />

Programme, S106<br />

TBC Borough-wide Y<br />

2<br />

Improve access to nature across London. Areas<br />

include Queens Road Cemetery, Melfort Avenue<br />

Recreation Ground, Norbury Hall Park, Addiscombe<br />

Railway Park, Purley Way East Playing Fields, Pollards<br />

Hill, Haling Grove, Wandle Park, Duppas Hill, Norbury<br />

Park/Brook, Cane Hill West and Waddon Ponds.<br />

GLA<br />

LB Croydon, Mayor of<br />

London<br />

Mayor of London,<br />

LDA<br />

N/A Borough-wide Y Y Y<br />

1<br />

Community food and flower growing initiatives LBC Mayor of London Mayor of London,<br />

LBC<br />

N/A Borough-wide Y<br />

1<br />

Management of the rare chalk downland,<br />

development of an extensive series of trails,<br />

woodland management and pond restoration<br />

London<br />

Downland<br />

Partnership<br />

LBC, LB Sutton, Surrey CC,<br />

Corp’ of London, Reigate<br />

& Banstead BC, Tandridge<br />

DC, Countryside Agency<br />

LBC, LDA, TfL,<br />

Network Rail, GAF,<br />

private developers<br />

Borough-wide<br />

Y<br />

1<br />

Re-opening of sites at South Norwood Lake and<br />

Pollards Hill, including upgrade of existing allotment<br />

facilities.<br />

LBC<br />

LBC, owners and<br />

occupiers<br />

LBC Capital<br />

funding, owners<br />

and occupiers<br />

Borough-wide<br />

Y<br />

1<br />

Surface Water Management Plan and Extensive<br />

Soakaway & Ancillary Drainage Cleaning Programme<br />

LBC<br />

LBC, Environment Agency<br />

and Croydon Fire Brigade<br />

DEFRA TBC Borough-wide Y Y Y<br />

1<br />

Mayor of London’s Street Tree Programme LBC LBC and Mayor of London Mayor of London £500k Borough-wide Y<br />

Delivery of an additional substation<br />

UK Power<br />

Networks<br />

UK Power Networks<br />

UK Power Networks<br />

and developers<br />

89<br />

TBC Borough-wide Y<br />

1<br />

3


INFRASTRUCTURE DELIVERY PLAN: SCHEDULE SUSTAINABLE CITY SCHEDULE<br />

Planned Provision Lead Partner Delivery Partners/<br />

Stakeholder<br />

Delivery Mechanism/Funding Source Cost (if known) Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021<br />

-<br />

Relationship to CLP Strategic<br />

Policies: (3) Critical, (2)<br />

Necessary, (1) Contributory<br />

COA District Heating, CHP<br />

related to energy centres on<br />

NHS Capital Programme<br />

LBC<br />

NHS, LDA, HCA,<br />

landowners and<br />

businesses<br />

UK Power Networks and developers<br />

£.5m identified from LBC/<br />

external sources from Capital<br />

Budget 2011/12-2015/2016.<br />

other sources: energy service<br />

company, developers, investors,<br />

funding institutions, NHS<br />

Croydon Capital Programme 4<br />

Borough-wide Y Y<br />

2<br />

Water supply reinforcement of<br />

strategic supplies and<br />

continuous renewal<br />

Thames Water,<br />

Sutton and East<br />

Surrey Water<br />

LBC Highways, TfL<br />

Thames Water Asset Management<br />

Plan and funding, Sutton and East<br />

Surrey Asset Management Plan and<br />

funding<br />

Costs are not available until the<br />

final determination by Ofwat is<br />

made public<br />

Borough-wide Y Y Y<br />

2<br />

Maintenance/renewal where<br />

needed of sewerage<br />

<strong>infrastructure</strong> and new<br />

sewerage <strong>infrastructure</strong> to<br />

support growth<br />

Thames Water<br />

LBC Highways, TfL,<br />

Developers<br />

Thames Water Asset Management<br />

Plan and funding. Developer funding<br />

TBC Borough-wide Y Y Y<br />

2<br />

Maintenance/renewal where<br />

needed of electricity supply<br />

<strong>infrastructure</strong><br />

UK Power<br />

Networks, National<br />

Grid<br />

LBC Highways, TfL<br />

UK Power Networks Capital<br />

Programme<br />

TBC Borough-wide Y Y Y<br />

3<br />

New Addington Masterplan:<br />

Rationalisation of public sector<br />

assets, new community centre,<br />

library relocation and public<br />

realm enhancements<br />

LBC GLA, LBC LBC- £30K<br />

GLA MRF– £800K<br />

GLA OLF- £500K<br />

£1.330m Addington Y<br />

2<br />

New Addington Masterplan:<br />

Leisure Centre<br />

LBC LBC, Fusion LBC- £30K<br />

GLA MRF– £800K<br />

GLA OLF- £500K<br />

£17m Addington Y<br />

2<br />

East Croydon Masterplan:<br />

Phase 1 public realm<br />

improvements<br />

LBC<br />

LBC, Network Rail and<br />

private sector<br />

Mayor Scheme funding, MRF, CIL,<br />

Capital Programme, National Rail and<br />

private<br />

£5.4 (doesn’t include cost of<br />

bridge station improvements,<br />

public realm on private land e.g<br />

Ruskin Square)<br />

COA<br />

Y<br />

3<br />

90


INFRASTRUCTURE DELIVERY PLAN: SCHEDULE SUSTAINABLE CITY SCHEDULE<br />

Planned Provision Lead Partner Delivery Partners/Stakeholder Delivery Mechanism/Funding Source Cost (if known) Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to<br />

CLP Strategic<br />

Policies: (3)<br />

Critical, (2)<br />

Necessary, (1)<br />

Contributory<br />

East Croydon Masterplan: Phase 2/3<br />

public realm improvements<br />

LBC LBC, Network Rail and private sector Mayor Scheme funding, MRF, CIL, Capital<br />

Programme, National Rail and private<br />

£13.7m COA Y<br />

3<br />

West Croydon Masterplan: Phase 1<br />

public realm improvements<br />

West Croydon Masterplan: Phase 2/3<br />

public realm improvements<br />

Fairfield Masterplan: Phase 1– public<br />

realm improvements<br />

LBC LBC, MRF, Network Rail and TfL LBC, Network Rail and TfL £4.9m (not including<br />

TfL funding for bus<br />

station and public<br />

realm delivered on<br />

private land.<br />

LBC LBC, MRF, Network Rail and TfL LBC, MRF, Network Rail and TfL £14.1m (approx) COA Y Y<br />

LBC LBC £560,000 COA Y<br />

COA<br />

Y<br />

3<br />

3<br />

3<br />

Fairfield Masterplan: Phase 2– public<br />

realm improvements and remodelling<br />

of Fairfield Halls<br />

LBC LBC £10.2m for public<br />

realm and £33.7m for<br />

Fairfield Halls<br />

COA Y Y Y<br />

3<br />

Mid Croydon Masterplan: Phase 1<br />

public realm improvements<br />

LBC<br />

LBC, CCURV, L&G, Minerva,<br />

Delancey and Chaseville<br />

Private sector, LBC, MRF, Sustrans, TfL £0.9m COA Y<br />

3<br />

Mid Croydon Masterplan: Phase 2/3<br />

public realm improvements<br />

LBC<br />

LBC, CCURV, L&G, Minerva,<br />

Delancey and Chaseville<br />

Private sector, LBC, MRF, Sustrans, TfL £21.4m COA Y Y Y<br />

3<br />

Old Town Masterplan: A range of<br />

transport and public realm<br />

improvements<br />

LBC LBC, Stakeholder Project Board CIL, S106 £11.7m COA Y Y Y<br />

Connected Croydon: East Croydon LBC LBC, Network London, TfL, Homes<br />

and Communities Agency, Royal<br />

Mail Group, Menta, Stanhope<br />

Network Rail, LBC Capital Programme,<br />

Growth Area Fund, S106, MRF, TfL Biking<br />

Boroughs, TfL LIP Major Scheme<br />

£25,240,000 COA Y Y<br />

2<br />

3<br />

Connected Croydon: West Croydon LBC, Network Rail LBC, GLA, Network Rail, TfL, Barratt<br />

Homes, CBRE Investors, Mapeley,<br />

Portman Square Holdings,<br />

Purespace Group, St Michael and<br />

MRF £4.6m COA Y<br />

3<br />

91


INFRASTRUCTURE DELIVERY PLAN: SUSTAINABLE CITY SCHEDULE<br />

Planned Provision Lead Partner Delivery Partners/Stakeholder Delivery Mechanism/Funding Source Cost (if known) Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to<br />

CLP Strategic<br />

Policies: (3)<br />

Critical, (2)<br />

Necessary, (1)<br />

Contributory<br />

Croydon Connected: High Streets LBC LBC, GLA, TfL, Local business and<br />

communities<br />

Croydon Connected: Wellesley Road<br />

Crossings<br />

MRF, TfL Local Implementation Plan,<br />

Growth Area Fund<br />

LBC LBC, GLA, TfL MRF, LBC Capital Programme, Growth<br />

Area Fund, S106, GLA, HPDG<br />

Croydon Connected: Connect 2 LBC LBC, TfL, Sustrans TfL LIP Greenways, LBC Capital<br />

