<strong>Metro</strong> Agenda Item<br />

Operations Committee<br />

June 19, 2012<br />

From: Raymond A. Friem, Chief Operating Officer - <strong>Transit</strong><br />

Subject: Automated Fare Collection and Smart Card System Update<br />

Disposition: Information/Presentation<br />

Presentation: Christopher C. Poehler, P.E. Senior VP, Engineering & New Systems<br />

Development; Thomas White, Fare Collection Project Manager; Anjana Mohan,<br />

Fare Collection Deputy Project Manager<br />

OBJECTIVES:<br />

To inform the Operations Committee of the current project status and schedule for the Automatic<br />

Fare Collection and Smart Card System.<br />

BACKGROUND:<br />

<strong>Metro</strong> is in the process of implementing a system-wide fare collection system utilizing smart<br />

card technology. The project consists of upgrading existing TVM and validators, replacing the<br />

outdated bus farebox equipment and installing a smart card back-end system. The System shall<br />

support <strong>Metro</strong> and Madison County <strong>Transit</strong> (MCT), and possible future participants.<br />

ANALYSIS:<br />

The attached presentation provides information on project status, schedule and near-term<br />

installation activities. The following provides highlights of the attached presentation.<br />

Project Status<br />

Farebox Contractor – Scheidt & Bachmann<br />

• Scheidt & Bachmann has started on the Phase 1 activities, which consists of the design and<br />

construction of fareboxes for cash and existing paper fare media use.<br />

• They have procured the materials for the farebox and have begun the manufacture of the first<br />

set of 50 fareboxes. The first Farebox was completed on June 1, 2012.<br />

• They have started preparing for farebox performance testing.<br />

Smart Card Contractor – Indra<br />

• Indra Installed the draft system software on <strong>Metro</strong>’s virtual Servers for testing<br />

• They passed the Functional Testing of the Ticket Vending Machines (TVMs)<br />

• They are preparing to deliver new TVMs and install them in Illinois<br />

• They are preparing to upgrade Missouri TVMs<br />

• They are preparing to deliver and install new Missouri and Illinois Validators<br />

• TVM Installation and Upgrades August 2012<br />

Near Term Project Schedule<br />

• Validator Installation September 2012