16.01.2015 Views

here - Atomic Energy Regulatory Board

here - Atomic Energy Regulatory Board

here - Atomic Energy Regulatory Board

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

out and clearances were issued in sub-stages, accordingly.<br />

After satisfactory resolution of all issues arising from the<br />

review and after completion of the prerequisites,<br />

authorization for FAC was granted on February 25, 2007<br />

and the unit achieved first criticality at 10:10 hours on<br />

February 26, 2007. Subsequently, after review of the results<br />

of first criticality, AERB granted authorization for phase-B<br />

low power physics tests. AERB granted authorization on<br />

March 26, 2007 for synchronization of the unit to the power<br />

grid and operation of the reactor power up to 50 % FP<br />

after successful completion of phase-B tests and review of<br />

the results.<br />

ACPSR-PHWR Members visiting KGS-3 Control Room<br />

From L to R: Shri R.I. Gujarathi, Director, NPSD, Dr. S. M. Lee,<br />

Chairman, PDSC-KGS-3&4, Shri S.K. Chande, VC-AERB,<br />

Shri S.S. Bajaj, Senior ED (Safety),NPCIl and Shri K. Ramamurthy,<br />

Station Director, KGS-3&4 Shri S.K. Chande, VC-AERB,<br />

Shri S.S. Bajaj, Senior ED (Safety), NPCIl and Shri K. Ramamurthy,<br />

Station Director, KGS-3&4<br />

For KGS-4, civil construction activities and erection<br />

of various systems, equipments and components are in<br />

progress.<br />

Civil construction activities and erection of various<br />

systems, components and equipment remained in progress<br />

for RAPP-5&6 units. It is expected that containment proof<br />

test, Integrated Leakage Rate Test (ILRT) and PHT system<br />

hot conditioning and light water commissioning would be<br />

taken up for RAPP-5 in the second quarter of 2007 after<br />

completion of required review.<br />

Some of the important observations made during<br />

design safety review of these 4 units and commissioning of<br />

KGS-3 are given below.<br />

●<br />

Containment proof test and ILRT of KGS-3 was carried<br />

out during November 2006. Observed leakage rate<br />

was 0.24 % of contained air volume per hour at 1.06<br />

kg/cm 2 . Interception by Secondary Containment (SC)<br />

was measured and was found to be more than 90 %<br />

as per the design intent. Containment isolation test was<br />

carried out in an integrated manner prior to FAC and<br />

results were satisfactory.<br />

●<br />

●<br />

●<br />

●<br />

●<br />

●<br />

The hot conditioning of KGS-3 was completed<br />

successfully and protective uniform magnetite layer of<br />

0.43 microns was achieved. Emergency Core Cooling<br />

System (ECCS) test and other light water tests related<br />

to PHT system were carried out and system performance<br />

was satisfactory.<br />

The design feature of on-line clutch release test for<br />

primary shutdown system has been incorporated in all<br />

the 4 units.<br />

Each of the 4 units has been provided with 3 Diesel<br />

Generator (DG) sets of 2400 kW each. After site<br />

installation, while testing of DGs of KGS-3 for the largest<br />

available load of 400 kW of Primary Pressurizing Pump<br />

(PPP) motor, the 6.6 KV DG terminal voltage collapsed<br />

and the PPP motor could not be started. This was due<br />

to voltage dip in excitation transformer, which is<br />

supplying excitation requirements of the pilot exciter of<br />

the alternator of DG set. The DG set performance<br />

became satisfactory when excitation requirement of DG<br />

alternator was fed from Class II buses. NPCIL<br />

proposed, as an interim measure, to install a 1 kVA<br />

inverter powered from 220 V class I buses of station<br />

power supply to cater the excitation requirements of<br />

the pilot exciter of each DG alternator and the proposal<br />

was accepted after the review. NPCIL has been asked<br />

to explore an alternate solution in consultation with<br />

manufacturer. In view of the above, a new clause – ‘If<br />

any of the two power UPS on its battery bank is not<br />

available or any of the class-II buses are not available,<br />

the reactor shall be brought to cold shut-down state’<br />

has been added in the technical specifications for<br />

operation.<br />

Each of these DG sets was equipped with a Class II<br />

electrically driven Crank Case Exhaust (CCE) fan. As<br />

per the manufacturer, the DG sets can run safely for<br />

~32 seconds only without availability of the CCE fan.<br />

Logic has been provided to trip the DG sets with 27<br />

seconds delay in case the CCE fan does not start.<br />

Subsequently, the fan power supply was changed over<br />

to Class III power supply to reduce the dependence of<br />

DG starting on Class II power supplies.<br />

For 1 of the 6 ion-chamber housings, the distance<br />

between calandria and the housing was found to be 28<br />

mm instead of the specified value of 20 mm. The<br />

reason of the deviation was reviewed and the deviation<br />

on neutron power readings/attenuation factor for the<br />

ion-chambers was found acceptable.<br />

Due emphasis was given for environmental<br />

qualifications of safety related structures, equipment<br />

and components since the design stage of KGS-3&4.<br />

NPCIL has been asked to submit a comprehensive<br />

report covering methodology followed, standards used,<br />

tests done, analysis carried out, etc., in this regard for<br />

review.<br />

8

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!