Programme, TfL Sustrans, S106<br />

£10m COA Y<br />

£6.6m COA Y<br />

£3.4m COA Y<br />

3<br />

3<br />

3<br />

Connected Croydon: Fair Field LBC LBC, Bridgewater Property, CCURV,<br />

Croydon College, Fairfield Halls<br />

Trustees, Magistrates Court,<br />

Metropolitan Property, Network<br />

Rail, NCP, Terrace Hill, TfL<br />

LBC Capital Programme, £2.2m COA Y<br />

3<br />

Provision of new school and<br />

upgrading of Croydon Sports Arena<br />

New “wet and dry” leisure centre in<br />

the south of the borough<br />

Refurbishment of New Addington<br />

Leisure Centre<br />

Upgrading, maintenance and<br />

improvement of the sports and<br />

swimming facilities within the<br />

borough’s Academies<br />

LBC<br />

LBC, Croydon Harriers Athletics Club<br />

& Croydon Football Club<br />

LBC LBC Sport England, Capital Bids, Big Lottery<br />

Fund, Football Foundation, S106/CIL<br />

South Norwood<br />

and Woodside<br />

Y Y Y<br />

£14.1m South Y<br />

LBC LBC Capital programme £14.3m Addington Y<br />

LBC LBC Borough-wide Y Y<br />

3<br />

3<br />

3<br />

2<br />

Total Costs : £343.73m<br />

92


INFRASTRUCTURE DELIVERY PLAN: SCHEDULE CARING CITY SCHEDULE<br />

Planned Provision Lead Partner Delivery Partners/<br />

Stakeholder<br />

Delivery Mechanism/<br />

Funding Source<br />

Cost (if known) Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to CLP<br />

Strategic<br />

Policies: (3) Critical,<br />

(2) Necessary, (1)<br />

Contributory<br />

Redevelopment of<br />

Woodside Health Centre to<br />

expand services<br />

NHS Croydon<br />

NHS Croydon, LBC,<br />

Healthcare for<br />

London<br />

LIFT, planning obligations,<br />

DoH NHS allocations<br />

TBC South Norwood and Woodside Y<br />

2<br />

New build New Addington<br />

GP-led Health Centre<br />

NHS Croydon<br />

NHS Croydon, LBC,<br />

Healthcare for<br />

London<br />

LIFT, planning obligations,<br />

DoH NHS allocations<br />

TBC Addington Y<br />

2<br />

Redevelopment of<br />

Croydon University<br />

Hospital Site , with the<br />

provision of an Urgent<br />

Care Strategy<br />

NHS Croydon<br />

NHS Croydon, LBC,<br />

Healthcare for<br />

London<br />

LIFT, planning obligations,<br />

DoH NHS allocations<br />

TBC Broad Green and Selhurst Y<br />

2<br />

Provision of a new burial<br />

ground on land adjoining<br />

Greenlawns Cemetery<br />

LBC<br />

LBC, Tandridge District<br />

Council<br />

£75k identified from LBC<br />

Capital Budget<br />

£1.04million Tandridge Y<br />

1<br />

Modernisation of<br />

supported housing<br />

schemes<br />

LBC LBC Borough-wide Y<br />

2<br />

Replacement for<br />

Croydon Ambulance<br />

Station<br />

London Ambulance<br />

Service<br />

London Ambulance<br />

Service<br />

Shirley<br />

2<br />

Replacement for Purley<br />

Fire Station<br />

London Fire Brigade London Fire Brigade Purley Y<br />

2<br />

93


INFRASTRUCTURE DELIVERY PLAN: SCHEDULE CARING CITY SCHEDULE<br />

Planned Provision Lead Partner Delivery Partners/<br />

Stakeholder<br />

Delivery Mechanism/<br />

Funding Source<br />

Cost (if<br />

known)<br />

Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to CLP<br />

Strategic<br />

Policies: (3) Critical,<br />

(2) Necessary, (1)<br />

Contributory<br />

Front Counters<br />

(Conventional police station Front Counters offering<br />

all policing services with secure and private<br />

Met Police Met Police, MOPAC CMC (this Front Counter will<br />

operate on a 24/7 basis)<br />

Windmill Rd Custody Centre<br />

Y<br />

Y<br />

2<br />

Contact Points<br />

(Contact Points are locations for non-urgent face-to<br />

-face contact, where the public can meet their local<br />

police at regular known times)<br />

Met Police Met Police, MOPAC Norbury, Thornton Heath, New<br />

Addington, Purley, Addington and<br />

Crystal Palace<br />

Y<br />

Y<br />

2<br />

Deployment Bases<br />

(Deployment Bases are where the borough’s Safer<br />

Neighbourhood Teams, Borough Tasking Teams<br />

and/or Emergency Response and Patrol officers and<br />

PCSOs start and end their tours of duty)<br />

Met Police Met Police, MOPAC CMC, Addington and Crystal Palace Y Y<br />

2<br />

Other Safer Neighbourhood Team Locations<br />

(As well as the locations shown above, there may be<br />

other bases where the borough’s Safer<br />

Neighbourhood Teams work. These will only be<br />

occupied when officers and PCSOs are not out on<br />

patrol and are not public access points)<br />

Met Police Met Police, MOPAC Coulsdon, Addiscombe, Selsdon,<br />

Shirley, Crystal Palace and CMC<br />

Y<br />

Y<br />

2<br />

Total Costs : £1.04m<br />

94


INFRASTRUCTURE DELIVERY PLAN: CRITICAL PROVISION FOR CROYDON LOCAL PLAN: STRATEGIC POLICIES SCHEDULE<br />

Planned Provision Lead Partner Delivery Partners/Stakeholder Delivery<br />

Mechanism/Funding<br />

Source<br />

Cost (if known) Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to CLP Strategic<br />

Policies: (3) Critical, (2)<br />

Necessary, (1) Contributory<br />

Wi-Fi Broadband enhancement LBC LBC, GLA, BT, CCURV, Croydon BID,<br />

Croydon College<br />

LBC Capital<br />

Programme<br />

£1.9million<br />

COA and then across<br />

the whole borough<br />

Y<br />

3<br />

New school at Westways Centre (3FE) LBC CFL LBC Education Estates<br />

Strategy<br />

TBC<br />

Broad Green and<br />

Selhurst<br />

Y<br />

3<br />

New school at Abderdeen Road (2FE) LBC CFL LBC Education Estates<br />

Strategy<br />

TBC COA Y<br />

3<br />

Ryelands Primary School-relocation of<br />

existing school (2FE)<br />

LBC CFL LBC Education Estates<br />

Strategy<br />

TBC<br />

South Norwood and<br />

Woodside<br />

Y<br />

3<br />

West Thornton Primary Academy– new<br />

annexe (2FE)<br />

LBC CFL LBC Education Estates<br />

Strategy<br />

TBC<br />

Broad Green and<br />

Selhurst<br />

Y<br />

3<br />

St Joseph’s Catholic Infants and Juniors<br />

– expansion (1FE)<br />

LBC CFL LBC Education Estates<br />

Strategy<br />

TBC<br />

Crystal Palace and<br />

Upper Norwood<br />

Y<br />

3<br />

Ark Oval– expansion (1FE) LBC CFL LBC Education Estates<br />

Strategy<br />

TBC Addiscombe Y<br />

3<br />

Kingsley Primary– expansion (1FE LBC CFL LBC Education Estates<br />

Strategy<br />

TBC<br />

Broad Green and<br />

Selhurst<br />

Y<br />

3<br />

Croydon Arena- (6FE) LBC CFL LBC Education Estates<br />

Strategy<br />

£29.3m<br />

South Norwood and<br />

Woodside<br />

Y<br />

Y<br />

3<br />

New School at Tennison Road-50<br />

places<br />

LBC CFL LBC Education Estates<br />

Strategy<br />

£7m South Norwood and<br />

Woodside<br />

Y<br />

3<br />

Masters provision at the University<br />

Centre<br />

Partnership with Sussex University to<br />

open an Innovation Centre<br />

Croydon College LBC, GLA, HE Partner, Croydon College TBC TBC COA Y Y<br />

Croydon College Croydon College, Sussex University, GLA TBC TBC COA Y Y<br />

3<br />

3<br />

Renewed Fairfield Halls complex LBC LBC, Fairfield Halls LBC Capital Budget £33.7m COA Y Y<br />

3<br />

Additional rolling stock (up to 4 units<br />

planned)<br />

TfL LBC, TfL TfL, LBC, CIL £20m Borough-wide Y Y<br />

3<br />

Connect 2, Wandle Park to Lloyd Park LBC Sustrans, TfL LBC, TfL, Sustrans £3,303,104 COA and<br />

surrounding<br />

Y<br />

3<br />

East Croydon Bridge Network Rail LBC, Network Rail, private sector LBC, Network Rail,<br />

private sector<br />

£6m (LBC contribution to<br />

£20m total)<br />

COA<br />

Y<br />

3<br />

95


INFRASTRUCTURE DELIVERY PLAN: CRITICAL PROVISION FOR CROYDON LOCAL PLAN: STRATEGIC POLICIES SCHEDULE<br />

Planned Provision Lead Partner Delivery Partners/<br />

Stakeholder<br />

Delivery<br />

Mechanism/<br />

Funding Source<br />

Cost (if known) Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to CLP Strategic<br />

