Lower Pilarcitos Creek Groundwater Basin Study - Coastside ...
Lower Pilarcitos Creek Groundwater Basin Study - Coastside ...
Lower Pilarcitos Creek Groundwater Basin Study - Coastside ...
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
and titration, and finally (3) disinfected and pH adjustment by caustic soda for corrosion<br />
control.<br />
Two types of aeration have been considered: one would be stripping through a<br />
packed tower, the other by providing a tank of 10,000 gallons resulting in about 20-<br />
minute retention at peak flow, and diffused air stripping and oxidation. Costs are based<br />
on the latter approach as either double pumping from a packed tower aerator or locating<br />
the bottom of its 20 plus feet height above the level of the flash mixers (Kennedy/Jenks,<br />
1988). The latter approach is not considered to be as feasible or cost effective.<br />
The construction costs of the aeration facilities are estimated at $105,500, and of<br />
the chemical storage feed facilities, $39,000. An additional $15,000 is estimated for<br />
contractor’s contingency for water treatment plant disruption, which provide for a total<br />
construction cost of $159,000 at the WTP<br />
as follows:<br />
Capital Costs. The capital costs of the various project elements are summarized<br />
Land Purchase, five lots at $100,000 $ 500,000<br />
Construction Wells, five wells at $146,000 730,000<br />
Transmission Pipeline 832,000<br />
Water Treatment 159,000<br />
SCADA 87,000<br />
Construction Subtotal $2,308,000<br />
Engineering Design & Construction Management at 15 percent $ 346,000<br />
Construction Total $2,654,000<br />
Other Costs:<br />
Environmental – CEQA – 5 percent Construction 115,000<br />
Coastal Development Permits & Acquisition 50,000<br />
CCWD Staff Costs, Legal, Administrative & Engineering 50,000<br />
Subtotal $ 215,000<br />
Total Current Budget Cost Estimate $2,869,000<br />
Escalation at 3 percent per year – 3 years (9 percent) $ 258,000<br />
Budget Total $3,127,000<br />
Operations and Maintenance Costs. The operations and maintenance costs<br />
are based upon the cost of an annual supply from the <strong>Lower</strong> <strong>Pilarcitos</strong> <strong>Creek</strong><br />
groundwater basin of 75 MGY (146 gpm; 0.21 MGD). Energy costs are based upon the<br />
current average cost of 10.1¢ per kilowatt-hour (KWH) and Nunes WTP costs of 7.1¢ per<br />
100 cubic feet (ft 3 ) of treated water (Mier, February 2003). Labor costs are estimated to<br />
be 5 hours per week additional at the Nunes WTP, and 2 hours per week at the wells.<br />
59