e) For the purpose of recovery of the amount, unpaid amount / security deposit/ SD by way of<br />

BG, provided by the vendor will be adjusted first, If there is any balance left to be recovered,<br />

the Vendor should be informed to deposit the money at the earliest.<br />

f) If he fails to deposit the balance amount no further enquiry will be given as per banning<br />

procedure.<br />

g) In case the amount is considerable, legal action may be considered by TAA. However in case<br />

of TAA is Board or Chairman, approval of concerned member shall be obtained.<br />

Alternatively, the Purchaser may short close the Order stating the reason for not resorting to risk<br />

purchase clause with approval of TAA.<br />

In the event of recourse to alternatives as mentioned above, the Purchaser will have the right to<br />

re-purchase the stores or complete the work, to meet urgency in requirement caused by Vendor’s<br />

failure to comply with the schedule of delivery or completion of the work or services irrespective<br />

of the fact whether the materials / equipments/ work/ service are similar or not.<br />

41. REASONABILITY OF PRICES:<br />

The Tender Committee has to assess the reasonableness of the offers. The Tenders with any<br />

condition shall normally be rejected. However, Tenders with conditional rebates/discounts may<br />

be considered, but without taking into account the conditional rebate/discount for the purpose of<br />

evaluation of the bid price. Tender Committee should specifically draw the attention of TAA to<br />

such conditional rebate/discount and to the fact that the evaluated cost of the Tenders is without<br />

considering such rebates/discounts. Tenders with unconditional rebate can be accepted. The<br />

following procedure may be considered for reasonability of rate:<br />

1. Total amount quoted by valid Tenderer should be compared with the estimated cost put to<br />

Tender duly enhanced by cost index, if available, and in absence of related indices, inflation @<br />

6% p.a. or part there off may be considered during the period of preparation of estimate to<br />

opening of the bid.<br />

2. There is no need for preparing justification statement, in case the offered price of lowest<br />

Tender is less than the enhanced estimated cost under sl.No.1 plus (+) 10 % thereof. However,<br />

the acceptance of Tender, remaining provision of Works & Purchase Manual shall apply.<br />

or<br />

3. Reasonability of the rate of Tenders is to be seen and commented upon by the TC. While<br />

accepting Tenders, rates of Tender of similar nature of Works placed within about last 3<br />

months may be referred to. Similar works shall mean similar in nature, quantum, specification<br />

and location in the near vicinity. Variation over market/justified rate upto +5% in total amount<br />

can be ignored.<br />

or<br />

4. In case of urgency, if certified by the user section, variation upto 10% of revised market cost<br />

under Sl.No.3 above may be allowed for recorded reason.<br />

W& P Manual – 2012 Page 68