Policies: (3) Critical, (2) Necessary, (1)<br />

Contributory<br />

Wellesley Road Phase 1 LBC TfL, MoL TfL, MoL, S106 £4,535,524 COA Y<br />

Wellesley Road Phase 2 (Lansdowne Road) LBC MoL MoL £1,750,000 COA Y<br />

3<br />

3<br />

West Croydon Public Realm LBC TfL, MoL LBC Capital<br />

Programme, CIL<br />

East Croydon Public Realm LBC TfL, MoL LBC Capital<br />

Programme, CIL,<br />

TfL, MoL<br />

High Streets (South End) LBC TfL, MoL LBC Capital<br />

Programme, CIL,<br />

GAF, MoL, TfL<br />

£4,934,060 COA Y<br />

£5,546,429 COA Y<br />

£2,934,711 COA Y<br />

3<br />

3<br />

3<br />

High Streets (London Road, Old Town,<br />

Central)<br />

LBC TfL, MoL MoL £6,156,480 COA Y<br />

3<br />

New Addington Central Parade Phase 2 LBC TfL, MoL MoL £864,000 Addington Y<br />

George Street tram stop LBC TfL, MoL MoL £878,620 COA Y<br />

South Norwood Public Realm LBC TfL TfL £241,005 S Norwood & Woodside Y<br />

3<br />

3<br />

3<br />

Billington Hill – Eastern Station Link LBC LBC, Network Rail,<br />

private sector<br />

LBC, Network Rail,<br />

private sector<br />

£3.4m COA Y<br />

3<br />

Public Realm: Future Tier 2 inc’ Wandle Park<br />

Pavilion, North End, COA subway removal,<br />

mini-hollands / cycle projects, district centres<br />

and future Legible London Future Phases<br />

£68m (approx) Borough-wide Y Y Y<br />

3<br />

Delivery of an additional substation<br />

UK Power<br />

Networks<br />

UK Power<br />

Networks<br />

UK Power Networks<br />

and developers<br />

TBC Borough-wide Y<br />

3<br />

Maintenance/renewal where needed of<br />

electricity supply <strong>infrastructure</strong><br />

UK Power<br />

Networks,<br />

National Grid<br />

LBC Highways, TfL<br />

UK Power<br />

Networks Capital<br />

Programme<br />

TBC Borough-wide Y Y Y<br />

3<br />

96


INFRASTRUCTURE DELIVERY PLAN: CRITICAL PROVISION FOR CROYDON LOCAL PLAN: STRATEGIC POLICIES SCHEDULE<br />

Planned Provision<br />

Lead<br />

Partner<br />

Delivery Partners/<br />

Stakeholder<br />

Delivery Mechanism/<br />

Funding Source<br />

Cost (if known) Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to CLP Strategic<br />

Policies: (3) Critical, (2)<br />

Necessary, (1) Contributory<br />

East Croydon Masterplan: Phase 1 public realm<br />

improvements<br />

LBC<br />

LBC, Network Rail and<br />

private sector<br />

Mayor Scheme funding,<br />

MRF, CIL, Capital<br />

Programme, National Rail<br />

and private<br />

£5.4 (doesn’t include cost of<br />

bridge station improvements,<br />

public realm on private land<br />

e.g Ruskin Square)<br />

COA<br />

Y<br />

3<br />

East Croydon Masterplan: Phase 2/3 public realm<br />

improvements<br />

LBC<br />

LBC, Network Rail and<br />

private sector<br />

Mayor Scheme funding,<br />

MRF, CIL, Capital<br />

Programme, National Rail<br />

and private<br />

£13.7m COA Y<br />

3<br />

West Croydon Masterplan: Phase 1 public realm<br />

improvements<br />

LBC<br />

LBC, MRF, Network Rail and<br />

TfL<br />

LBC, Network Rail and TfL<br />

£4.9m (not including TfL<br />

funding for bus station and<br />

public realm delivered on<br />

private land.<br />

COA<br />

Y<br />

3<br />

West Croydon Masterplan: Phase 2/3 public realm<br />

improvements<br />

LBC<br />

LBC, MRF, Network Rail and<br />

TfL<br />

LBC, MRF, Network Rail<br />

and TfL<br />

£14.1m (approx) COA Y Y<br />

3<br />

Fairfield Masterplan: Phase 1– public realm<br />

improvements<br />

LBC LBC £560,000 COA Y<br />

3<br />

Fairfield Masterplan: Phase 2– public realm<br />

improvements and remodelling of Fairfield Halls<br />

LBC LBC £10.2m for public realm and<br />

£33.7m for Fairfield Halls<br />

COA Y Y Y<br />

3<br />

Mid Croydon Masterplan: Phase 1 public realm<br />

improvements<br />

LBC<br />

LBC, CCURV, L&G, Minerva,<br />

Delancey and Chaseville<br />

Private sector, LBC, MRF,<br />

Sustrans, TfL<br />

£0.9m COA Y<br />

3<br />

Mid Croydon Masterplan: Phase 2/3 public realm<br />

improvements<br />

LBC<br />

LBC, CCURV, L&G, Minerva,<br />

Delancey and Chaseville<br />

Private sector, LBC, MRF,<br />

Sustrans, TfL<br />

£21.4m COA Y Y Y<br />

3<br />

Connected Croydon: East Croydon LBC LBC, Network London, TfL,<br />

Homes and Communities<br />

Agency, Royal Mail Group,<br />

Menta, Stanhope Schroders<br />

Network Rail, LBC Capital<br />

Programme, Growth Area<br />

Fund, S106, MRF, TfL<br />

Biking Boroughs, TfL LIP<br />

Major Scheme<br />

£25,240,000 COA Y Y<br />

3<br />

Connected Croydon: West Croydon<br />

LBC,<br />

Network<br />

Rail<br />

LBC, GLA, Network Rail, TfL,<br />

Barratt Homes, CBRE<br />

Investors, Mapeley,<br />

Portman Square Holdings,<br />

Purespace Group, St Michael<br />

and All Angels Church,<br />

Canmoor<br />

MRF £4.6m COA Y<br />

3<br />

97


INFRASTRUCTURE DELIVERY PLAN: CRITICAL PROVISION FOR CROYDON LOCAL PLAN: STRATEGIC POLICIES SCHEDULE<br />

Planned Provision Lead Partner Delivery Partners/<br />

Stakeholder<br />

Delivery Mechanism/Funding<br />

Source<br />

Cost (if known) Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to CLP Strategic<br />

Policies: (3) Critical, (2) Necessary, (1)<br />

Contributory<br />

Connected Croydon: High Streets LBC LBC, GLA, TfL, Local<br />

business and<br />

communities<br />

MRF, TfL Local Implementation<br />

Plan, Growth Area Fund<br />

£10m COA Y<br />

3<br />

Connected Croydon: Wellesley Road<br />

Crossings<br />

LBC LBC, GLA, TfL MRF, LBC Capital Programme,<br />

Growth Area Fund, S106, GLA,<br />

£6.6m COA Y<br />

3<br />

Connected Croydon: Connect 2 LBC LBC, TfL, Sustrans TfL LIP Greenways, LBC Capital<br />

Programme, TfL Sustrans, S106<br />

£3.4m COA Y<br />

3<br />

Connected Croydon: Fair Field LBC LBC, Bridgewater<br />

Property, CCURV,<br />

Croydon College,<br />

Fairfield Halls Trustees,<br />

Magistrates Court,<br />

Metropolitan Property,<br />

Network Rail, NCP,<br />

Terrace Hill, TfL<br />

LBC Capital Programme, £2.2m COA Y<br />

3<br />

Provision of new school and upgrading of<br />

Croydon Sports Arena<br />

LBC<br />

LBC, Croydon Harriers<br />

Athletics Club &<br />

South Norwood<br />

and Woodside<br />

Y Y Y<br />

3<br />

New “wet and dry” leisure centre in the<br />

south of the borough<br />

LBC LBC Sport England, Capital Bids, Big<br />

Lottery Fund, Football<br />

£14.1m South of borough Y<br />

3<br />

Refurbishment of New Addington Leisure<br />

Centre<br />

LBC LBC Capital programme £14.3m Addington Y<br />

3<br />

Road Network: Bridge Strengthening<br />

Network Rail/<br />

LBC<br />

LBC, TfL, Network Rail LIP, CIL £750k per year Borough-wide Y<br />

3<br />

Total Costs : £405.26m<br />

98


INFRASTRUCTURE DELIVERY PLAN: NECESSARY PROVISION FOR CROYDON LOCAL PLAN: STRATEGIC POLICIES SCHEDULE<br />

Planned Provision Lead Partner Delivery Partners/<br />

Stakeholder<br />

Delivery Mechanism/Funding<br />

Source<br />

Cost (if known) Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to CLP Strategic<br />

Policies: (3) Critical, (2)<br />

Necessary, (1) Contributory<br />

Enterprise centres for creative and<br />

cultural industries<br />

LBC<br />

LBC, ACAVA, CCURV,<br />

ACME, Croydon<br />

College<br />

LBC Capital Programme, S106, CIL<br />

COA, Crystal Palace, Portland<br />

Road/South, Norwood and<br />

Purley<br />

Y<br />

Y<br />

2<br />

Bring vacant commercial and retail<br />

premises into productive use<br />

LBC<br />

LBC, ACAVA, Village<br />

Underground,<br />

Meanwhile Space<br />

CIC<br />

LBC Capital Funding, S106, CIL Borough-wide Y Y Y<br />

2<br />

East Croydon Station: Additional<br />

platforms<br />

Network Rail Network Rail £80m COA Y<br />

2<br />

Rail Capacity: 12 coach trains on<br />

Central London-Brighton line<br />

Thames-link/<br />

Southern Railway<br />

Network Rail,<br />

Thameslink<br />

Thameslink Investment Programme TBC Borough-wide Y<br />

2<br />

Rail Capacity: More frequent services,<br />

or more capacity on existing services<br />

Thames-link/<br />

Southern Railway<br />

Network Rail,<br />

Thameslink<br />

Thameslink Investment Programme<br />

Strategic Business Plan, London and<br />

South East Rail Utilisation Study,<br />

Operational Business Plans<br />

Current best<br />

estimates up to<br />

£1bn<br />

Borough-wide Y Y<br />

2<br />

Rail Capacity: Railtrack junction<br />

improvements and by-passes<br />

Thames-link/<br />

Southern Railway<br />

Network Rail,<br />

Thameslink<br />

Thameslink Investment Programme<br />

Strategic Business Plan, London and<br />

South East Rail Utilisation Study,<br />

Operational Business Plans<br />

Current best<br />

estimates up to<br />

£1bn<br />

Borough-wide Y Y<br />

Tram stop improvements TfL LBC, TfL TfL, LBC, CIL £2.5m Borough-wide Y Y<br />

2<br />

Tram capacity improvements TfL LBC, TfL TfL, LBC, CIL £2.5m Borough-wide Y<br />

2<br />

Tramlink: Dingwall Road loop TfL LBC, TfL TfL, LBC, CIL £21m COA Y<br />

2<br />

2<br />

College Green Paving LBC Croydon College LBC Capital Programme, CIL £553,986 COA Y<br />

