Edition: October 2011<br />

<strong>Installation</strong> guidelines<br />

System: ONDATHERM <strong>900</strong> C<br />

ArcelorMittal Construction International<br />

Industriestrasse 19<br />

8112 Otelfingen / Zürich<br />

Switzerland<br />

www.arcelormittal.com/arval<br />

ArcelorMittal Construction Page 1 of 21<br />

Javier Cirauqui


Summary<br />

1. Basic principles ........................................................................................................ 3<br />

2. Documentation ......................................................................................................... 3<br />

3. Building site conditions............................................................................................ 3<br />

3.1. Lifting the material ....................................................................................... 4<br />

3.2. Packaging and storage on site....................................................................... 4<br />

3.3. Un-packaging................................................................................................ 5<br />

3.4. Protective film .............................................................................................. 5<br />

4. Safety........................................................................................................................ 5<br />

5. General rules............................................................................................................. 6<br />

5.1. Inspection of existing works......................................................................... 6<br />

5.2. Inspection of installation work ..................................................................... 6<br />

5.3. Structure alignment ...................................................................................... 6<br />

5.4. Installing the panels...................................................................................... 6<br />

6. Cutting and drilling during installation .................................................................... 7<br />

6.1. Cutting .......................................................................................................... 7<br />

6.2. Drilling ......................................................................................................... 7<br />

7. Anchoring, fixing and connecting the panels during installation............................. 7<br />

7.1. General.......................................................................................................... 7<br />

7.2. Fixations and how to fix ............................................................................... 7<br />

7.2.1. Screws....................................................................................................... 8<br />

7.2.2. Blind rivets ............................................................................................... 8<br />

7.2.3. Considerations .......................................................................................... 8<br />

8. System fixation description ...................................................................................... 9<br />

8.1. <strong>Installation</strong> .................................................................................................... 9<br />

8.2. Width of support........................................................................................... 9<br />

8.3. Alignment of the panels................................................................................ 9<br />

8.4. Fixings and connections ............................................................................. 10<br />

8.5. Sealing strips .............................................................................................. 10<br />

8.6. Fillers for profiles sheeting......................................................................... 10<br />

8.7. Drainage...................................................................................................... 11<br />

8.8. Overlaps...................................................................................................... 11<br />

8.8.1. Side laps.................................................................................................. 11<br />

8.8.2. End lap.................................................................................................... 12<br />

8.9. Direction of installation.............................................................................. 12<br />

8.10. Securing for uplift................................................................................... 13<br />

8.11. Holes....................................................................................................... 13<br />

8.12. Design of flashings ................................................................................. 13<br />

8.12.1. Flashings overlap.................................................................................... 14<br />

Annexes .......................................................................................................................... 15<br />

I. Templates ....................................................................................................... 16<br />

I.1. Checking lists templates ............................................................................. 16<br />

I.2. Cutting list templates.................................................................................. 17<br />

I.3. Curved cutting list templates ...................................................................... 20<br />

II. <strong>Installation</strong> ratios ............................................................................................ 21<br />

ArcelorMittal Construction Page 2 of 21<br />

Javier Cirauqui


1. Basic principles<br />

Every project has requirements according with national and local regulations.<br />

These regulations must be taken in consideration to select a system with the<br />

right performances to fulfil the requirements of the project.<br />

Safety, thermal and acoustic comfort, or energy savings may fail if not properly<br />

selected.<br />

Before ordering any material, it must be checked that the selected system<br />

performances are in accordance with the requirements for the project.<br />

1.1. Load bearing of the system support<br />

1.2. Load bearing of the external skin<br />

1.3. Thermal insulation<br />

1.4. Noise insulation<br />

1.5. Acoustic absorption<br />

1.6. Fire behaviour<br />

1.7. Air permeability<br />

2. Documentation<br />

For any project it is necessary to prepare a basic documentation to verify that<br />

the building can be erected in accordance with client’s performance<br />

requirements:<br />

• <strong>Installation</strong> drawings with the layout of the roof or façade and indications<br />

about the position of any profile and the direction of installation should be<br />

