11.2.2 Non-Structural Practices<br />

This section describes the planning and implementation of the required non-structural BMPs<br />

to minimize erosion and off-site sedimentation.<br />

These BMPs include:<br />

floodplain avoidance<br />

stream buffer zones<br />

reduced exposure time<br />

limits on maximum disturbed area<br />

embankment slope minimization<br />

<strong>Flood</strong>plain Avoidance<br />

No construction or grading activities are permitted in the post-development floodplains, as<br />

defined in Chapter 1 of this manual, except for road and utility crossings and permanent<br />

stormwater management facilities. Therefore, only erosion and sediment control practices<br />

related to allowable construction activities shall be permitted in the post-development<br />

floodplain. Temporary sediment control in a permanent pond shall be allowed in the postdevelopment<br />

floodplain but not in a stream.<br />

Vegetative Buffer Strips<br />

Buffer strips are required adjacent to all streams and wetlands in Fayette <strong>County</strong>. The buffer<br />

strip width shall be 25 feet from the top of each bank and from the edge of a wetland. No<br />

grading or land clearing is allowed within the buffer zone, and native vegetation must be<br />

preserved.<br />

Reduced Exposure Time<br />

All on-site measures required by the Erosion and Sediment <strong>Control</strong> Plan shall be made<br />

functional before other land disturbance takes place. Permanent or temporary soil<br />

stabilization, as described under structural practices, shall be applied to disturbed or<br />

constructed areas within 14 days after final grade is reached. Soil stabilization shall also be<br />

applied to all disturbed areas not at final grade, including soil stockpiles, dams, dikes, and<br />

diversions, which have been inactive for 14 days.<br />

Limits on Maximum Disturbed Area<br />

The maximum area that may be disturbed at any time during construction, without soil<br />

stabilization, is 25 acres. For sites over 25 acres in size, additional land can be disturbed only<br />

when an equal amount of land is stabilized. A construction site shall not be broken into<br />

individual permits to avoid this requirement.<br />

Embankment Slope Minimization<br />

Steep embankment slopes present increased opportunities for erosion and sediment<br />

production due to high runoff velocities. To minimize adverse effects of steep embankment<br />

slopes, constructed fill slopes and cut slopes shall not be steeper than 3H:1V. For slopes of<br />

4H:1V or steeper with slope lengths of greater than 100 feet, temporary diversion ditches shall<br />

be constructed at the top of the slope and every 100 feet horizontally down the slope.<br />

STORMWATER MANUAL 11-5 August 29, 2011<br />