2<br />

Road Network: Congestion relief<br />

measures<br />

LBC, TfL LBC, TfL TfL, CIL, LBC funding £1.8m Borough-wide Y<br />

2<br />

Road Network: Soakaway<br />

Maintenance and Replacement–<br />

Highways Drainage<br />

LBC<br />

LBC, TfL,<br />

Environment Agency<br />

£1.7m from LBC Capital Budget<br />

2011/12-2015/16<br />

£1.75m Borough-wide Y<br />

2<br />

99


INFRASTRUCTURE DELIVERY PLAN: NECESSARY PROVISION FOR CROYDON LOCAL PLAN: STRATEGIC POLICIES SCHEDULE<br />

Planned Provision Lead Partner Delivery Partners/<br />

Stakeholder<br />

Delivery Mechanism/Funding<br />

Source<br />

Cost (if known) Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to CLP Strategic<br />

Policies: (3) Critical, (2)<br />

Necessary, (1) Contributory<br />

Car park improvements and rationalisation LBC NCP/private sector LBC Transport Strategy TBC Borough-wide Y Y Y<br />

2<br />

Purley Town Centre: Change to gyratory TfL LBC TfL TBC Purley Y<br />

2<br />

Bus system: Accessibility and safety<br />

improvements<br />

TfL Bus operators and TfL Bus operator plans, Mayor’s<br />

Transport Strategy and Revenue<br />

Programme<br />

£100k per year Borough-wide Y Y Y<br />

2<br />

Bus information improvements TfL TfL Borough Transport Strategy,<br />

Mayor’s Transport Strategy<br />

£250k Borough-wide Y<br />

2<br />

Bus priority measures TfL LBC, TfL TfL £1.9m Borough-wide Y Y Y<br />

2<br />

Bus stands/standbys TfL, LBC LBC, TfL TfL £3m per year COA Y Y<br />

2<br />

Improvements to West Croydon bus station TfL TfL TfL £3m COA Y Y<br />

2<br />

Refurbishment of London cycling network<br />

and provision of Quietways<br />

TfL LBC, TfL Borough Transport Strategy,<br />

Mayor’s Vision for Cycling, LIP<br />

TBC Borough-wide Y<br />

2<br />

Cycling provision at major stations Network Rail LBC, TfL, Network Rail Master Plans, Public Realm<br />

Strategy, Planning Obligations,<br />

Mayor’s Vision for Cycling, LIP,<br />

TOCs, National Rail<br />

TBC Borough-wide Y Y<br />

2<br />

Completion of Connect 2 and Greenway<br />

routes<br />

TfL LBC, TfL, Sustrans TfL, LBC, CIL TBC Borough-wide Y Y<br />

2<br />

Cycling measures at key junctions TfL/LBC LBC, TfL, Sustrans TfL, LBC, CIL TBC Borough-wide Y Y<br />

2<br />

Other cycle links LBC LBC, TfL, Sustrans LIP2 or Connect 2 programme TBC through<br />

LIP2 or<br />

Conenct 2<br />

programme<br />

Borough-wide Y Y<br />

2<br />

Connect 2, National Cycling Network 21, N-S<br />

link Norbury– Kenley Addington, other<br />

lower priority routes and Emerald Necklace,<br />

South Norwood Greenways<br />

LBC TfL, PCT, Sustrans TfL, LBC Capital Programme, S106 TBC Borough-wide Y<br />

2<br />

Improvements to the borough’s play areas LBC LBC, DCSF DCSF, LBC Capital Programme,<br />

S106, HLF, other funding streams<br />

£2.4m Borough-wide Y Y<br />

2<br />

100


INFRASTRUCTURE DELIVERY PLAN: NECESSARY PROVISION FOR CROYDON LOCAL PLAN: STRATEGIC POLICIES SCHEDULE<br />

Planned Provision Lead Partner Delivery<br />

Partners/<br />

Stakeholder<br />

Delivery Mechanism/<br />

Funding Source<br />

Cost (if known) Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to CLP Strategic<br />

Policies: (3) Critical, (2)<br />

Necessary, (1) Contributory<br />

Connect 2, National Cycling Network<br />

21, N-S link Norbury– Kenley<br />

Addington, other lower priority<br />

routes & Emerald Necklace, Sth<br />

Norwood Greenways<br />

LBC<br />

TfL, PCT,<br />

Sustrans<br />

TfL, LBC Capital<br />

Programme, S106<br />

TBC Borough-wide Y<br />

2<br />

COA District Heating, CHP related to<br />

energy centres on NHS Capital<br />

Programme<br />

LBC<br />

NHS, LDA, HCA,<br />

landowners and<br />

businesses<br />

UK Power Networks<br />

and developers<br />

£.5m from LBC from Capital Budget<br />

2011/12-2015/2016. Energy service<br />

company, developers, investors, funding<br />

institutions, NHS Croydon<br />

Borough-wide Y Y<br />

2<br />

Water supply reinforcement of<br />

strategic supplies and continuous<br />

renewal<br />

Thames Water, Sutton<br />

and East Surrey Water<br />

LBC Highways,<br />

TfL<br />

Thames Water Asset<br />

Mgt Plan and funding,<br />

Sutton and East Surrey<br />

Asset Mgt Plan and<br />

funding<br />

Costs are not available until the final<br />

determination by Ofwat is made public<br />

Borough-wide Y Y Y<br />

2<br />

Maintenance/renewal where<br />

needed of sewerage <strong>infrastructure</strong><br />

and new sewerage <strong>infrastructure</strong> to<br />

support growth<br />

Thames Water<br />

LBC Highways,<br />

TfL, Developers<br />

Thames Water Asset<br />

Management Plan and<br />

funding developer<br />

funding<br />

TBC Borough-wide Y Y Y<br />

2<br />

New Addington: rationalisation of<br />

public sector assets, new<br />

community centre, library relocation<br />

and public realm enhancements<br />

LBC GLA, LBC LBC-£30k<br />

GLA MRF- £800k<br />

GLA ORF- £500k<br />

£1.33m Addington Y<br />

2<br />

New Addington Masterplan: Leisure<br />

Centre<br />

LBC LBC, Fusion LBC- £30K<br />

GLA MRF– £800K<br />

GLA OLF- £500K<br />

£17m Addington Y<br />

2<br />

Old Town Masterplan: A range of<br />

transport and public realm<br />

improvements<br />

LBC<br />

LBC, Stakeholder<br />

Project Board<br />

CIL, S106 £11.7m COA Y Y Y<br />

2<br />

Upgrading and maintenance of the<br />

sports and swimming facilities<br />

within the borough’s Academies<br />

LBC LBC Borough-wide Y Y<br />

2<br />

Redevelopment of Woodside Health<br />

Centre to expand services<br />

NHS Croydon<br />

NHS Croydon,<br />

LBC, Healthcare<br />

for London<br />

LIFT, planning<br />

obligations, DoH NHS<br />

allocations<br />

TBC<br />

South Norwood and<br />

Woodside<br />

Y<br />

2<br />

101


INFRASTRUCTURE DELIVERY PLAN: NECESSARY PROVISION FOR CROYDON LOCAL PLAN: STRATEGIC POLICIES SCHEDULE<br />

Planned Provision Lead Partner Delivery Partners/<br />

Stakeholder<br />

Delivery<br />

Mechanism/<br />

Funding Source<br />

Cost (if<br />

known)<br />

Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to CLP<br />

Strategic<br />

Policies: (3) Critical, (2)<br />

Necessary, (1) Contributory<br />

New build New Addington GP-led Health Centre NHS Croydon NHS Croydon, LBC,<br />

Healthcare for<br />

London<br />

LIFT, planning<br />

obligations, DoH<br />

NHS allocations<br />

TBC Addington Y<br />

2<br />

Redevelopment of Croydon University Hospital Site , with the provision of<br />

an Urgent Care Strategy<br />

NHS Croydon<br />

NHS Croydon, LBC,<br />

Healthcare for<br />

London<br />

LIFT, planning<br />

obligations, DoH<br />

NHS allocations<br />

TBC Broad Green and Selhurst Y<br />

2<br />

Modernisation of supported housing schemes LBC LBC Borough-wide Y<br />

2<br />

Replacement for Purley Fire Station<br />

London Fire<br />

Brigade<br />

London Fire<br />

Brigade<br />

Purley<br />

Y<br />

2<br />

Replacement for Croydon Ambulance Station<br />

London<br />

Ambulance Service<br />

London Ambulance<br />

Service<br />

Shirley<br />

2<br />

Front Counters<br />

(Conventional police station Front Counters offering all policing services<br />

with secure and private facilities)<br />

Met Police<br />

Met Police,<br />

MOPAC<br />

CMC (this Front Counter will<br />

operate on a 24/7 basis)<br />

Windmill Rd Custody Centre<br />

Y<br />

Y<br />

2<br />

Contact Points<br />

(Contact Points are locations for non-urgent face-to-face contact, where the<br />

public can meet their local police at regular known times)<br />

Met Police<br />

Met Police,<br />

MOPAC<br />

Norbury, Thornton Heath,<br />

New Addington, Purley,<br />

Addington and Crystal Palace<br />

Y<br />

Y<br />

2<br />

Deployment Bases<br />

(Deployment Bases are where the borough’s Safer Neighbourhood Teams,<br />

Borough Tasking Teams and/or Emergency Response and Patrol officers and<br />

PCSOs start and end their tours of duty)<br />

Met Police<br />

Met Police,<br />

MOPAC<br />

CMC, Addington and Crystal<br />

Palace<br />

Y<br />

Y<br />

2<br />

Other Safer Neighbourhood Team Locations<br />

(As well as the locations shown above, there may be other bases where the<br />

borough’s Safer Neighbourhood Teams work. These will only be occupied<br />

when officers and PCSOs are not out on patrol and are not public access<br />

points)<br />

Met Police<br />

Met Police,<br />

MOPAC<br />

Coulsdon, Addiscombe,<br />

Selsdon, Shirley, Crystal<br />

Palace and CMC<br />

Y<br />

Y<br />

2<br />

Wandle Road bus stand LBC TfL TfL £1.22m COA Y<br />

2<br />

Total Costs : £179.63m<br />

102


INFRASTRUCTURE DELIVERY PLAN: CONTRIBUTORY PROVISION TO CROYDON LOCAL PLAN: STRATEGIC POLICIES SCHEDULE<br />

Planned Provision Lead Partner Delivery Partners/<br />

Stakeholder<br />

Delivery Mechanism/<br />

Funding Source<br />

Cost (if known) Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to CLP<br />

Strategic<br />

Policies: (3) Critical,<br />

(2) Necessary, (1)<br />

Contributory<br />

Expansion at Resource Base 1 at Croydon<br />

Arena–10 to 15 places<br />

Expansion of Resource Base 2 at Croydon<br />

General Hospital Site– 15 places<br />

LBC CFL LBC Education Estates Strategy £780,000 South Norwood and Woodside Y<br />

