Electrostatic precipitator replacement<br />
“<strong>Mammoet</strong> USA<br />
suggested replacing<br />
each ESP as<br />
a complete unit”<br />
Power<br />
LOCATION: FLAMANVILLE, FRANCE<br />
JOB: LIFTING AND ASSEMBLING<br />
A TUNNEL BORING MACHINE<br />
CHALLENGE: A SMALL AND<br />
CROWDED SITE<br />
18 19<br />
Two Electrostatic Precipitators in a Crystel River Florida Power Plant were in need of<br />
replacement. Normally, the replacement of hundreds of ESP plates and other components<br />
would require a long shutdown. However, <strong>Mammoet</strong> USA suggested replacing<br />
each ESP as a complete unit and was commissioned to design the chamber assembly<br />
frames, transport the chambers on site and lift them into position.<br />
We used a PTC 35 DS with 80 meter main boom, 45 meter jib and 1,600 ton counterweight.<br />
The ESPs (8 x 13 x 17 meters, 400 tons) were transported on site using SPMTs.<br />
After that, it took only two hours to position the first unit, operating at a radius of 89<br />
meters. That was quite a challenge as the ESP had only 15 millimeters clearance and the<br />
boom only had 600 millimeters clearance.<br />
“Tunnel boring<br />
machine<br />
components<br />
lowered down<br />
the shaft”<br />
LOCATION: CRYSTAL RIVER,<br />
FLORIDA, USA<br />
JOB: LIFTING ESP CHAMBERS<br />
IN POSITION<br />
CHALLENGE: RESTRICTED<br />
CLEARANCE<br />
Power station in France A new plant in Russia<br />
The new nuclear power station at<br />
Flamanville will have cooling water tunnels<br />
leading to the sea. <strong>Mammoet</strong> France lowered<br />
the components of the tunnel boring<br />
machine down the access shaft with a CC<br />
2400 SSL crane and assisted with the<br />
assembly of the unit. The heaviest component<br />
weighed 163 tons. We had to<br />
operate on a small and crowded site,<br />
which made the work quite difficult, but<br />
managed to keep to the schedule. Our<br />
new LTM 11200 and SPMTs were used to<br />
install a gantry crane in the powerhouse.<br />
Each of the two gantry beams weighed<br />
180 tons and was 52 meters long.<br />
<strong>Mammoet</strong> Seumersteel was awarded the<br />
contract to supply a CC 2600 and two<br />
LTM 1250s for the construction of a new<br />
plant at one of the oldest power stations<br />
in the Moscow region. The work was quite<br />
different from our normal operations<br />
in Russia. Good preparation and close<br />
cooperation with the customer ensured<br />
that the lifts were completed safely and<br />
efficiently.<br />
LOCATION: SHATURA, MOSCOW<br />
REGION, RUSSIA<br />
JOB: HEAVY LIFTS<br />
CHALLENGE: LIFT WITH THREE<br />