China<br />
Production imminent from Jiangsu plant<br />
GALAXY Resources expects to achieve first<br />
production at the Jiangsu Lithium Carbonate<br />
Project in Jiangsu Province by the end of<br />
March. Mechanical completion of the plant<br />
was completed in December with the commissioning<br />
process being undertaken during<br />
the current quarter.<br />
After receiving construction completion certificates<br />
for all areas of the plant from EPCM<br />
contractor Hatch Engineering, Galaxy began<br />
the cold commissioning process which involves<br />
ensuring the integrity of plant, equipment, electrical,<br />
instrumentation and control systems.<br />
Galaxy’s managing director Iggy Tan said<br />
this process had been progressing well without<br />
any major defect issues being identified.<br />
It was expected to be completed in mid-February.<br />
“Some areas of the plant like micronizing<br />
and packaging have progressed to hot<br />
commissioning and operation. <strong>The</strong> company<br />
is very satisfied with the progress to date and,<br />
if no major defects are identified, we expect<br />
the plant to be well into hot commissioning<br />
by late February and the first lithium carbonate<br />
produced by the end of the quarter.<br />
“Our operations team continues to be fully<br />
involved in all stages of commissioning activities<br />
to ensure a smooth transfer from the commissioning<br />
to the operations phase,” he said.<br />
<strong>The</strong> plant fire protection system has been<br />
inspected and accepted by a third-party and<br />
local government. An environment system<br />
completion report was submitted to the<br />
Jiangsu Provincial Government, with an onsite<br />
inspection scheduled, and this is expected<br />
to lead to final production and start<br />
up approvals. During February the kilns, with<br />
associated coolers, and the sodium sulphate<br />
Construction advances on the reagents and utilities plant at Galaxy Resources’ Jiangsu lithium carbonate plant.<br />
plant were to be commissioned with this involving<br />
the final dry out and firing of both the<br />
calciner and the sulphation kiln.<br />
Galaxy says the spodumene unloading system<br />
at the Two Lions wharf, overland conveyor<br />
and ore storage area have been fully commissioned,<br />
with trial shipments being successfully<br />
unloaded. A 31,000 tonne spodumene shipment<br />
from Galaxy’s Mt Cattlin mine in Western<br />
Australia was successfully unloaded and conveyed<br />
to the plant ore storage area.<br />
At Mt Cattlin Galaxy mines lithium pegmatite<br />
ore and processes it on site to produce<br />
a spodumene concentrate and<br />
tantalum by-product. At full capacity, Galaxy<br />
will annually produce 137,000 tonnes of spodumene<br />
concentrate and 56,000 pounds of<br />
contained tantalum. <strong>The</strong> concentrate is<br />
shipped to the Jiangsu plant which is expected<br />
to annually produce 17,000 tonnes of<br />
battery grade lithium carbonate.<br />
Galaxy also has a farm-in agreement with<br />
Lithium One to acquire up to 70% of the<br />
James Bay Lithium Pegmatite Project in Quebec,<br />
Canada, while it is also advancing plans<br />
for a lithium-ion battery plant, to produce<br />
350,000 battery packs annually for the electric<br />
bike market.<br />
江 苏 碳 酸 锂 工 厂 即 将 投 产<br />
银 河 资 源 有 限 公 司 旗 下 位 于 江 苏 省 的 江 苏 碳<br />
酸 锂 项 目 预 计 在 3 月 底 实 现 首 次 生 产 。 该 厂<br />
在 12 月 份 完 成 了 机 械 竣 工 , 当 前 季 度 正 在<br />
进 行 试 运 行 。<br />
银 河 资 源 在 收 到 总 包 工 程 管 理 公 司 - 赫 氏<br />
工 程 公 司 给 出 的 碳 酸 锂 工 厂 所 有 区 域 的 竣 工<br />
证 书 后 , 开 始 冷 试 车 , 其 中 包 括 确 保 厂 房 、<br />
设 备 、 电 气 、 仪 器 和 控 制 系 统 的 完 善 。<br />
银 河 的 董 事 总 经 理 Iggy Tan 称 , 该 过 程<br />
进 展 顺 利 , 没 有 发 现 任 何 大 纰 漏 。 预 计 于 2<br />
月 中 旬 结 束 。“ 工 厂 的 一 些 区 域 例 如 微 粉<br />
和 包 装 车 间 正 在 准 备 进 行 热 试 车 和 运 营 。<br />
公 司 对 迄 今 为 止 的 进 展 感 到 非 常 满 意 , 如<br />
果 没 有 发 现 重 大 缺 陷 , 我 们 预 计 工 厂 在 2 月<br />
末 进 入 热 试 车 阶 段 , 首 批 碳 酸 锂 将 在 本 季<br />
度 末 产 出 。”<br />
“ 我 们 的 运 营 团 队 会 继 续 全 面 参 与 到 试 运<br />
行 的 各 个 阶 段 中 , 以 确 保 从 试 运 行 到 运 营 阶<br />
段 的 顺 利 过 渡 ,” 他 说 道 。<br />
工 厂 的 防 火 系 统 已 经 检 查 完 毕 , 并 已 得 到<br />
第 三 方 和 当 地 政 府 的 认 可 。 环 境 体 系 完 善 报<br />
告 已 经 递 交 江 苏 省 政 府 , 现 场 检 查 工 作 已 经<br />
提 上 日 程 , 预 计 将 推 进 最 终 生 产 和 启 动 的 通<br />
过 。2 月 份 , 煅 烧 窑 及 相 关 的 冷 却 设 备 和 硫<br />
酸 钠 设 备 将 进 行 试 运 行 , 其 中 包 括 煅 烧 窑 和<br />
硫 酸 窑 的 最 后 干 燥 和 烘 烤 。<br />
银 河 资 源 称 , 双 狮 码 头 的 锂 辉 石 装 卸 系<br />
统 、 带 式 传 送 机 和 储 矿 区 域 已 经 全 面 试 行 ,<br />
试 运 货 物 已 经 成 功 卸 载 。 来 自 银 河 资 源 位 于<br />
西 澳 大 利 亚 州 的 Mt Cattlin 矿 区 的 3.1 万 吨 锂<br />
辉 石 已 经 成 功 卸 载 , 并 通 过 传 送 带 运 至 工 厂<br />
的 储 矿 区 域 。<br />
在 Mt Cattlin 矿 区 , 银 河 资 源 开 采 伟 晶 岩<br />
型 锂 矿 石 , 并 在 现 场 处 理 , 生 产 锂 辉 石 精 矿<br />
和 钽 副 产 品 。 全 面 投 产 后 , 银 河 资 源 每 年 将<br />
生 产 13.7 万 吨 锂 辉 石 精 矿 和 5.6 万 磅 钽 。 这<br />
些 精 矿 将 运 至 江 苏 的 工 厂 , 预 计 每 年 生 产<br />
1.7 万 吨 电 池 级 碳 酸 锂 。<br />
银 河 资 源 还 与 Lithium One 公 司 签 署 了 一<br />
份 矿 权 买 入 协 议 , 获 得 了 位 于 加 拿 大 魁 北 克<br />
省 的 詹 姆 斯 湾 伟 晶 岩 型 锂 矿 项 目 70% 的 股<br />
权 , 同 时 , 公 司 正 在 推 进 建 设 一 个 锂 离 子 电<br />
池 厂 的 计 划 , 目 标 是 每 年 为 电 动 车 市 场 生 产<br />
35 万 个 电 池 组 。<br />
32 | <strong>ASIA</strong> <strong>Miner</strong> | March/April <strong>2012</strong>