LBC CFL LBC Education Estates Strategy TBC South Norwood and Woodside Y<br />

1<br />

1<br />

Expansion of Resource Base 3– 15 places LBC CFL LBC Education Estates Strategy TBC TBC Y<br />

1<br />

Improvement of Selhurst, Sanderstead and<br />

Norwood Junction and other stations<br />

Network Rail TfL Network Rail, TfL, LBC £400k Borough-wide Y Y<br />

1<br />

Tramlink: extensions to Crystal Palace TfL LBC, TfL TfL, LBC, CIL £150m North Y Y<br />

1<br />

Road network: Minor highway improvements LBC LBC, TfL Capital Programme, CIL £250k per year Borough-wide Y Y<br />

1<br />

Road network: Electric car <strong>infrastructure</strong> LBC, TfL LBC, TfL Mayor’s Transport<br />

Strategy<br />

£5k per station<br />

(estimated capital<br />

costs)<br />

Borough-wide Y Y Y<br />

1<br />

Street lighting PFI programme LBC LBC, London<br />

Borough of<br />

Lewisham and<br />

Skanska<br />

Infrastructure<br />

Services<br />

PFI for street lights £40m capital Borough-wide Y Y<br />

1<br />

Street waymarking and signage LBC TfL Public Realm Strategy £3m COA Y Y Y<br />

1<br />

Freight consolidation centre LBC Private sector Private Sector, CIL TBC South of the borough Y<br />

1<br />

East Croydon Landsdowne Taxi Rank LBC Private external TfL £100k COA Y<br />

1<br />

Woodland and Tree Management Plan:<br />

Highway tree inspection and works,<br />

woodland health and safety inspection, tree<br />

planting and woodland inspection and works<br />

LBC LBC LBC £690,000 Borough-wide Y<br />

1<br />

103


INFRASTRUCTURE DELIVERY PLAN: CONTRIBUTORY PROVISION TO CROYDON LOCAL PLAN: STRATEGIC POLICIES SCHEDULE<br />

Planned Provision Lead Partner Delivery Partners/<br />

Stakeholder<br />

Delivery Mechanism/<br />

Funding Source<br />

Cost (if known) Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to CLP<br />

Strategic<br />

Policies: (3) Critical, (2)<br />

Necessary, (1)<br />

Contributory<br />

To improve access to nature across London. These areas<br />

include Queens Road Cemetery, Melfort Avenue<br />

Recreation Ground, Norbury Hall Park, Addiscombe Railway<br />

Park, Purley Way East Playing Fields, Pollards Hill, Haling<br />

Grove, Wandle Park, Duppas Hill, Norbury Park and Brook,<br />

Cane Hill Hospital West and Waddon Ponds.<br />

GLA<br />

LB Croydon, Mayor of<br />

London<br />

Mayor of London, LDA N/A Borough-wide Y Y Y<br />

1<br />

Community food and flower growing initiatives LBC Mayor of London Mayor of London, LBC N/A Borough-wide Y<br />

1<br />

Management of the rare chalk downland, development of<br />

an extensive series of trails, woodland management and<br />

pond restoration<br />

London<br />

Downland<br />

Partnership<br />

LBC, LB Sutton, Surrey<br />

County Council, Corporation<br />

of London, Reigate &<br />

Banstead Borough Council,<br />

Tandridge District Council,<br />

Countryside Agency<br />

LBC, LDA, TfL, Network Rail,<br />

GAF, private developers<br />

Borough-wide<br />

Y<br />

1<br />

Re-opening of sites at South Norwood Lake and Pollards<br />

Hill, including upgrade of existing allotment facilities<br />

LBC LBC, owners and occupiers LBC Capital funding,<br />

owners and occupiers<br />

TBC Borough-wide Y<br />

1<br />

Surface Water Management Plan and Extensive Soakaway<br />

and Ancillary Drainage Cleaning Programme<br />

LBC<br />

LBC, Environment Agency<br />

and Croydon Fire Brigade<br />

DEFRA TBC Borough-wide Y Y Y<br />

1<br />

Mayor of London’s Street Tree Programme LBC LBC and Mayor of London Mayor of London £500k Borough-wide Y<br />

1<br />

Provision of a new burial ground on land adjoining<br />

Greenlawns Cemetery<br />

LBC<br />

LBC, Tandridge District<br />

Council<br />

£75k identified from LBC<br />

Capital Budget<br />

£1.04million Tandridge Y<br />

1<br />

Total Costs : £199.01m<br />

104


INFRASTRUCTURE DELIVERY PLAN: SCHEDULE BY LOCATION– 16 PLACES OF CROYDON<br />

Planned Provision Lead Partner Delivery Partners/<br />

Stakeholder<br />

Delivery Mechanism/Funding Source Cost (if known) Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to CLP Strategic<br />

Policies: (3) Critical, (2)<br />

Necessary, (1) Contributory<br />

Bring vacant commercial and<br />

retail premises into productive<br />

use<br />

LBC<br />

LBC, ACAVA, Village<br />

Underground, Meanwhile<br />

Space CIC<br />

LBC Capital Funding, S106, CIL Borough-wide Y Y Y<br />

2<br />

Improvement of Selhurst,<br />

Sanderstead and Norwood<br />

Junction and other stations<br />

Network Rail TfL Network Rail, TfL, LBC £400k Borough-wide Y Y<br />

1<br />

Rail Capacity: 12 coach trains on<br />

Central London-Brighton line<br />

Thames-link/<br />

Southern Railway<br />

Network Rail, Thameslink Thameslink Investment Programme TBC Borough-wide Y<br />

2<br />

Rail Capacity: more frequent<br />

services or more capacity on<br />

existing services<br />

Thames-link/<br />

Southern Railway<br />

Network Rail, Thameslink<br />

Thameslink Investment Programme<br />

Strategic Business Plan, London and<br />

South East Rail Utilisation Study,<br />

Operational Business Plans<br />

Current best<br />

estimates up to<br />

£1bn<br />

Borough-wide Y Y<br />

2<br />

Rail Capacity: Railtrack junction<br />

improvements and by-passes<br />

Thames-link/<br />

Southern Railway<br />

Network Rail, Thameslink<br />

Thameslink Investment Programme<br />

Strategic Business Plan, London and<br />

South East Rail Utilisation Study,<br />

Operational Business Plans<br />

Current best<br />

estimates up to<br />

£1bn<br />

Borough-wide Y Y<br />

2<br />

Additional rolling stock (up to 4<br />

units planned)<br />

TfL LBC, TfL TfL, LBC, CIL £20m Borough-wide Y Y<br />

3<br />

Tram stop improvements TfL LBC, TfL TfL, LBC, CIL £2.5m Borough-wide Y Y<br />

2<br />

Tram capacity improvements TfL LBC, TfL TfL, LBC, CIL £2.5m Borough-wide Y<br />

2<br />

Road Network: Bridge<br />

Strengthening<br />

Network Rail/LBC LBC, TfL, Network Rail TfL, CIL £750k per year Borough-wide Y<br />

3<br />

Road Network: Soakaway<br />

Maintenance and Replacement–<br />

Highways Drainage<br />

LBC LBC, TfL, Environment Agency £1.7m from LBC Capital Budget<br />

2011/12-2015/16<br />

£1.75m Borough-wide Y<br />

2<br />

Road Network: Congestion relief<br />

measures<br />

Road Network: Minor highway<br />

improvements<br />

LBC, TfL LBC, TfL TfL, CIL, LBC funding £1.8m Borough-wide Y<br />

LBC LBC, TfL Capital Programme, CIL £250k per year Borough-wide Y Y<br />

2<br />

1<br />

Road network: Electric car<br />

<strong>infrastructure</strong><br />

LBC, TfL LBC, TfL Mayor’s Transport Strategy £5k per station<br />

(estimated capital<br />

costs)<br />

Borough-wide Y Y Y<br />

1<br />

105


INFRASTRUCTURE DELIVERY PLAN: SCHEDULE BY LOCATION– 16 PLACES OF CROYDON<br />

Planned Provision Lead Partner Delivery Partners/<br />

Stakeholder<br />

Delivery Mechanism/Funding Source Cost (if known) Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to<br />

CLP Strategic<br />

Policies: (3)<br />

Critical, (2)<br />

Necessary, (1)<br />

Contributory<br />

Street lighting PFI programme LBC LBC, London Borough of<br />

Lewisham and Skanska<br />

Infrastructure Services<br />

PFI for street lights £40m capital Borough-wide Y Y<br />

1<br />

Car park improvements and rationalisation LBC NCP/private sector LBC Transport Strategy TBC Borough-wide Y Y Y<br />

