29.03.2015 Views

Project Hurunui Wind Construction and Project Overview

Project Hurunui Wind Construction and Project Overview

Project Hurunui Wind Construction and Project Overview

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

Meridian Energy Ltd<br />

<strong>Project</strong> <strong>Hurunui</strong> <strong>Wind</strong><br />

<strong>Construction</strong> <strong>and</strong> <strong>Project</strong> <strong>Overview</strong><br />

<strong>Construction</strong> Effects & Management Report<br />

February 2011


Meridian Energy Ltd<br />

<strong>Project</strong> <strong>Hurunui</strong> <strong>Wind</strong><br />

<strong>Construction</strong> <strong>and</strong> <strong>Project</strong> <strong>Overview</strong><br />

<strong>Construction</strong> Effects & Management Report<br />

February 2011<br />

Prepared By<br />

Len Wiles<br />

<strong>Project</strong> Engineer<br />

Opus International Consultants Limited<br />

Wellington Office<br />

Level 9, Majestic Centre, 100 Willis Street<br />

PO Box 12 003, Wellington 6144,<br />

New Zeal<strong>and</strong><br />

Reviewed By Telephone: +64 4 471 7000<br />

Gareth McKay Facsimile: +64 4 471 1397<br />

<strong>Project</strong> Manager<br />

Date: 14 Feb 2011<br />

Reference: 5C-1604.02<br />

Status: Final<br />

© Opus International Consultants Limited 2011


<strong>Project</strong> <strong>Hurunui</strong> <strong>Wind</strong> <strong>Construction</strong> Effects <strong>and</strong> Management Report<br />

Contents<br />

1 Introduction .......................................................................................................................... 1<br />

2 Access Route, Turbine <strong>and</strong> Fill Site Selection ................................................................... 4<br />

2.1 Preliminary Design Criteria ........................................................................................... 4<br />

2.2 Geotechnical Appraisal ................................................................................................. 7<br />

2.3 Core Site Access Route & Turbine Site Selection ......................................................... 7<br />

2.4 Spoil Fill Site Selection ................................................................................................. 9<br />

2.5 Assessment of Effects & General Consultation ........................................................... 10<br />

2.6 Implementation Team Review ..................................................................................... 11<br />

2.7 Access Options ........................................................................................................... 12<br />

3 Core Site <strong>Construction</strong> Works .......................................................................................... 16<br />

3.1 <strong>Overview</strong> <strong>and</strong> Site Description .................................................................................... 16<br />

3.1.1 General Approach ....................................................................................................... 16<br />

3.2 L<strong>and</strong> Disturbance ........................................................................................................ 16<br />

3.2.1 Detailed Description of Core Site Access Roads ......................................................... 17<br />

3.2.2 Access Road Formation .............................................................................................. 21<br />

3.2.3 Turbine Platforms ....................................................................................................... 26<br />

3.2.5 Spoil Fill Sites ............................................................................................................. 29<br />

3.2.6 Concrete Works .......................................................................................................... 31<br />

3.2.7 Borrow Areas .............................................................................................................. 32<br />

3.2.8 Soil Stockpile Areas .................................................................................................... 33<br />

3.2.9 Site Lay Down Areas .................................................................................................. 34<br />

3.2.10 Internal Cable Reticulation ................................................................................... 34<br />

3.2.11 Substation ............................................................................................................ 35<br />

3.2.12 66 kV Transmission Line Connection ................................................................... 36<br />

3.2.13 Services Building .................................................................................................. 36<br />

3.2.14 Meteorological Masts (<strong>Wind</strong> Monitoring Towers) .................................................. 37<br />

3.3 Discharges .................................................................................................................. 40<br />

3.3.1 Erosion, Sediment <strong>and</strong> Dust Control ........................................................................... 40<br />

3.3.2 Permanent Stormwater Run-off .................................................................................. 43<br />

3.3.3 New Culverts at Stream or Gully Crossings in the Core Site ....................................... 44<br />

3.3.4 Upgrading Existing Culverts Along Motunau Beach Road ........................................... 45<br />

3.3.5 Culvert <strong>Construction</strong> Methodology .............................................................................. 45<br />

4 Minor Shoulder Widening At Motunau Beach Road ........................................................ 45<br />

4.1 Shoulder Road Widening Opposite Site Entrance ....................................................... 45<br />

5 Geotechnical Assessment ................................................................................................ 46<br />

5.1 Geotechnical Appraisal ............................................................................................... 46<br />

5.2 Geotechnical Risk ....................................................................................................... 46<br />

5.2.1 Potential Slope Instability ............................................................................................ 46<br />

5.2.2 Seismic Hazard........................................................................................................... 47<br />

5C-1604.02<br />

February 2011<br />

i


<strong>Project</strong> <strong>Hurunui</strong> <strong>Wind</strong> <strong>Construction</strong> Effects <strong>and</strong> Management Report<br />

6 Other Proposed Activities ................................................................................................. 49<br />

6.1 Detailed Geotechnical Investigations .......................................................................... 49<br />

6.2 Controlled Blasting ...................................................................................................... 49<br />

7 Indicative <strong>Construction</strong> Methodology, Noise <strong>and</strong> Lighting............................................. 49<br />

7.1 Indicative <strong>Construction</strong> Methodology .......................................................................... 49<br />

7.2 <strong>Construction</strong> Noise ..................................................................................................... 51<br />

7.3 Lighting <strong>and</strong> Night Works ............................................................................................ 51<br />

7.4 On Site <strong>Project</strong> Office ................................................................................................. 52<br />

7.5 Bulk Fuel Storage Facility ........................................................................................... 52<br />

7.6 On Site Batching Plant ................................................................................................ 52<br />

8 Summary <strong>and</strong> Conclusions ............................................................................................... 53<br />

Appendix A –<br />

Appendix B –<br />

Appendix C –<br />

Appendix D –<br />

Appendix E –<br />

Appendix F –<br />

Drawing Plans<br />

A.1 – Overall Site Development Plans<br />

A.2 – Access Road Plans & Cross Sections<br />

A.3 – L<strong>and</strong>owner Boundary Plan<br />

A.4 – Culvert Location Plans & Typical Details<br />

A.5 – Typical Turbine Platform & External Turbine Transformer Details<br />

A.6 – Hydrological Catchment Area Plan<br />

A.7 – Substation, Underground Cabling & Transmission Line Details<br />

A.8 – Indicative Site Office & Lay-down Area Plan<br />

A.9 – Indicative <strong>Wind</strong> Monitoring Mast Details<br />

Site Photographs<br />

Typical Transport Details<br />

Preliminary Geotechnical Appraisal<br />

Environmental Management Plan<br />

Photographs Illustrating Representative <strong>Construction</strong> Requirements<br />

<strong>and</strong> Effects<br />

5C-1604.02<br />

February 2011<br />

ii


<strong>Project</strong> <strong>Hurunui</strong> <strong>Wind</strong> <strong>Construction</strong> Effects <strong>and</strong> Management Report<br />

1 Introduction<br />

Meridian Energy Ltd (Meridian) proposes to develop, build <strong>and</strong> operate a wind farm 66km<br />

north of Christchurch as shown on the site location plan on Drawing Sheet 200 in Appendix<br />

A (Appendix A.1 – Overall Site Development Plans). The proposed core site comprises five<br />

properties, identified on Drawing Sheet 5 in Appendix A (Appendix A.3 – L<strong>and</strong>owner<br />

Boundary Plan), covering approximately 34km 2 <strong>and</strong> is bounded by:<br />

• Reeces Road to the southwest.<br />

• Motunau Beach Road to the northeast.<br />

• State Highway 1 to the west.<br />

The core site measures approximately 6km <strong>and</strong> 5km at its longest <strong>and</strong> widest points<br />

respectively. The core site is approximately 30km south of Cheviot <strong>and</strong> approximately 34km<br />

north of Amberley. The preferred access to the core site is from Motunau Beach Road off<br />

State Highway 1.<br />

The core site is primarily located along two main ridgelines running in a north-east to south<br />

west direction with some short minor spurs running from the main ridgelines. Both of the<br />

main ridgelines are typically characterised by sections of eastern facing escarpments. The<br />

majority of the site is relatively steep undulating countryside interspaced with numerous<br />

valleys <strong>and</strong> ridges. The overall site is farm l<strong>and</strong> mainly covered in pasture with some<br />

occasional tussock at higher altitudes <strong>and</strong> scrub <strong>and</strong> shrubl<strong>and</strong> vegetation in some of<br />

the gullies. The ridgelines lie between 300m <strong>and</strong> 550m above sea level. Soil depths within<br />

the area vary typically between 0.5m <strong>and</strong> 1.0m in thickness, overlying the greywacke<br />

bedrock. Exposures of naturally occurring bedrock are generally slightly to moderately<br />

weathered. Road cuts have exposed some areas of moderately to highly weathered<br />

bedrock. Rock outcrops can be found scattered throughout the site.<br />

The core site is predominantly covered with pasture, <strong>and</strong> is used for farming. In addition to<br />

tracks (typically 2m to 3m in width), <strong>and</strong> stock fences that have been established by the<br />

l<strong>and</strong>owners, a water mains network owned by the <strong>Hurunui</strong> District Council runs through the<br />

project area.<br />

The proposed <strong>Project</strong> <strong>Hurunui</strong> <strong>Wind</strong> will consist of thirty three (33) wind turbine generators<br />

(WTGs) located within the site. The turbines being considered for this site have a<br />

generation capacity of 2.3MW each <strong>and</strong> a rotor diameter of 101m. The maximum height of<br />

each turbine to the tip of a rotor blade when vertical will be approximately 130.5m.<br />

Each turbine will typically consist of the following components as illustrated in Figure 1<br />

below:<br />

• Foundation, typically completely buried.<br />

• Tapered tubular steel tower.<br />

5C-1604.02<br />

February 2011 1


<strong>Project</strong> <strong>Hurunui</strong> <strong>Wind</strong> <strong>Construction</strong> Effects <strong>and</strong> Management Report<br />

• Nacelle which sits on top of the tower <strong>and</strong> houses the control gear, generator <strong>and</strong><br />

the main rotor shaft that transmits the rotating energy from the turbine rotor to the<br />

main gearbox.<br />

• 3 bladed turbine rotor.<br />

• External turbine transformer unit at ground level adjacent to the turbine tower (refer<br />

Drawing Sheet 100 in Appendix A (Appendix A.5 Typical Turbine Platform &<br />

External Turbine Transformer Details) for details.<br />

Figure 1 below illustrates the various components of a typical wind turbine generator.<br />

Figure 1: Typical <strong>Wind</strong> Turbine Generator (<strong>Project</strong> West <strong>Wind</strong> Example)<br />

<strong>Construction</strong> of an internal core site road network of approximately 22.2km will be required<br />

in order to construct <strong>and</strong> service the WTGs. In addition minor access tracks will be required<br />

to construct the transmission towers supporting the transmission line between the site<br />

substation <strong>and</strong> external 66kV transmission line. Existing farm tracks are to be upgraded<br />

wherever possible to reduce the net earthworks required to form core site access roads<br />

thereby minimising the overall impact of earthworks. Upgraded roads, farm tracks <strong>and</strong> new<br />

access roads are expected to range in widths from approximately 6m wide, in the majority<br />

5C-1604.02<br />

February 2011 2


<strong>Project</strong> <strong>Hurunui</strong> <strong>Wind</strong> <strong>Construction</strong> Effects <strong>and</strong> Management Report<br />

of cases, to a maximum of 10m at tight bends. In order to reduce construction effects<br />

access road widths will be kept to a practical minimum.<br />

At each turbine, a flat platform will be formed to provide a cranage area as well as to<br />

contain the turbine foundation. Excavated material from these earthworks would be used<br />

as roading fill, if suitable, while any excess material would be disposed of at appropriate<br />

locations across the core site. Conversely, where there is a shortfall of materials for access<br />

road construction, borrow areas will be established at suitable locations.<br />

Other facilities required in addition to the turbines include:<br />

• Temporary lay down areas during construction.<br />

• Temporary concrete batching plant.<br />

• Temporary erosion <strong>and</strong> sediment control measures.<br />

• Temporary offices, workshops, stores <strong>and</strong> staff facilities.<br />

• Electricity substation.<br />

• Temporary mobile crushing plant.<br />

• An underground transmission & fibre optic communication network between the<br />

turbines <strong>and</strong> substation.<br />

• Overhead transmission between the substation <strong>and</strong> the external transmission<br />

network.<br />

• A maintenance <strong>and</strong> operations building.<br />

• Two Meteorological masts (wind monitoring towers).<br />

In general, power from the site will be fed into the local Main Power 66kV Line which runs<br />

parallel to State Highway 1 from the south before following Burrows Road. An internal wind<br />

farm 33kV or 22kV network will be constructed to channel power generated by the WTGs to<br />

the substation. The internal network will generally be underground, typically following the<br />

access roads. One overhead circuit will be incorporated within the internal transmission<br />

network to span a gully between the substation near Road D <strong>and</strong> Road A as an<br />

underground route is impractical due to significant construction requirements.<br />

This <strong>Construction</strong> Effects <strong>and</strong> Management Report has been prepared to support the<br />

application for resource consent. It deals specifically with the civil <strong>and</strong> access road work<br />

required to construct the wind farm, together with the expected management measures that<br />

will be undertaken during construction <strong>and</strong> site rehabilitation. Transport of oversized <strong>and</strong><br />

overweight turbine components from the Port of Timaru to the site together with any effects<br />

on public roads are addressed in a separate Traffic Impact Assessment report.<br />

Drawing Sheets 1 <strong>and</strong> 2 in Appendix A (Appendix A.1 Overall Site Development Plans)<br />

illustrates the proposed site location <strong>and</strong> layout.<br />

5C-1604.02<br />

February 2011 3


<strong>Project</strong> <strong>Hurunui</strong> <strong>Wind</strong> <strong>Construction</strong> Effects <strong>and</strong> Management Report<br />

2 Access Route, Turbine <strong>and</strong> Fill Site Selection<br />

2.1 Preliminary Design Criteria<br />

Preliminary design criteria for road access to turbine sites <strong>and</strong> the turbine platforms are<br />

governed by:<br />

1. The movement of equipment <strong>and</strong> materials that are necessary for installing WTGs.<br />

2. The size <strong>and</strong> weight of the tower sections, blades <strong>and</strong> nacelle units.<br />

3. The mobility of the main erection crane along access roads <strong>and</strong> at the turbine<br />

platform.<br />

Equipment sizes <strong>and</strong> transport needs were discussed with potential turbine manufacturers,<br />

haulage companies <strong>and</strong> cranage service providers to derive preliminary design criteria for<br />

the access roads. Meridian has gained significant experience from the construction of<br />

<strong>Project</strong> Te Apiti (completed in 2004), <strong>Project</strong> White Hill (completed in 2007), <strong>Project</strong> West<br />

<strong>Wind</strong> (completed in 2009) <strong>and</strong> Te Uku (currently under construction). This experience has<br />

also contributed to deriving the preliminary design criteria. Typical characteristics of these<br />

plant items <strong>and</strong> indicative access road/platform requirements are described as follows:<br />

(a) Tubular tower sections <strong>and</strong> blades<br />

Based on data provided by New Zeal<strong>and</strong> haulage companies <strong>and</strong> experience from similar<br />

wind farm projects (<strong>Project</strong> Te Apiti, White Hill <strong>and</strong> West <strong>Wind</strong>), a minimum internal<br />

horizontal radius of 30m has been adopted for preliminary design purposes. A road width of<br />

up to 10m has been provided at such minimum curves.<br />

On a straight section of road, a minimum road/running surface of approximately 6m will be<br />

adopted to accommodate transporters hauling the tower sections <strong>and</strong> to ensure the safe<br />

passing of other vehicles <strong>and</strong> the main erection crane as described below. This minimum<br />

road width is adequate where the internal horizontal radius of the access road is greater<br />

than approximately 55m. The main access road from the public road network to the core<br />

site will be approximately 7m wide as it will be more trafficked than the internal core roads.<br />

In addition to providing an adequate road surface width, clearance beyond the edge of the<br />

road surface needs to be provided for the sweep of the overhanging blade where the road<br />

is on a curve. In general, if the internal horizontal radius of the road is less than 175m, the<br />

clearance required is examined on a case by case basis considering the following factors:<br />

• Road width.<br />

• Angle of departure.<br />

• Final trailer configuration.<br />

• Selected turbine type.<br />

• Height of blade above ground when transported.<br />

5C-1604.02<br />

February 2011 4


<strong>Project</strong> <strong>Hurunui</strong> <strong>Wind</strong> <strong>Construction</strong> Effects <strong>and</strong> Management Report<br />

Currently a minimum vertical curve radius of 200m has been adopted based on the ground<br />

clearance of a multi-axle platform trailer with 0.5m wheel articulation. It is recognised that<br />

this may be further reduced if the final trailer configuration permits.<br />

Where access road grades exceed 12.5%, we envisage that haulage of the heavier turbine<br />

components, such as tower sections <strong>and</strong> nacelles, may require additional tractor units,<br />

dozers, or assistance by winching. An upper bound gradient of 15% has generally been<br />

adopted. Steeper gradients may be applied at straight or broad sweeping sections if<br />

unavoidable, subject to a maximum limit of 20%. At tighter horizontal curves, the gradient<br />

has generally been limited to less than 12.5%.<br />

Appendix C illustrates typical tower <strong>and</strong> blade transport configurations. Actual transport<br />

configurations will depend on the selected turbine.<br />

(b) Nacelle units<br />

Depending on the turbine, nacelle units typically weigh 90 tonnes (which typically includes<br />

an 8 tonne transport frame). Typical road transportation details/schematics (provided by<br />

turbine manufacturers) are attached in Appendix C. An example of an off-road<br />

configuration is also illustrated.<br />

The minimum geometric criteria for transport of the nacelle units around the site are within<br />

the parameters assessed for the blade <strong>and</strong> tower sections.<br />

(c) Main erection crane<br />

An erection crane capable of lifting the tower sections, nacelle unit <strong>and</strong> rotors to the top of<br />

the towers (typically 80m) will need to access each turbine site. The erection crane<br />

proposed for this project may have a crane track width of up to approximately 5m. A<br />

photograph of a typical crane is shown on Photograph F1 in Appendix F.<br />

An access road width of approximately 6m is expected to accommodate the main erection<br />

crane based on its operational requirements. This width has been assumed for all roads<br />

within the core site although further detailed design may reduce this width down to 4.5m<br />

towards the end of roads <strong>and</strong> along spur roads depending on the final crane configuration.<br />

Based on feedback from cranage service providers, a maximum access road grade of 17%<br />

(5.7H:1V or 10 o ) is considered negotiable by a crawler crane that is unloaded with the boom<br />

up. The crane can also negotiate road grades in excess of 17% by removing the crane’s<br />

boom which may be required along a limited number of road sections.<br />

(d) Turbine platform at turbine locations<br />

The turbine platform at each turbine location is an integral part of the road access. The<br />

turbine platform merges with the road access to enable transporters to deliver turbine<br />

components <strong>and</strong> provide a working platform to both construct the turbine foundation <strong>and</strong><br />

erect the turbine components. Turbine platforms <strong>and</strong> the access roads are constructed at<br />

the same time <strong>and</strong> therefore the preliminary design criteria for both are considered<br />

together.<br />

Based on experience gained at <strong>Project</strong> Te Apiti, <strong>Project</strong> White Hill <strong>and</strong> <strong>Project</strong> West <strong>Wind</strong><br />

together with feedback from turbine manufacturers <strong>and</strong> cranage service providers, a<br />

5C-1604.02<br />

February 2011 5


<strong>Project</strong> <strong>Hurunui</strong> <strong>Wind</strong> <strong>Construction</strong> Effects <strong>and</strong> Management Report<br />

minimum platform size of between 40m x 20m <strong>and</strong> 50m x 35m will be required for turbines<br />

depending on the specific crane selected <strong>and</strong> ridge positions.<br />

Examples of typical foundation working platforms at <strong>Project</strong> White Hill <strong>and</strong> <strong>Project</strong> West<br />

<strong>Wind</strong>, during the turbine component erection phase are shown on Photographs F2 to F6 in<br />

Appendix F.<br />

The proposed approach for rotor assembly is to fit the hub followed by the rotor blades one<br />

blade at a time. An alternative option, also known as the single lift approach, is to assemble<br />

the rotor <strong>and</strong> hub on the ground before lifting the assembly as one unit onto the turbine.<br />

The turbine platforms have been sized based on the proposed approach as the platform<br />

area can be reduced which is beneficial given the site’s hilly terrain.<br />

Photograph F7 <strong>and</strong> F8, from <strong>Project</strong> White Hill <strong>and</strong> <strong>Project</strong> West <strong>Wind</strong> respectively, in<br />

Appendix F illustrate the blades being lifted <strong>and</strong> assembled on to the turbine one at a time.<br />

Based on the above requirements, the parameters outlined in Table 1 have been adopted<br />

for preliminary design.<br />

5C-1604.02<br />

February 2011 6


<strong>Project</strong> <strong>Hurunui</strong> <strong>Wind</strong> <strong>Construction</strong> Effects <strong>and</strong> Management Report<br />

Design Aspect<br />

Main <strong>Construction</strong> Access<br />

Road To Turbine A11<br />

Internal <strong>Construction</strong><br />

Access Roads (traversable<br />

by crawler crane)<br />

Maintenance road (postconstruction)<br />

Preliminary Criteria Adopted<br />

Approximately 7m wide with a 1.0m drainage channel.<br />

Drainage channel to be provided on both sides in box<br />

cuts.<br />

Localised widening to approximately 10m at internal<br />

radii approaching 30m.<br />

Approximately 6m wide with a 1.0m drainage channel.<br />

Drainage channel to be provided on both sides in box<br />

cuts.<br />

Similar to construction access.<br />

Pavement maintenance to 5m central strip only.<br />

Gradient Preferred < 5%<br />

Normal


<strong>Project</strong> <strong>Hurunui</strong> <strong>Wind</strong> <strong>Construction</strong> Effects <strong>and</strong> Management Report<br />

All planning <strong>and</strong> wind modelling studies leading to this final layout have focused on<br />

achieving the maximum number of technically feasible turbine sites on the ridges based on<br />

the design criteria, l<strong>and</strong>owner consent <strong>and</strong> site geology. The design process adopted to<br />

develop the feasibility layout is described below.<br />

(a) <strong>Wind</strong> Model<br />

Meridian developed initial turbine positions based on minimum turbine separation of<br />

approximately 5 rotor diameters <strong>and</strong> 4 rotor diameters to the prevailing upwind <strong>and</strong><br />

crosswind direction respectively. This clearance is necessary to avoid turbulence effects<br />

<strong>and</strong> ensure a smooth laminar air flow. When combined with the terrain/layout of the ridges,<br />

this separation requirement places a constraint on turbine placement.<br />

(b) Desktop Review<br />

Initial turbine positions were reviewed against aerial photographs <strong>and</strong> 5m contour data<br />

which were obtained specifically for the site. The primary focus of this desktop review was<br />

to identify terrain constraints <strong>and</strong> potential encumbrances (survey trigs, transmission line,<br />

etc) to the proposed turbine positions in view of the preliminary design criteria for access<br />

roads <strong>and</strong> turbine platforms summarised in Table 1. Turbines which appeared to be<br />

physically located on or near steep slopes, gullies, local depressions, watercourses, or<br />

other potentially unfavourable terrain were noted prior to the micrositing phase which is<br />

described below.<br />

Other criteria <strong>and</strong> key aspects considered in developing the turbine <strong>and</strong> access road layout<br />

included:<br />

• Where possible, access routes were chosen to follow existing tracks, disturbed<br />

areas such as fence lines, contours <strong>and</strong> ridgelines to reduce environmental effects<br />

<strong>and</strong> to minimise the earthwork footprint.<br />

• Generally a cut-to-fill approach was adopted where practicable. On steeper terrain,<br />

a cut-to-waste approach was adopted given the difficulty of fill containment on<br />

steeper slopes.<br />

• Taking into account or avoiding where possible:<br />

<br />

<br />

<br />

<br />

<br />

<br />

Existing trigonometric stations.<br />

Large rock outcrops/formations or other significant natural features.<br />

Undisturbed watercourses.<br />

Damp or boggy areas.<br />

Areas of high ecological value.<br />

Steep slopes which are typically slopes > 28 o (refer Figure 4 – Site Slope<br />

Analysis Plan in Appendix D).<br />

• Any l<strong>and</strong>owner requirements.<br />

(c) Micrositing<br />

Micrositing involved both Opus <strong>and</strong> Meridian locating each turbine position in the field to<br />

confirm access <strong>and</strong> turbine platform feasibility. Turbines were located in the field using a<br />

5C-1604.02<br />

February 2011 8


<strong>Project</strong> <strong>Hurunui</strong> <strong>Wind</strong> <strong>Construction</strong> Effects <strong>and</strong> Management Report<br />

h<strong>and</strong> held GPS receiver with an accuracy of +/- 6 to 12m. Turbines located in unfavourable<br />

positions as described above were moved to a more suitable position within the constraints<br />

of optimal wind generation. Turbines which were repositioned following micrositing are<br />

described below:<br />

• Turbine E1 was relocated approximately 20m away from a prominent rocky outcrop<br />

(Refer Photograph 12 in Appendix B).<br />

• Turbine A4 was relocated approximately 20m to the west to reduce excavation <strong>and</strong><br />

ensure the turbine platform was integrated with Road A as indicated on Photograph<br />

17 in Appendix B.<br />

(d) Access Tracks<br />

Following the site-based micrositing exercise, sections of the road that were on particularly<br />

complex terrain were modelled to confirm feasibility. Earthworks quantities were<br />

subsequently derived using the following approach:<br />

• All sections of road were modelled using MXRoad (computer-aided three<br />

dimensional road design package) to derive preliminary longitudinal alignments <strong>and</strong><br />

cross sections. For sidling cuts in steeper terrain, a cut to waste philosophy was<br />

generally adopted with cross sections examined for areas of unacceptable cut or fill.<br />

At areas of unacceptable cut or fill minor refinements to the preliminary longitudinal<br />

alignments <strong>and</strong> cross sections were made to ensure these areas remained within<br />

acceptable limits.<br />

• All earthworks have been estimated using MXRoad generally using a cut-to-waste<br />

approach including areas of gentler terrain to give an upperbound earthworks<br />

quantity <strong>and</strong> dem<strong>and</strong> on fill site capacity. Fill embankments have been adopted only<br />

along sections of the route where longitudinal gradient <strong>and</strong> vertical curvature<br />

requirements (refer Table 1 Preliminary Design Criteria) could not be met. However<br />

during detailed design a cut-to-fill approach is envisaged which would result in a<br />

reduction of cut-to-waste earthworks.<br />

Drawing Sheets 11 to 14 in Appendix A (Appendix A.2 Access Road Plans & Cross<br />

Sections) illustrate the proposed turbine locations <strong>and</strong> derived access road layout from<br />

MXRoad. Roads indicated in the drawings have been identified alphabetically, while<br />

turbines are referenced to the road on which they are located. The final access layout <strong>and</strong><br />

position of the turbines will be confirmed following a site survey, detailed design <strong>and</strong> the<br />

geotechnical/foundation conditions as encountered at each site.<br />

Approximately 22% of the proposed access roads will comprise upgraded existing tracks<br />

(with some localised corner smoothing <strong>and</strong> widening to approximately 10m).<br />

2.4 Spoil Fill Site Selection<br />

Selecting fill sites for excess excavated material will be generally driven by the following<br />

criteria:<br />

1. Environmental- Sites suitable as fill sites include:<br />

5C-1604.02<br />

February 2011 9


<strong>Project</strong> <strong>Hurunui</strong> <strong>Wind</strong> <strong>Construction</strong> Effects <strong>and</strong> Management Report<br />

• Local shallow depressions or the tops <strong>and</strong> upper reaches of natural dry gullies with<br />

good containment are favoured for compaction, aesthetics, rehabilitation <strong>and</strong> to<br />

reduce the risk of erosion <strong>and</strong> damming of natural drainage paths.<br />

• Well drained, broad <strong>and</strong> gentle terrain is also suitable to ensure minimal impact to<br />

natural flow paths. Fill material can be shaped to reinstate natural flow paths or to<br />

create alternative drainage paths as well as blend into the terrain.<br />

Sites not suitable as fill sites are:<br />

• Boggy or wet areas.<br />

• Gullies or valleys with perennial watercourses.<br />

• Steeper areas where fill cannot be contained in particular slopes.<br />

• Areas of high ecological value.<br />

2. Haul Length - The haul length to <strong>and</strong> from fill sites needs to be minimised wherever<br />

possible to maximise efficiency <strong>and</strong> to minimise plant traffic.<br />

3. Geotechnical – Avoid obvious areas of seepage <strong>and</strong> soft, steep or unstable areas.<br />

Several potential fill sites, near turbine positions <strong>and</strong> along proposed access roads, have<br />

been identified within the site to accommodate the projected volume of earthworks. These<br />

have been identified by desk top study <strong>and</strong> site visits. Photographs 50 to 58 in Appendix B<br />

illustrate some of these potential fill sites.<br />

The extent <strong>and</strong> final position of each fill site will be determined during the detailed design<br />

phase <strong>and</strong> will be based on the criteria outlined above <strong>and</strong> the proposed construction<br />

methodology. Refinement of fill site layouts will take place under the framework of the<br />

Environmental Management Plan (EMP) for the site which is outlined in Appendix E.<br />

As part of the process for selecting final fill sites, the design/construction team will discuss<br />

the location, size <strong>and</strong> depth of potential fill sites with respective l<strong>and</strong>owners, relevant<br />

stakeholders (Councils or other) <strong>and</strong> the project environmental team to incorporate their<br />

requirements. The fill site selection strategy will involve selecting sites of limited size to<br />

control the area of disturbance <strong>and</strong> control later re-generation. The site selection strategy<br />

will also consider visual effects by aiming to keep fill areas “internal” to the site so that they<br />

are obscured from external view as far as possible.<br />

2.5 Assessment of Effects & General Consultation<br />

During the development of the preliminary engineering plans, the proposed wind farm<br />

layout was discussed amongst Meridian's assessment of environmental effects (AEE) team<br />

comprising transmission, ecological, noise, planning, traffic, l<strong>and</strong>scape, cultural <strong>and</strong><br />

archaeological specialists.<br />

5C-1604.02<br />

February 2011 10


<strong>Project</strong> <strong>Hurunui</strong> <strong>Wind</strong> <strong>Construction</strong> Effects <strong>and</strong> Management Report<br />

The AEE team also met on site to discuss the project layout. A key outcome of the process<br />

was the endorsement of the identified turbine sites <strong>and</strong> road alignments by the assessment<br />

team, in particular:<br />

• Identification <strong>and</strong> the accurate location of any archaeological, cultural <strong>and</strong> ecological<br />

sites of significance.<br />

• Identifying preferred main access routes <strong>and</strong> turbine locations (if necessary) to avoid<br />

environmentally, culturally <strong>and</strong> archaeologically sensitive areas.<br />

• Criteria for fill site (<strong>and</strong> borrow area) selection: Avoiding (as identified in Ecological<br />

Values <strong>and</strong> Assessment of Effects report prepared by Boffa Miskell):<br />

<br />

<br />

Covenanted areas such as the recently covenanted QEII l<strong>and</strong> within the<br />

Turnbull property.<br />

A totara forest remnant within the Batchelor property.<br />

• Avoiding where possible (as identified in Ecological Values <strong>and</strong> Assessment of Effects<br />

report prepared by Boffa Miskell):<br />

<br />

<br />

Areas of higher ecological value.<br />

2.6 Implementation Team Review<br />

Areas for fill sites <strong>and</strong> construction works within the Motunau <strong>and</strong> Cave<br />

hydrological catchment areas by locating these areas in neighbouring<br />

northern catchments. This is because the northern catchment areas have<br />

been assessed as having less sensitive receiving environments than the<br />

Motunau <strong>and</strong> Cave receiving environments. This is generally feasible where<br />

these construction areas straddle both catchments.<br />

Meridian’s project construction implementation team completed a site visit on 15 April 2009<br />

<strong>and</strong> 30 July 2009 to provide input <strong>and</strong> feedback on the proposed layout based on<br />

experience from other Meridian wind farm projects including <strong>Project</strong> Te Apiti, <strong>Project</strong> White<br />

Hill <strong>and</strong> <strong>Project</strong> West <strong>Wind</strong>.<br />

Input from this process contributed to:<br />

• Refining the layout of access roads <strong>and</strong> turbine positions.<br />

• Updating construction timeframes <strong>and</strong> construction sequencing (discussed in Section<br />

6).<br />

• Refining the lay down area strategy <strong>and</strong> selection.<br />

• Identifying a potential site office area <strong>and</strong> lay down areas.<br />

• Identifying potential substation area.<br />

• Identifying internal transmission route options.<br />

5C-1604.02<br />

February 2011 11


<strong>Project</strong> <strong>Hurunui</strong> <strong>Wind</strong> <strong>Construction</strong> Effects <strong>and</strong> Management Report<br />

• Refining the criteria for fill site selection criteria as well as identifying potential fill sites.<br />

2.7 Access Options<br />

This section describes the access options considered for hauling wind turbine components<br />

to the core site together from the public road network with a description of the preferred<br />

route. A separate Traffic Impact Assessment (TIA) has been compiled to:<br />

• Assess any impact on traffic together with any proposed means of mitigating impacts.<br />

• Assess route options to transport components from port to site.<br />

2.7.1 Access Objectives<br />

The principal objectives in determining the main access from the local road network are:<br />

• To minimise impact on the environment.<br />

• To manage disruption to other road users <strong>and</strong> the public road network.<br />

• To maximise the efficiency of material transport.<br />

2.7.2 Core Site Access Options From The Local Public Road Network<br />

This section describes the access options considered from the local public road network to<br />

the core site.<br />

Several potential access options were assessed as indicated below <strong>and</strong> on Drawing Sheets<br />

3 <strong>and</strong> 4 in Appendix A (Appendix A.1 Overall Site Development Plans).<br />

Southern Access Options via Reeces Road<br />

1) Southern Access Road Option 1 via Reeces Road (Stevenson Property)<br />

2) Southern Access Road Option 2 via Reeces Road (Turnbull Property)<br />

3) Southern Access Road Option 3 via Reeces Road (Turnbull Property)<br />

Western Access Options via SH1<br />

1) Western Access Road Option 1 via SH1 (MacFarlane Property)<br />

2) Western Access Road Option 2 via SH1 (MacFarlane Property)<br />

3) Western Access Road Option 3 via SH1 (Sowden Property)<br />

Northern Access Options via Motunau Beach Road<br />

1) Northern Access Option 1 Road via Motunau Beach Road (Batchelor Property<br />

2.8km from SH1)<br />

5C-1604.02<br />

February 2011 12


<strong>Project</strong> <strong>Hurunui</strong> <strong>Wind</strong> <strong>Construction</strong> Effects <strong>and</strong> Management Report<br />

2) Northern Access Option 2 Road via Motunau Beach Road (Batchelor Property<br />

3.2km from SH1)<br />

3) Northern Access Option 3 Road via Motunau Beach Road (Batchelor Property<br />

3.2km from SH1)<br />

4) Northern Access Option 4 Road via Motunau Beach Road (Batchelor Property<br />

3.2km from SH1)<br />

Each option is discussed below.<br />

Southern Access Options via Reeces Road<br />

1) Southern Access Road Option 1 via Reeces Road (Stevenson Property) – Approx<br />

2.2km Long<br />

This route begins at the entrance to the Stevenson’s residence on Reeces Road<br />

approximately 5.9km from the intersection of Reeces Rd with SH1. This route utilises the<br />

existing driveway up to the Stevenson residence, approximately 600m long, before<br />

following a newly formed access road approximately 1.6km long to access the southern end<br />

of Road D at turbine D1.<br />

The majority of this southern access option route involves moderate earthworks with<br />

minimal road cuts apart from the initial section of this route as it climbs the side of the ridge<br />

in a sidling cut. This route was ruled out as it utilised the existing Stephenson driveway <strong>and</strong><br />

there are no other viable options to circumvent this section of the route.<br />

2) Southern Access Road Option 2 via Reeces Road (Turnbull Property) - Approx<br />

2.4km Long<br />

This route begins at the Turnbull entrance off Reeces Road, approximately 7km from the<br />

intersection of Reeces Rd <strong>and</strong> SH1. This route is approximately 2.4km long <strong>and</strong> generally<br />

follows an established farm track to Road A between turbines A1 <strong>and</strong> A2.<br />

This option involves extensive earthworks, significant geotechnical risks <strong>and</strong> environmental<br />

concerns associated with 2 stream crossings <strong>and</strong> working along the valley floor adjacent to<br />

a stream. This option was ruled out due to the geotechnical risks associated with the road<br />

cuttings along the steep sided ridge to Turbine A1 <strong>and</strong> the environmental impact associated<br />

with the stream crossings <strong>and</strong> section along the valley floor.<br />

3) Southern Access Road Option 3 via Reeces Road (Turnbull Property) - Approx<br />

2.7km Long<br />

This option commences at the southwest end of the Turnbull property, approximately 7.6km<br />

from the intersection of Reeces Rd <strong>and</strong> SH1. Rather than traverse the side of the main<br />

ridge to reach Road A, as does the previous option, this route generally runs along the main<br />

ridge following 2 stream crossings, both requiring culverts, at the beginning of the route.<br />

This option was also ruled out due to extensive earthworks <strong>and</strong> the environmental impact<br />

associated with the 2 stream crossings at the beginning of this route.<br />

5C-1604.02<br />

February 2011 13


<strong>Project</strong> <strong>Hurunui</strong> <strong>Wind</strong> <strong>Construction</strong> Effects <strong>and</strong> Management Report<br />

Western Access Options via SH1<br />

1) Western Access Road Option 1 via SH1 (MacFarlane Property) - Approx 3.1km<br />

Long<br />

The western access begins at the main entrance to the MacFarlane property, approximately<br />

4.4km north from the junction of SH1 with Reeces Road. This route passes over a railway<br />

crossing <strong>and</strong> typically follows an existing farm track which generally runs along side the<br />

MacFarlane property’s southern boundary up to Road D between turbines D2 <strong>and</strong> D3. This<br />

section is illustrated on Photographs 64, 65 <strong>and</strong> 66 in Appendix B.<br />

This option was also ruled out due to extensive earthworks, the environmental impact<br />

associated with the stream crossing at the beginning of this route <strong>and</strong> the potential issues<br />

associated with the rail crossing.<br />

2) Western Access Road Option 2 via SH1 (MacFarlane Property) - Approx 2.5km<br />

Long<br />

This option begins approximately 7.8km north from the junction of SH1 with Reeces Road<br />

<strong>and</strong> generally follows an existing farm track to Road D between turbines D10 <strong>and</strong> D11.<br />

Sections of this route are illustrated on Photographs 67 <strong>and</strong> 68 in Appendix B.<br />

This option was also ruled out due to extensive earthworks <strong>and</strong> the environmental impact<br />

associated with the stream crossing at the beginning of this route.<br />

3) Western Access Road Option 3 via SH1 (Sowden Property) - Approx 1.8km Long<br />

This option begins approximately 11km from the junction of SH1 with Reeces Road <strong>and</strong><br />

climbs a low lying ridge to Road D at Turbine D14. This option involves less earthworks <strong>and</strong><br />

less environmental impacts than the other western access options described above but still<br />

requires significant earthworks with gradients up to approximately 20% <strong>and</strong> a maximum cut<br />

height of approximately 20m.<br />

This option was ruled out in favour of the northern access options described below.<br />

Northern Access Options via Motunau Beach Road<br />

Four access options from the north were considered <strong>and</strong> are described below. The first<br />

option considered provided the most direct route to the turbines but passed close to<br />

neighbouring l<strong>and</strong>owners the Guards <strong>and</strong> the Symmonds. Three further options were<br />

considered following consultation with these l<strong>and</strong>owners. These three options are also<br />

described below.<br />

1) Northern Access Option 1 via Motunau Beach Road (Batchelor Property) – Approx<br />

2.2km Long<br />

This route commences at the intersection of Motunau Beach Road <strong>and</strong> the Batchelor/Daly<br />

property approximately 2.8km from SH1. The initial section of this route avoids the main<br />

access to the Batchelor residence <strong>and</strong> nearby farm buildings by running parallel to the<br />

existing Batchelor/Daly access before linking up with <strong>and</strong> generally following the main farm<br />

track along an east to west running ridgeline to Road A near Turbine A11.<br />

5C-1604.02<br />

February 2011 14


<strong>Project</strong> <strong>Hurunui</strong> <strong>Wind</strong> <strong>Construction</strong> Effects <strong>and</strong> Management Report<br />

This route has no stream crossings <strong>and</strong> the least earthworks of all the northern options<br />

investigated. However the initial section of this route passes close to the boundaries of two<br />

adjacent l<strong>and</strong>owners (Guard <strong>and</strong> Symmonds) to the north.<br />

2) Northern Access Option 2 via Motunau Beach Road (Batchelor Property) – Approx<br />

2.2km Long<br />

This route commences at the intersection of Motunau Beach Road <strong>and</strong> the Batchelor/Daly<br />

property approximately 3.2km from SH1. This route was considered following consultation<br />

with the adjacent l<strong>and</strong>owners identified above. The initial section of this route commences<br />

approximately 400m further south of the Option 1 above <strong>and</strong> offers a significant separation<br />

from the adjacent l<strong>and</strong>owners. The route travels west across two stream crossings <strong>and</strong><br />

climbs the next ridgeline south of Option 1 in deep box cuts to meet Road A at Turbine A11.<br />

This route requires extensive cuts reaching approximately 30m <strong>and</strong> steep gradients up to<br />

20%.<br />

This option was ruled out due to extensive cuts, steep gradients <strong>and</strong> the environmental<br />

impact associated with two stream crossings.<br />

3) Northern Access Option 3 via Motunau Beach Road (Batchelor Property) – Approx<br />

2.4km Long<br />

This route commences at the same location of Option 2 above <strong>and</strong> was also considered<br />

following consultation with the adjacent l<strong>and</strong>owners identified above. This route also travels<br />

west across one stream crossing but climbs another east to west running ridgeline south of<br />

Option 2. This route requires significant earthworks <strong>and</strong> steep gradients up to 20%. The box<br />

cuts required along this route are not as deep as Option 2 <strong>and</strong> are expected to reach<br />

approximately 16m.<br />

This option was ruled out due to significant earthworks <strong>and</strong> the environmental impact<br />

associated with the stream crossing.<br />

4) Northern Access Option 4 via Motunau Beach Road (Batchelor Property) – Approx<br />

2.5km Long<br />

This route also commences at the same location of Options 2 <strong>and</strong> 3 above following<br />

consultation to provide a significant separation from the adjacent l<strong>and</strong>owners. However this<br />

route avoids the stream crossings associated with Options 2 <strong>and</strong> 3 above by following the<br />

same ridgeline utilised by Option 1 to meet Road A at Turbine A11. To maintain a<br />

reasonable separation between the adjacent l<strong>and</strong>owners this option climbs along the<br />

southern side of ridgeline for approximately 800m before following the same route as<br />

Option 1 to reach Turbine A11 at Road A. The maximum gradient expected along this route<br />

is approximately 15% <strong>and</strong> a maximum box cut of approximately 18m.<br />

This route requires greater earthworks than Option 1 as a result of providing a reasonable<br />

separation from the adjacent l<strong>and</strong>owners but like Option 1 involves no stream crossings.<br />

This option was selected for the following reasons:<br />

• Provides the most technically feasible option with respect to earthworks while<br />

maintaining a reasonable separation from adjacent l<strong>and</strong>owners.<br />

5C-1604.02<br />

February 2011 15


<strong>Project</strong> <strong>Hurunui</strong> <strong>Wind</strong> <strong>Construction</strong> Effects <strong>and</strong> Management Report<br />

• Requires no stream crossings thereby reducing environmental impacts<br />

• Provides access to the site from a local road rather than a State Highway<br />

3 Core Site <strong>Construction</strong> Works<br />

3.1 <strong>Overview</strong> <strong>and</strong> Site Description<br />

3.1.1 General Approach<br />

The overall access road design philosophy has been to follow existing tracks <strong>and</strong> tops of<br />

ridges wherever possible. This minimises the volume of excavation (<strong>and</strong> hence l<strong>and</strong><br />

disturbance), improves geotechnical conditions, reduces the risk of erosion (due to these<br />

being the flatter areas) <strong>and</strong> generally avoids areas such as gullies <strong>and</strong> undisturbed<br />

watercourses.<br />

As discussed in Section 2.1 above the width of the core site access roads are largely<br />

governed by the crane required to erect the wind turbine components, together with the<br />

provision of safe <strong>and</strong> efficient utilisation for construction traffic. Within the core site two<br />

access road widths have been assumed:<br />

• 7m wide trafficable width (formation width of 8.5m) for the main access road from<br />

the public road network to the core site.<br />

• 6m wide trafficable width for core site access roads.<br />

3.2 L<strong>and</strong> Disturbance<br />

The main sources of l<strong>and</strong> disturbance will arise from:<br />

• Forming access roads <strong>and</strong> working platform areas at turbine sites.<br />

• Disposing excess excavated material at suitable sites identified within the project<br />

area. The identification of spoil fill areas is part of the Supplementary Environmental<br />

Management Plan (SEMP) process (Refer Environmental Management Plan in<br />

Appendix E).<br />

• Establishing borrow areas at suitable locations to be identified within the project<br />

area to extract aggregates for road construction.<br />

• Forming turbine component lay down areas at strategic locations.<br />

• Forming platforms for site offices <strong>and</strong> a workshop.<br />

• Forming a platform for a concrete batching plant.<br />

• Forming a platform for the substation.<br />

• Laying underground cables, or the construction of overhead lines, between the<br />

turbine sites <strong>and</strong> substations.<br />

5C-1604.02<br />

February 2011 16


<strong>Project</strong> <strong>Hurunui</strong> <strong>Wind</strong> <strong>Construction</strong> Effects <strong>and</strong> Management Report<br />

• Overhead transmission from the substations to the external transmission network.<br />

• Constructing foundations for each turbine.<br />

• Constructing wind monitoring tower foundations.<br />

The indicative access road <strong>and</strong> site layout are shown in the drawings in Appendix A<br />

(Appendix A.2 – Access Road Plans & Cross Sections). Drawing Sheets 6 <strong>and</strong> 7 highlight<br />

indicative gradients along each of the access road alignments, while Drawing Sheets 8 <strong>and</strong><br />

9 show the approximate cross slopes along the roads <strong>and</strong> cross reference those to typical<br />

cross sections on Drawing Sheet 10. