NOTICE OF MEETING AND AGENDA - Metro Transit
NOTICE OF MEETING AND AGENDA - Metro Transit
NOTICE OF MEETING AND AGENDA - Metro Transit
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
Operations Committee<br />
Capital Projects Update - Engineering<br />
June 19, 2012<br />
Page 2<br />
UMSL Interlocking<br />
• Scope – The UMSL Interlocking project consists of the construction of a new universal<br />
mainline crossover (Interlocking). The average separation of mainline crossover tracks on<br />
the Phase 1 <strong>Metro</strong>Link Alignment is approximately 2 miles. However, over the subject<br />
segment of the alignment, the distance between the North Hanley and Page Interlockings is<br />
4.2 miles. Installation of the new interlocking will provide much needed operational<br />
flexibility with regard to maintenance and incident management. <strong>Metro</strong> manages all aspects<br />
of the design, material procurement and construction of multiple bid packages for civil, track,<br />
traction power, signals, and communications work associated with this project. The location<br />
of the planned UMSL Interlocking is just south of the existing UMSL South <strong>Metro</strong>Link<br />
Station.<br />
• Budget – The total project budget is currently $9,931,880. The original budget was<br />
$8,487,106. The low bid to perform all work associated with this project was $9,700,000, in<br />
December 2010. <strong>Metro</strong> made the decision to cancel that solicitation and take on the<br />
management and coordination of all project disciplines in the interest of minimizing cost. By<br />
breaking the project into discreet construction and procurement packages, <strong>Metro</strong> is on track<br />
to realize roughly $2,000,000, in overall project savings.<br />
• Schedule - Civil and Track Installation work are currently under contract and actively<br />
working. Both of these disciplines will complete in the third quarter of 2012. The Signal<br />
Installation contract is waiting to be awarded and represents the project critical path,<br />
completing in February 2013.<br />
MANAGEMENT RECOMMENDATION:<br />
No action is required. This material is provided for information only.