2<br />

Bus system: accessibility and safety improvements TfL Bus operators and TfL Bus operator plans, Mayor’s Transport<br />

Strategy and Revenue programme<br />

Bus information improvements TfL TfL Borough Transport Strategy, Mayor’s<br />

Transport Strategy<br />

£100k per year Borough-wide Y Y Y<br />

£250k Borough-wide Y<br />

2<br />

2<br />

Bus priority measures TfL LBC, TfL TfL £1.9m Borough-wide Y Y Y<br />

2<br />

Refurbishment of London cycling network and provision of<br />

Quietways<br />

TfL LBC, TfL Borough Transport Strategy, Mayor’s<br />

Vision for Cycling, LIP<br />

TBC Borough-wide Y<br />

2<br />

Cycling provision at major stations Network Rail LBC, TfL, Network Rail Master Plans, Public Realm Strategy,<br />

Planning Obligations, Mayor’s Vision for<br />

Cycling, LIP, TOCs, National Rail<br />

TBC Borough-wide Y Y<br />

2<br />

Completion of Connect 2 and Greenway routes TfL LBC, TfL, Sustrans TfL, LBC, CIL TBC Borough-wide Y Y<br />

Cycling measures at key junctions TfL/LBC LBC, TfL, Sustrans TfL, LBC, CIL TBC Borough-wide Y Y<br />

2<br />

2<br />

Other cycle links LBC LBC, TfL, Sustrans LIP2 or Connect 2 programme TBC through LIP2<br />

or Conenct 2<br />

programme<br />

Borough-wide Y Y<br />

2<br />

Improvements to the borough’s play areas LBC LBC, DCSF DCSF, LBC Capital Programme, S106, HLF,<br />

other funding streams<br />

Public Realm: Future Tier 2 including Wandle Park pavilion,<br />

North End, COA subway removal, mini-hollands/cycle projects,<br />

district centres and future Legible London Future Phases<br />

£2.4m Borough-wide Y Y<br />

£68m (approx) Borough-wide Y Y Y<br />

2<br />

3<br />

Woodland and Tree Management Plan: Highway tree<br />

inspection and works, woodland health and safety inspection,<br />

tree planting and woodland inspection and works<br />

LBC LBC LBC £690,000 Borough-wide Y<br />

106<br />

1


INFRASTRUCTURE DELIVERY PLAN: SCHEDULE BY LOCATION– 16 PLACES OF CROYDON<br />

Planned Provision Lead Partner Delivery Partners/Stakeholder Delivery Mechanism/Funding<br />

Source<br />

Cost (if<br />

known)<br />

Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021<br />

-<br />

Relationship to CLP<br />

Strategic<br />

Policies: (3) Critical, (2)<br />

Necessary, (1)<br />

Contributory<br />

Connect 2, National Cycling Network 21, N-S link<br />

Norbury– Kenley Addington, other lower priority<br />

routes and Emerald Necklace, South Norwood<br />

Greenways<br />

LBC TfL, PCT, Sustrans TfL, LBC Capital Programme,<br />

S106<br />

TBC Borough-wide Y<br />

2<br />

To improve access to nature across London.<br />

These areas include Queens Road Cemetery,<br />

Melfort Avenue Recreation Ground, Norbury Hall<br />

Park, Addiscombe Railway Park, Purley Way East<br />

Playing Fields, Pollards Hill, Haling Grove, Wandle<br />

Park, Duppas Hill, Norbury Park and Brook, Cane<br />

Hill Hospital West and Waddon Ponds.<br />

GLA LB Croydon, Mayor of London Mayor of London, LDA N/A Borough-wide Y Y Y<br />

1<br />

Community food and flower growing initiatives LBC Mayor of London Mayor of London, LBC N/A Borough-wide Y<br />

1<br />

Management of the rare chalk downland,<br />

development of an extensive series of trails,<br />

woodland management and pond restoration<br />

London Downlands<br />

Partnership<br />

LBC, LB Sutton, Surrey County<br />

Council, Corporation of<br />

London, Reigate & Banstead<br />

Borough Council, Trandridge<br />

District Council, Countryside<br />

Agency<br />

LBC, LDA, TfL, Network Rail,<br />

GAF, private developers<br />

TBC Borough-wide Y<br />

1<br />

Re-opening of sites at South Norwood Lake and<br />

Pollards Hill, including upgrade of existing<br />

allotment facilities.<br />

LBC LBC, owners and occupiers LBC Capital funding, owners and<br />

occupiers<br />

Borough-wide<br />

Y<br />

1<br />

Surface Water Management Plan and Extensive<br />

Soakaway and Ancillary Drainage Cleaning<br />

Programme<br />

LBC<br />

LBC, Environment Agency and<br />

Croydon Fire Brigade<br />

DEFRA £7m (TBC) Borough-wide Y Y Y<br />

1<br />

Mayor of London’s Street Tree Programme LBC LBC and Mayor of London Mayor of London £500k Borough-wide Y<br />

1<br />

Delivery of an additional substation UK Power Networks UK Power Networks UK Power Networks and<br />

developers<br />

TBC Borough-wide Y<br />

3<br />

107


INFRASTRUCTURE DELIVERY PLAN: SCHEDULE BY LOCATION– 16 PLACES OF CROYDON<br />

Planned Provision Lead Partner Delivery<br />

Partners/<br />

Stakeholder<br />

Delivery Mechanism/<br />

Funding Source<br />

Cost (if known) Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to CLP<br />

Strategic<br />

Policies: (3) Critical, (2)<br />

Necessary, (1)<br />

Contributory<br />

COA District Heating, CHP related to energy centres on NHS Capital<br />

Programme<br />

LBC<br />

NHS, LDA,<br />

HCA,<br />

landowners<br />

and businesses<br />

UK Power Networks and<br />

developers<br />

£.5m from LBC/Capital Budget. Other<br />

sources: energy service company,<br />

developers, investors, funding institutions,<br />

NHS Croydon Capital Programme 4<br />

Boroughwide<br />

Y<br />

Y<br />

2<br />

Water supply reinforcement of strategic supplies and continuous<br />

renewal<br />

Thames Water,<br />

Sutton and East<br />

Surrey Water<br />

LBC<br />

Highways, TfL<br />

TW Asset Management<br />

Plan, S & ES Asset Mgt<br />

Plan and funding<br />

Costs are not available until the final<br />

determination by Ofwat is made public<br />

Boroughwide<br />

Y Y Y<br />

2<br />

Maintenance/renewal where needed of sewerage <strong>infrastructure</strong> and<br />

new sewerage <strong>infrastructure</strong> to support growth<br />

Thames Water<br />

LBC<br />

Highways, TfL,<br />

Developers<br />

Thames Water Asset<br />

Management Plan and<br />

developer funding<br />

TBC<br />

Boroughwide<br />

Y Y Y<br />

2<br />

Maintenance/renewal where needed of electricity supply<br />

<strong>infrastructure</strong><br />

UK Power<br />

Networks,<br />

National Grid<br />

LBC<br />

Highways, TfL<br />

UK Power Networks<br />

Capital Programme<br />

TBC<br />

Boroughwide<br />

Y Y Y<br />

3<br />

Upgrading, maintenance and improvement of the sports and<br />

swimming facilities within the borough’s Academies<br />

LBC LBC Boroughwide<br />

Y<br />

Y<br />

2<br />

Modernisation of supported housing schemes LBC LBC Boroughwide<br />

Y<br />

2<br />

Front Counters<br />

(Conventional police station Front Counters offering all policing<br />

services with secure and private facilities)<br />

Met Police<br />

Met Police,<br />

MOPAC<br />

Boroughwide<br />

Y<br />

Y<br />

2<br />

Contact Points<br />

(Contact Points are locations for non-urgent face-to-face contact,<br />

where the public can meet their local police at regular known times)<br />

Met Police<br />

Met Police,<br />

MOPAC<br />

Boroughwide<br />

Y<br />

Y<br />

2<br />

Deployment Bases<br />

(Deployment Bases are where the borough’s Safer Neighbourhood<br />

Teams, Borough Tasking Teams and/or Emergency Response and<br />

Patrol officers and PCSOs start and end their tours of duty)<br />

Met Police<br />

Met Police,<br />

MOPAC<br />

Boroughwide<br />

Y<br />

Y<br />

2<br />

Other Safer Neighbourhood Team Locations (As well as locations<br />

above, there may be other bases where the borough’s Safer<br />

Neighbourhood Teams work. These will only be occupied when<br />

officers/PCSOs are not on patrol and are not public access points)<br />

Met Police<br />

Met Police,<br />

MOPAC<br />

Boroughwide<br />

Y<br />

Y<br />

2<br />

108


INFRASTRUCTURE DELIVERY PLAN: SCHEDULE BY LOCATION– 16 PLACES OF CROYDON<br />

Planned Provision Lead Partner Delivery<br />

Partners/<br />

Stakeholder<br />

Delivery Mechanism/<br />

Funding Source<br />

Cost (if known) Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to CLP Strategic<br />

Policies: (3) Critical, (2) Necessary, (1)<br />

Contributory<br />

Freight consolidation centre LBC Private sector Private sector, CIL South of the borough Y<br />

1<br />

New “wet and dry” leisure centre<br />

in the south of the borough<br />

LBC LBC Sport England, Capital Bids,<br />

Big Lottery Fund, Football<br />

Foundation, S106/CIL<br />

£14.1m South of borough Y<br />

3<br />

Planned Provision Lead Partner Delivery<br />

Partners/<br />

Stakeholder<br />

Delivery Mechanism/Funding<br />

Source<br />

Cost (if known) Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to CLP Strategic<br />

