You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
<strong>Mammoet</strong> Canada Eastern was contracted to receive, barge, transport, and erect 86 wind turbines for the Wolfe Island Wind Project. As the water<br />
around the Island is relatively shallow, all parts were first received and stored at the Port of Ogdensburg, New York. The turbines were then transferred<br />
onto barges and towed to Wolfe Island, a small island located in the St. Lawrence River between Canada and the USA, and subsequently<br />
transported about four kilometers to the 30-acre laydown yard on the Island. Due to the high volume and the limited timeframe, a huge amount of<br />
equipment and manpower was required to deliver the turbines. With the combined equipment fleet of <strong>Mammoet</strong> Canada and <strong>Mammoet</strong> USA, the<br />
job required 15 trucks, 17 cranes, 27 trailer combinations, and 62 field staff to move and erect 86 – 2.3 megawatt wind turbines consisting of 1,000<br />
items of oversize cargo. Stationed at Wolfe Island were Burnell Gerber, Transport Supervisor, <strong>Mammoet</strong> Canada Eastern, and Rob Binkley, Crane<br />
Operator, <strong>Mammoet</strong> Crane Inc.-East. Providing the engineering was Barend Schuring, <strong>Mammoet</strong> Canada Eastern.<br />
LOCATION: WOLFE ISLAND, ONTARIO,<br />
CANADA AND OGDENSBURG, NEW<br />
YORK, USA<br />
JOB: TRANSPORTING AND INSTALLING<br />
WIND TURBINES<br />
CHALLENGE: COMPLEX LOGISTICS<br />
Burnell Gerber aka Barney<br />
Three perspectives<br />
of the Wolfe Island<br />
Wind Project<br />
Burnell Gerber,<br />
Transport Supervisor<br />
Biggest Challenges<br />
As the Transport Supervisor on this job, it<br />
was my responsibility to do all I could to<br />
make our work sites as efficient and safe as<br />
possible and to ensure all groups of men<br />
worked together as a team. The barge<br />
unloading / reloading was at the top of my<br />
list. I also had to receive all other equipment<br />
coming to this laydown yard. Things got a<br />
little hectic at times. The yard crew and<br />
supervisor did a fantastic job in keeping up<br />
with all of this excitement. The St. Lawrence<br />
Seaway closed on December 21 because of<br />
ice conditions; therefore, all component<br />
barges were delivered by December 20.<br />
Barge work, transport, and yard crews all<br />
pulled together. Safety was always at the<br />
top of our list. Each morning we started our<br />
day in our lunch room trailer where we held<br />
our Toolbox Meeting. Each safety meeting<br />
started with the work on the barge. We also<br />
discussed the previous day’s activities and<br />
any problems encountered. The floor was<br />
always open for discussion. We all wanted<br />
to be on a winning team!<br />
Best Accomplishments<br />
Moving transformers in Vermont has to rate<br />
at the top of my list of ‘best accomplishments’.<br />
All work in the Northeast USA has<br />
been a testament to <strong>Mammoet</strong>’s ability to<br />
overcome some logistical nightmares. Over<br />
the years, I have had some great foremen.<br />
They took the time to show me how to do<br />
my work safely. They took the time to let me<br />
know what could really hurt me. Putting<br />
safety and people first means so much.<br />
Absolute Highlights<br />
When I think back to day one on this<br />
project, I wondered how we were going to<br />
get the job done with so many new guys! I<br />
realized how much I depended on those I<br />
have worked with before. They are so professional<br />
in performing their duties. With the<br />
help of competent operators, the new<br />
employees were shown how to do it the<br />
‘<strong>Mammoet</strong> way’. Work safely, work smart<br />
and have some fun! Our crew in the laydown<br />
yard was a well-oiled machine,<br />
though their workload was heavy.<br />
Rob Binkley, Crane<br />
Operator<br />
Biggest Challenges<br />
Upon being assigned to the Wolfe Island<br />
Project, I became responsible for mobilizing<br />
and demobilizing cranes, coordinating crane<br />
movements (including assembly and disassembly),<br />
and building crawler pads for<br />
cranes to stand on. In the down time, I also<br />
operated different types of cranes, including<br />
the CC 2800, LT 1550, AC 500 and LTM<br />
1300, for various parts of the turbine lifts.<br />
The safety and well-being of my fellow<br />
employees, as well as the crew and<br />
Rob Binkley<br />
28 29 Visit <strong>Mammoet</strong>’s