a must before starting the erection.<br />

• Details showing how flashings should be positioned, sealed, and fixed.<br />

• Cutting list to have a reference of the materials we have ordered and<br />

ease following of the layout<br />

3. Building site conditions<br />

A necessary task that can save time and money during the erection of the<br />

building is to do a visit to check if:<br />

• Site is in conditions to receive and storage the materials properly<br />

• Free space to place and move the cranes, platforms, scaffoldings, etc.<br />

• Safety measure can be installed<br />

ArcelorMittal Construction Page 3 of 21<br />

Javier Cirauqui


3.1. Lifting the material<br />

Bundles must be handled properly to avoid damaging the material.<br />

Bundles can be handled with:<br />

• Sling belts<br />

• Sling belts and spreader beam<br />

• Fork lift<br />

3.2. Packaging and storage on site<br />

Avoiding the retention of water between sheets and panels is a must to avoid<br />

corrosion.<br />

Bundles must be stored with a slop of 1% to facilitate the evacuation of the<br />

water.<br />

ArcelorMittal Construction Page 4 of 21<br />

Javier Cirauqui


The materials must be distributed on site as close as possible to the area where<br />

they will be installed.<br />

Bundles can not be stacked on top of each other on the construction site.<br />

They can be delivered stacked but they must be unloaded and stored<br />

separately.<br />

When lifting the bundles to the roof, you must secure them to avoid sliding<br />

sheets or panels.<br />

Before leaving bundles on the roof, you must check with the contractor that the<br />

structure can support the bundled weight.<br />

3.3. Un-packaging<br />

When you unpack the materials you have to take care about the risk of<br />

displacements of the materials or up-lifting them due to the wind action.<br />

Waste material has to be taken to the proper place to avoid dirty and risk of<br />

accidents.<br />

3.4. Protective film<br />

Coated products are supplied with a removable<br />

protective film to prevent mechanical damage<br />

during transport and assembly. This film must<br />

be removed 15 days after outside storage<br />

exposed to weather and/or immediately after<br />

installation, whichever is soonest.<br />

4. Safety<br />

The work site must have the collective protective measures installed properly<br />

before starting the works.<br />

These protections must be defined according with the requirements of the<br />

safety project created by the General contractor.<br />

Employees must be equipped with the individual protections appropriated for<br />

the job that they are doing.<br />

Some of the protections are: helmets, gloves, boots, harness, etc.<br />

ArcelorMittal Construction Page 5 of 21<br />

Javier Cirauqui


5. General rules<br />

5.1. Inspection of existing works<br />

Before starting the installation, it is necessary to check the works and analyze if<br />

there are deviations in the existing works (structure alignment, dimensions, etc.)<br />

that could concern your own works and stop you installing materials properly.<br />

5.2. Inspection of installation work<br />

Your own works must be inspected regularly to verify that all the works are<br />

being developed according with the manufacturer’s instructions and the<br />

construction rules.<br />

When works are done professionally, we all will get the customer satisfaction<br />

and reducing the claims.<br />

The checking list documents provided in this document can help to do it.<br />

5.3. Structure alignment<br />

If the structure is not properly aligned, the roof will not be with the right pitch.<br />

Every error in the structure will be transmitted to the roof.<br />

When defects in the alignment, etc. the contractor should correct the defects or<br />

installing a substructure prior starting our works.<br />

Maximum deflection of purlins must be considered to avoid water retentions on<br />

the roof.<br />

5.4. Installing the panels<br />

Panels have to be installed according with the layout drawing prepared for this<br />

job. It must be done in the direction indicated in the drawings.<br />

Before interrupting the day works, profiles must be secured to avoid uplift due to<br />

the wind action.<br />

ArcelorMittal Construction Page 6 of 21<br />

Javier Cirauqui


6. Cutting and drilling during installation<br />

6.1. Cutting<br />

Panels can not be cut with abrasive tools.<br />

Most kinds of saws are suitable to cut steel<br />

sheets and panels if they don’t burn the<br />

material as abrasive tools.<br />

Metal shavings have to be removed from the<br />

area to avoid adverse optical and warranty<br />

issues.<br />

During the cuts, the area where the saw tool<br />

can scratch the sheet must be protected.<br />

6.2. Drilling<br />

Metal shavings from these operations have to be removed to avoid optical and<br />

warranty issues.<br />

7. Anchoring, fixing and connecting the panels during<br />

installation<br />

7.1. General<br />

Depending on the final use of the sheet / panel, its dimension and the<br />

supporting structure, several fixings systems can be used.<br />

Fasteners must have an appropriate corrosion protection for the environment<br />

where the buildings are located.<br />

<strong>Installation</strong> and dimension of the fasteners is described in the next points<br />

7.2. Fixations and how to fix<br />

The next points will describe the possible fasteners, how they must be fitted and<br />

the field of application.<br />

ArcelorMittal Construction Page 7 of 21<br />

Javier Cirauqui


7.2.1. Screws<br />

Screws can be used to fix cladding panels.<br />

Two types of screws are acceptable:<br />

• Self-drilling<br />

• Self-tapping<br />

Tools, power and speed must be fitted according with the technical<br />

recommendations of the screw manufacturers.<br />

In the case of self-tapping screws, the diameter of the hole must be in<br />

concordance with the instruction of the screw manufacturer to keep the loadbearing<br />

capacity.<br />

If the screws have a sealing washer, it is recommended to use a depth stop to<br />

keep the waterproof properties.<br />

No water tight Correct Too tight Oblique<br />

7.2.2. Blind rivets<br />

Blind rivets can be used for stitching two sheets together for side laps,<br />

flashings, etc.<br />

Load-bearing capacity and diameter of the drilled hole must be considered from<br />

the recommendations of the rivets manufacturer.<br />

7.2.3. Considerations<br />

Expansion and contraction of the materials due to the changes of temperature<br />

must be taken in consideration when the type of fixation is decided.<br />

Our technical assistance can support you to choose the right fastener and<br />

indications about how to install it properly.<br />

ArcelorMittal Construction Page 8 of 21<br />

Javier Cirauqui


8. System fixation description<br />

8.1. <strong>Installation</strong><br />

Every system has its own way of installation.<br />

In this case, you must follow the<br />

recommendations below:<br />

• <strong>Installation</strong> of consecutive panels<br />

• <strong>Installation</strong> of the distribution plate and<br />

fixing it in the central hole or two<br />

external holes (depending on uplift<br />

loads) with a screw diameter 6.3 mm x<br />

L<br />

• <strong>Installation</strong> of a thermal insulation<br />

between the two ribs.<br />

• <strong>Installation</strong> of the cover plate clipping<br />

to the ribs and hiding insulation and fixation.<br />

8.2. Width of support<br />

Width of the support must be confirmed according with the product we are using<br />

and, material of the structure and the wind loads<br />

In general, you can consider that for steel structure we need a minimum width:<br />

• End support: 40 mm<br />

• Intermediate supports: 60 mm<br />

Performances of the panels change considerably when we increase the width of<br />

the supports.<br />

8.3. Alignment of the panels<br />

The ribs of the profiles of every row must be aligned on whole surface.<br />

The first panel must be properly vertical or horizontal installed because it is the<br />

reference for the whole roof.<br />

ArcelorMittal Construction Page 9 of 21<br />

Javier Cirauqui


8.4. Fixings and connections<br />

The number of fixings must be calculated per project to ensure the resistance of<br />

the roof / façade to the wind actions.<br />

The selection of the fasteners has to be done according with the thickness of<br />

the structure and the grade of steel.<br />

All the fixings must be protected against corrosion, stainless steel or bichromium<br />

protection.<br />

When water runs off on the fixings, a waterproof washer is a must.<br />

8.5. Sealing strips<br />

End laps must be sealed and also flashing laps<br />

8.6. Fillers for profiles sheeting<br />

Fillers for profiling sheets or panels must be installed properly to avoid dropping<br />

out.<br />

ArcelorMittal Construction Page 10 of 21<br />

Javier Cirauqui


8.7. Drainage<br />

Dimensions of gutters and outlets must be done in accordance with the<br />

technical standards.<br />

Solutions for overflows must be designed an installed when inside mounted<br />

gutter.<br />

8.8. Overlaps<br />

Overlaps must be done according with professional rules to keep the water<br />

tightness under every action.<br />

Panels can be prepared with two types of overlap depending on the slope that<br />

will be placed, right and left overlap. The reason of both overlaps is to allow the<br />

continuity of the ribs from one slope to the other slope at the ridge.<br />

Right overlap<br />

Left overlap<br />

8.8.1. Side laps<br />

As consequence of cover plates, it is not necessary to seal side laps<br />

ArcelorMittal Construction Page 11 of 21<br />

Javier Cirauqui


8.8.2. End lap<br />

End lap must be sealed with a row of<br />

8mm diameter PIB butyl strip positioned<br />

maximum 15mm from the edge of the<br />

under lapping sheet or using butt straps to<br />

achieve a flush joint use tapes as above.<br />

It is not necessary to stitch it.<br />

Cover plate overlap must be displaced 500 mm upstream from panel overlap to<br />

avoid water infiltrations.<br />

8.9. Direction of installation<br />

<strong>Installation</strong> must be done in the direction of the predominant winds. Every<br />

product has its own direction of installation and must be consider before starting<br />

installing it.<br />

ArcelorMittal Construction Page 12 of 21<br />

Javier Cirauqui


8.10. Securing for uplift<br />

Products must be fixed as soon as they are placed on the roof or façade to<br />

avoid any uplift due to the action of the wind.<br />

Before interrupting the work, it is necessary to check that all the products are<br />

properly fixed and the bundles are also fixed with some straps to avoid risks of<br />

falling materials.<br />

Direction of installation is important for an easier secure.<br />

8.11. Holes<br />

Pipe penetrations must be properly made in concordance with the design taking<br />

in consideration that:<br />

• Pipes can not transmit forces to the façade<br />

• Reduction of the thermal bridges is a must<br />

• Flashings must be water and air tight<br />

8.12. Design of flashings<br />

Flashings must be defined following some recommendations:<br />

• Flat surface shouldn’t be larger than 250 mm to keep the flatness<br />

• Small slope is recommended to avoid water retention.<br />

• Drip is recommended in any flashing to reduce the dirty on the façade.<br />

ArcelorMittal Construction Page 13 of 21<br />

Javier Cirauqui


8.12.1. Flashings overlap<br />

Laps can be done:<br />

• Overlapping the flashings 100 mm and adding a sealant butyl tape 15<br />

mm from the end and in front of the stitching screws or using butt straps<br />

to achieve a flush joint use tapes as above<br />

• Joining obtusely to an underlay sheet with sealant tapes 15 mm from the<br />

ends of the two pieces of flashing and in front of the stitching screws.<br />

ArcelorMittal Construction Page 14 of 21<br />

Javier Cirauqui


Annexes<br />

The next annexes are showed as example and orientation, ArcelorMittal<br />

Construction is not responsible about the right use of them.<br />

Other alternatives are possible and the customer must check if the information<br />

is enough for his company.<br />

ArcelorMittal Construction Page 15 of 21<br />

Javier Cirauqui


I. Templates<br />

I.1. Checking lists templates<br />

ArcelorMittal Construction Page 16 of 21<br />

Javier Cirauqui


Only if cutting list,<br />

drawings have been<br />

made by AMC<br />

Only if installation is<br />

supervised by AMC<br />

Check list<br />

Site<br />

Tidy and clean<br />

Y N<br />

Delivery On time<br />

Y N<br />

Number of times<br />

Packages properly storages<br />

Y N<br />

Material properly lifted from packet to site<br />

Y N<br />

On time<br />

Y N<br />

Delays<br />

Y N<br />

Roof<br />

Fixation to the roof Y N<br />

Are properly Junctions<br />

Y N<br />

done Ends<br />

Y N<br />

Gutters<br />

Expansion joints<br />

Y N<br />

Are they Shavings<br />

Y N<br />

clean bubles<br />

Y N<br />

Are installed Joints<br />

Y N<br />

properly mouths<br />

Y N<br />

Aligment of the gutter and ridge<br />

Y N<br />

Undulations, scratchs, dents, material properly managed<br />

Y N<br />

Roof is lengh enough at the gutter<br />

Y N<br />

Overlaps of the roof are properly done<br />

Y N<br />

Fixations are enough and well positioned<br />

Y N<br />

Roof material properly fixed<br />

Y N<br />

Ridge properly installed<br />

Y N<br />

Ridge joints properly installed<br />

Y N<br />

End of the roof material is properly folded<br />

Y N<br />

Fixation of flashings properly done<br />

Y N<br />

Every solution is water proof<br />

Y N<br />

Holes revised and properly done<br />

Y N<br />

Protected film properly retired and storaged<br />

Y N<br />

Roof cleaned<br />

Y N<br />

Façade<br />

Material properly lifted from packet to site<br />

Y N<br />

Material without bubles and undulations<br />

Y N<br />

Fixations are enough and well positioned<br />

Y N<br />

Drip and façade are properly leveled and aligned<br />

Y N<br />

Doors, Windows and holes properly done and flashings installed<br />

Y N<br />

Overlaps or vertical joints properly installed and sealed<br />

Y N<br />

Drip is properly aligned<br />

Y N<br />

Corners are properly aligned<br />

Y N<br />

Windows are properly aligned<br />

Y N<br />

Flashings properly designed<br />

Y N<br />

Flashings properly sealed and fixed<br />

Y N<br />

Drip flashing doesn't have any dent<br />

Y N<br />

Safety<br />

Installers have finished the safety training<br />

Y N<br />

Safety speach has been done to the installers<br />

Y N<br />

Collective safety measures are installed<br />

Access to the roof is safe<br />

Y N<br />

Electricity wires are at the right distance and properly insulated<br />

Y N<br />

Electrical box containers have a "gadget that cut the electricity if contact with metal" Y N<br />

Installers have the right tools for the installation<br />

Y N<br />

Material packets are properly placed and/or fixed<br />

Y N<br />

Scaffolding and platforms are safe<br />

Y N<br />

The ground permits the movement of the platforms<br />

Y N<br />

The roof holes are protected aganist fallings<br />

Y N<br />

Working area is properly indicated<br />

Y N<br />

Installers have the individual safety elements<br />

Y N<br />

New installer in the work site has been trained in safety<br />

Y N<br />

Components installation<br />

The insulation is properly installed according with the system description<br />

Y N<br />

The spacers are properly installed and fixed<br />

Y N<br />

Vapour barrier is installed properly<br />

Y N<br />

Are there thermal bridges visibles<br />

Y N<br />

I.2. Cutting list templates<br />

ArcelorMittal Construction Page 17 of 21<br />

Javier Cirauqui


Panels cutting list<br />

Customer<br />

Work reference<br />

Location<br />

Delivery address<br />

Number of order<br />

Date<br />

Number of<br />

position<br />

Product<br />

Core<br />

Panel<br />

thickness<br />

Number of<br />

units<br />

Lenght<br />

External face<br />

Internal face<br />

Steel thick Coating Colour Steel thick. Coating Colour Layout drawing position<br />

Signature<br />

Stamp<br />

ArcelorMittal Construction Page 18 of 21<br />

Javier Cirauqui


Flashings cutting list<br />

Customer<br />

Work reference<br />

Location<br />

Delivery address<br />

Number of order<br />

Date<br />

Flashing name<br />

Number of pieces<br />

Lenght piece<br />

Number overlap pieces<br />

Coating<br />

Colour<br />

Steel thickness<br />

Layout drawing position<br />

Flashing name<br />

Number of pieces<br />

Lenght piece<br />

Number overlap pieces<br />

Coating<br />

Colour<br />

Steel thickness<br />

Layout drawing position<br />

Flashing name<br />

Number of pieces<br />

Lenght piece<br />

Number overlap pieces<br />

Coating<br />

Colour<br />

Steel thickness<br />

Layout drawing position<br />

Signature<br />

Stamp<br />

Flashing name<br />

Number of pieces<br />

Lenght piece<br />

Number overlap pieces<br />

Coating<br />

Colour<br />

Steel thickness<br />

Layout drawing position<br />

ArcelorMittal Construction Page 19 of 21<br />

Javier Cirauqui


I.3. Curved cutting list templates<br />

Curved steel profiled sheets cutting list<br />

Customer<br />

Work reference<br />

Location<br />

Delivery address<br />

Number of order<br />

Date<br />

Internal face<br />

Number of<br />

position<br />

Product<br />

Thickness<br />

Number of<br />

units<br />

Internal<br />

Radius<br />

Angle<br />

External face<br />

(to be filled if different of back coating)<br />

Coating Colour Coating Colour Layout drawing position<br />

Signature<br />

Stamp<br />

ArcelorMittal Construction Page 20 of 21<br />

Javier Cirauqui


II. <strong>Installation</strong> ratios<br />

<strong>Installation</strong> ratios are given in hours per man and square meter.<br />

In general, we can consider that installation must be done by teams and every<br />

team is composed by three members: two handling and fixing and the third one<br />

preparing the material at the position.<br />

Element<br />

Rate<br />

(Hours / (man · m 2 )<br />

Panel 0.08 hours / (man · m 2 )<br />

Flashings 0.2 hours / (man · m)<br />

ArcelorMittal Construction Page 21 of 21<br />