Policies: (3) Critical, (2) Necessary, (1)<br />

Contributory<br />

Tramlink: extensions to Crystal<br />

Palace<br />

TfL LBC, TfL TfL, LBC, CIL £150m North of the borough Y Y<br />

1<br />

Planned Provision Lead Partner Delivery<br />

Partners/<br />

Stakeholder<br />

Delivery Mechanism/Funding<br />

Source<br />

Cost (if known) Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to CLP Strategic<br />

Policies: (3) Critical, (2) Necessary, (1)<br />

Contributory<br />

Wi-Fi Broadband enhancement LBC LBC, GLA, BT,<br />

CCURV,<br />

Croydon BID,<br />

Croydon<br />

College<br />

LBC Capital Programme £1.9million COA and then across the<br />

whole borough<br />

Y<br />

3<br />

Enterprise centres for creative and<br />

cultural industries<br />

LBC<br />

LBC, ACAVA,<br />

CCURV, ACME,<br />

Croydon<br />

College<br />

LBC Capital Programme, S106,<br />

CIL<br />

TBC<br />

COA, Crystal Palace,<br />

Portland Road/South,<br />

Norwood and Purley<br />

Y<br />

Y<br />

2<br />

New school at Abderdeen Road LBC CFL LBC Education Estates Strategy TBC COA Y<br />

3<br />

Expansion of Resource Base 2 at<br />

Croydon General Hospital Site– 15<br />

places<br />

LBC CFL LBC Education Estates Strategy TBC COA Y<br />

1<br />

Masters provision at the University<br />

Centre<br />

Croydon College<br />

LBC, GLA, HE<br />

Partner,<br />

Croydon<br />

College<br />

TBC TBC COA Y Y<br />

3<br />

109


INFRASTRUCTURE DELIVERY PLAN: SCHEDULE BY LOCATION– 16 PLACES OF CROYDON<br />

Planned Provision Lead Partner Delivery Partners/<br />

Stakeholder<br />

Delivery<br />

Mechanism/<br />

Funding Source<br />

Cost (if known) Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to CLP Strategic<br />

Policies: (3) Critical, (2) Necessary, (1)<br />

Contributory<br />

Partnership with Sussex University to open<br />

an Innovation Centre<br />

Croydon College<br />

Croydon College,<br />

Sussex University,<br />

TBC TBC COA Y Y<br />

3<br />

Renewed Fairfield Halls complex LBC LBC, Fairfield Halls LBC Capital<br />

Budget<br />

2011/12-<br />

2017/18<br />

£33.7m COA Y Y<br />

3<br />

East Croydon Station: Additional platforms Network Rail Network Rail £80m COA Y<br />

2<br />

Tramlink: Dingwall Road loop TfL LBC, TfL TfL, LBC, CIL £21m COA Y<br />

2<br />

Bus stands/standbys TfL, LBC LBC, TfL TfL £3m per year COA Y Y<br />

2<br />

Improvements to West Croydon bus station TfL TfL TfL £3m COA Y Y<br />

2<br />

East Croydon Lansdowne Road Taxi Rank LB Croydon Private external TfL £100K COA Y<br />

1<br />

Street wayfinding and signage LBC TfL Public Realm<br />

Strategy<br />

£3m COA Y Y Y<br />

1<br />

Public Realm: Connect2 £3,076,807 COA and surrounding Y<br />

3<br />

Public Realm: East Croydon Bridge<br />

£6,000,000 (TBC<br />

contribution to £20m<br />

total)<br />

COA<br />

Y<br />

3<br />

Public Realm: Wellesley Road Phase 1 £4,535,524 COA Y<br />

3<br />

Public Realm: Wellesley Road phase 2<br />

(Lansdowne Road)<br />

Public Realm: College Green Paving LBC TfL LBC Capital<br />

Programme, CIL<br />

West Croydon Public Realm LBC TfL LBC Capital<br />

Programme, CIL<br />

£1,714,810 COA Y<br />

£553,986 COA Y<br />

£4,908,060 COA Y<br />

3<br />

3<br />

3<br />

110


INFRASTRUCTURE DELIVERY PLAN: SCHEDULE BY LOCATION– 16 PLACES OF CROYDON<br />

Planned Provision Lead Partner Delivery Partners/<br />

Stakeholder<br />

Delivery<br />

Mechanism/<br />

Funding Source<br />

Cost (if known) Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to CLP Strategic<br />

Policies: (3) Critical, (2) Necessary, (1)<br />

Contributory<br />

East Croydon Public Realm LBC TfL LBC Capital<br />

Programme, CIL<br />

Public Ream: High Street South End LBC TfL LBC Capital<br />

Programme, CIL<br />

£4,400,000 COA Y<br />

£2,934,711 COA Y<br />

3<br />

3<br />

Public Realm: High Streets (London Road,<br />

Old Town, Central)<br />

LBC TfL LBC Capital<br />

Programme, CIL<br />

£6,156,480 COA Y<br />

3<br />

Public Realm: George Street tram stop LBC TfL LBC Capital<br />

Programme, CIL<br />

£878,620 COA Y<br />

3<br />

Public Realm: Billinton Hill – Eastern Link £3,400,000 COA Y<br />

3<br />

Wandle Road bus stand<br />

£20,000 (feasibility)<br />

£1.2m (construction)<br />

COA<br />

Y<br />

3<br />

East Croydon Masterplan: Phase 1 public<br />

realm improvements<br />

LBC<br />

LBC, Network Rail<br />

and private sector<br />

Mayor Scheme<br />

funding, MRF,<br />

CIL, Capital<br />

Programme,<br />

National Rail<br />

and private<br />

£5.4m (doesn’t<br />

include cost of bridge<br />

station<br />

improvements,<br />

public realm on<br />

private land e.g<br />

Ruskin Square)<br />

COA<br />

Y<br />

3<br />

East Croydon Masterplan: Phase 2/3 public<br />

realm improvements<br />

LBC<br />

LBC, Network Rail<br />

and private sector<br />

Mayor Scheme<br />

funding, MRF,<br />

CIL, Capital<br />

Programme,<br />

National Rail<br />

and private<br />

£13.7m COA Y<br />

3<br />

West Croydon Masterplan: Phase 1 public<br />

realm improvements<br />

LBC<br />

LBC, MRF, Network<br />

Rail and TfL<br />

LBC, Network<br />

Rail and TfL<br />

£4.9m (not including<br />

TfL funding for bus<br />

station and public<br />

realm delivered on<br />

private land.<br />

COA<br />

Y<br />

3<br />

West Croydon Masterplan: Phase 2/3 public<br />

realm improvements<br />

LBC<br />

LBC, MRF, Network<br />

Rail and TfL<br />

LBC, MRF,<br />

Network Rail<br />

and TfL<br />

£14.1m (approx) COA Y Y<br />

3<br />

111


INFRASTRUCTURE DELIVERY PLAN: SCHEDULE BY LOCATION– 16 PLACES OF CROYDON<br />

Planned Provision Lead Partner Delivery Partners/Stakeholder Delivery Mechanism/Funding<br />

Source<br />

Cost (if known) Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to CLP Strategic<br />

Policies: (3) Critical, (2)<br />

Necessary, (1) Contributory<br />

Fairfield Masterplan: Phase 1–<br />

public realm improvements<br />

LBC LBC £560,000 COA Y<br />

3<br />

Fairfield Masterplan: Phase 2–<br />

public realm improvements<br />

and remodelling of Fairfield<br />

Halls<br />

LBC LBC £10.2m for public<br />

realm and £33.7m for<br />

Fairfield Halls<br />

COA Y Y Y<br />

3<br />

Mid Croydon Masterplan:<br />

Phase 1 public realm<br />

improvements<br />

LBC<br />

LBC, CCURV, L&G, Minerva, Delancey and<br />

Chaseville<br />

Private sector, LBC, MRF,<br />

Sustrans, TfL<br />

£0.9m COA Y<br />

3<br />

Mid Croydon Masterplan:<br />

Phase 2/3 public realm<br />

improvements<br />

LBC<br />

LBC, CCURV, L&G, Minerva, Delancey and<br />

Chaseville<br />

Private sector, LBC, MRF,<br />

Sustrans, TfL<br />

£21.4m COA Y Y Y<br />

3<br />

Old Town Masterplan: A range<br />

of transport and public realm<br />

improvements<br />

LBC LBC, Stakeholder Project Board CIL, S106 £11.7m COA Y Y Y<br />

2<br />

Connected Croydon: East<br />

Croydon<br />

LBC<br />

LBC, Network London, TfL, Homes and<br />

Communities Agency, Royal Mail Group,<br />

Menta, Stanhope Schroders<br />

Network Rail, LBC Capital<br />

Programme, Growth Area Fund,<br />

S106, MRF, TfL Biking Boroughs,<br />

TfL LIP Major Scheme<br />

£25,240,000 COA Y Y<br />

3<br />

Connected Croydon: West<br />

Croydon<br />

LBC, Network<br />

Rail<br />

LBC, GLA, Network Rail, TfL, Barratt Homes,<br />

CBRE Investors, Mapeley, Portman Square<br />

Holdings, Purespace Group, St Michael and<br />

All Angels Church, Canmoor<br />

MRF £4.6m COA Y<br />

3<br />

Connected Croydon: High<br />

Streets<br />

LBC<br />

LBC, GLA, TfL, Local business and<br />

communities<br />

MRF, TfL Local Implementation<br />

Plan, Growth Area Fund<br />

£10m COA Y<br />

3<br />

Connected Croydon: Wellesley<br />

Road Crossings<br />

LBC LBC, GLA, TfL MRF, LBC Capital Programme,<br />

Growth Area Fund, S106, GLA,<br />

HPDG<br />

£6.6m COA Y<br />

3<br />

Connected Croydon: Connect 2 LBC LBC, TfL, Sustrans TfL LIP Greenways, LBC Capital<br />

Programme, TfL Sustrans, S106<br />

£3.4m COA Y<br />

3<br />

Connected Croydon: Fair Field LBC LBC, Bridgewater Property, CCURV, Croydon<br />

College, Fairfield Halls Trustees, Magistrates<br />

Court, Metropolitan Property, Network Rail,<br />

NCP, Terrace Hill, TfL<br />

LBC Capital Programme, £2.2m COA Y<br />

112<br />

3


INFRASTRUCTURE DELIVERY PLAN: SCHEDULE BY LOCATION– 16 PLACES OF CROYDON<br />

Planned Provision Lead Partner Delivery<br />

Partners/<br />

Stakeholder<br />

Delivery Mechanism/Funding<br />

Source<br />

Cost (if known) Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to CLP Strategic<br />

Policies: (3) Critical, (2) Necessary, (1)<br />

Contributory<br />

Public Realm: New Addington<br />

Phase 2<br />

LBC TfL LBC Capital Programme, CIL £864,000 Addington Y<br />

3<br />

New Addington: Rationalisation of<br />

public sector assets, new<br />

community centre, library<br />

relocation and public realm<br />

enhancements<br />

LBC GLA, LBC LBC- £30K<br />

GLA MRF– £800K<br />

GLA OLF- £500K<br />

£1.330m Addington Y<br />

2<br />

New Addington Masterplan:<br />

Leisure Centre<br />

LBC LBC, Fusion LBC- £30K<br />

GLA MRF– £800K<br />

GLA OLF- £500K<br />

£17m Addington Y<br />

2<br />

New build New Addington GP-led<br />

Health Centre<br />

NHS Croydon<br />

NHS Croydon,<br />

LBC, Healthcare<br />

for London<br />

LIFT, planning obligations,<br />

DoH NHS allocations<br />

TBC Addington Y<br />

2<br />

Planned Provision Lead Partner Delivery<br />

Partners/<br />

Stakeholder<br />

Delivery Mechanism/Funding<br />

Source<br />

Cost (if known) Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to CLP Strategic<br />

Policies: (3) Critical, (2) Necessary, (1)<br />

Contributory<br />

Ark Oval– expansion (1FE) LBC CFL LBC Education Estates Strategy TBC Addiscombe Y<br />

3<br />

Planned Provision Lead Partner Delivery<br />

Partners/<br />

Stakeholder<br />

Delivery Mechanism/Funding<br />

Source<br />

Cost (if known) Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to CLP Strategic<br />

Policies: (3) Critical, (2) Necessary, (1)<br />

Contributory<br />

New school at Westways Centre<br />

(3FE)<br />

LBC CFL LBC Education Estates Strategy TBC Broad Green and Selhurst Y<br />

3<br />

West Thornton Primary Academy LBC CFL LBC Education Estates Strategy TBC Broad Green and Selhurst Y<br />

3<br />

Kingsley Primary– expansion (1FE) LBC CFL LBC Education Estates Strategy TBC Broad Green and Selhurst Y<br />

3<br />

Redevelopment of Croydon<br />

University Hospital Site , with the<br />

provision of an Urgent Care<br />

NHS Croydon<br />

NHS Croydon,<br />

LBC, Healthcare<br />

for London<br />

LIFT, planning obligations,<br />

DoH NHS allocations<br />

TBC Broad Green and Selhurst Y<br />

2<br />

113


INFRASTRUCTURE DELIVERY PLAN: SCHEDULE BY LOCATION– 16 PLACES OF CROYDON<br />

Planned Provision Lead Partner Delivery<br />

Partners/<br />

Stakeholder<br />

Delivery Mechanism/Funding<br />

Source<br />

Cost (if known) Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to CLP Strategic<br />

Policies: (3) Critical, (2) Necessary, (1)<br />

Contributory<br />

St Joseph’s Catholic Infants and<br />

Juniors– expansion (1FE)<br />

LBC CFL LBC Education Estates Strategy TBC Crystal Palace and Upper<br />

Norwood<br />

Y<br />

3<br />

Planned Provision Lead Partner Delivery<br />

Partners/<br />

Stakeholder<br />

Delivery Mechanism/Funding<br />

Source<br />

Cost (if known) Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to CLP Strategic<br />

Policies: (3) Critical, (2) Necessary, (1)<br />

Contributory<br />

Enterprise centres for creative and<br />

cultural industries<br />

LBC<br />

LBC, ACAVA,<br />

CCURV, ACME,<br />

Croydon<br />

College<br />

LBC Capital Programme, S106,<br />

CIL<br />

COA, Crystal Palace,<br />

Portland Road/South,<br />

Norwood and Purley<br />

Y<br />

Y<br />

2<br />

Purley Town Centre: Change to<br />

gyratory<br />

Purley Town Centre: Road network<br />

and public realm enhancement<br />

TfL LBC TfL TBC Purley Y<br />

LBC TfL TfL £7.4m Purley Y Y<br />

2<br />

2<br />

Replacement for Purley Fire Station London Fire Brigade<br />

London Fire<br />

Brigade<br />

Purley<br />

Y<br />

2<br />

Planned Provision Lead Partner Delivery<br />

Partners/<br />

Stakeholder<br />

Delivery Mechanism/Funding<br />

Source<br />

Cost (if known) Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to CLP Strategic<br />

Policies: (3) Critical, (2) Necessary, (1)<br />

Contributory<br />

Replacement for Croydon<br />

Ambulance Station<br />

London Ambulance<br />

Service<br />

London<br />

Ambulance<br />

Service<br />

Shirley<br />

Y<br />

2<br />

114


INFRASTRUCTURE DELIVERY PLAN: SCHEDULE BY LOCATION– 16 PLACES OF CROYDON<br />

Planned Provision Lead Partner Delivery<br />

Partners/<br />

Stakeholder<br />

Delivery Mechanism/Funding<br />

Source<br />

Cost (if known) Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to CLP Strategic<br />

Policies: (3) Critical, (2) Necessary, (1)<br />

Contributory<br />

Ryelands Primary School-relocation<br />

of existing school (2FE)<br />

LBC CFL LBC Education Estates Strategy TBC South Norwood and<br />

Woodside<br />

Y<br />

3<br />

Croydon Arena- (6FE) LBC CFL LBC Education Estates Strategy £29.3m South Norwood and<br />

Woodside<br />

Y<br />

Y<br />

3<br />

Expansion at Resource Base 1 at<br />

Croydon Arena–10 to 15 places<br />

LBC CFL LBC Education Estates Strategy £780,000 South Norwood and<br />

Woodside<br />

Y<br />

1<br />

New School at Tennison Road-50<br />

places<br />

Education Estates Strategy £7m South Norwood and<br />

Woodside<br />

3<br />

Provision of new school and<br />

upgrading of Croydon Sports Arena<br />

LBC<br />

LBC, Croydon<br />

Harriers<br />

Athletics Club &<br />

Croydon<br />

Football Club<br />

South Norwood and<br />

Woodside<br />

Y Y Y<br />

3<br />

Redevelopment of Woodside<br />

Health Centre to expand services<br />

NHS Croydon<br />

NHS Croydon,<br />

LBC, Healthcare<br />

for London<br />

LIFT, planning obligations,<br />

DoH NHS allocations<br />

TBC<br />

South Norwood and<br />

Woodside<br />

Y<br />

2<br />

Enterprise centres for creative and<br />

cultural industries<br />

LBC<br />

LBC, ACAVA,<br />

CCURV, ACME,<br />

Croydon<br />

College<br />

LBC Capital Programme, S106,<br />

CIL<br />

COA, Crystal Palace,<br />

Portland Road/South,<br />

Norwood and Purley<br />

Y<br />

Y<br />

2<br />

South Norwood Public Realm LBC TfL LBC Capital Programme, CIL £241,005 South Norwood and<br />

Woodside<br />

Y Y Y<br />

3<br />

Planned Provision Lead Partner Delivery<br />

Partners/<br />

Stakeholder<br />

Delivery Mechanism/Funding<br />

Source<br />

Cost (if known) Location 2011-<br />

2015<br />

2016-<br />

2020<br />

2021- Relationship to CLP Strategic<br />

Policies: (3) Critical, (2) Necessary, (1)<br />

Contributory<br />

Provision of a new burial ground on<br />

land adjoining Greenlawns<br />

LBC<br />

LBC, Tandridge<br />

District Council<br />

£75k identified from LBC<br />

Capital Budget<br />

£1.04million Tandridge Y<br />

1<br />

115


INFRASTRUCTURE DELIVERY PLAN: IDENTIFIED COSTS<br />

Programme<br />

Enterprising City<br />

Learning City<br />

Creative City<br />

Connected City<br />

Sustainable City<br />

Caring City Programme<br />

Total Costs<br />

£1.9m<br />

£37.08m<br />

£33.7m<br />

£366.45m<br />

£343.73m<br />

£1.04m<br />

Priority<br />

Total Costs<br />

3 £405.26m<br />

2 £179.63m<br />

1 £199.01m<br />

Location<br />

Borough-wide<br />

Total Costs<br />

£164.84m<br />

North of the Borough £150m<br />

South of the Borough<br />

Croydon Opportunity Area<br />

Addington<br />

£14.1m<br />

£390.01m<br />

£19.19m<br />

Addiscombe -<br />

116


INFRASTRUCTURE DELIVERY PLAN: IDENTIFIED COSTS<br />

Location<br />

Total Costs<br />

Broad Green and Selhurst -<br />

Crystal Palace and Upper Norwood -<br />

Purley<br />

South Norwood and Woodside<br />

Tandridge<br />

£7.4m<br />

£37.32m<br />

£1.04m<br />

Please note: The costs set out above are for those projects where figures are available and total in excess of £780m. However, for many projects, detailed<br />

costings are not currently available to inform this IDP Update. Therefore, total investment in Croydon’s <strong>infrastructure</strong> will be higher than indicated. Updates<br />

regarding costs will be included in future updates of the IDP.<br />

117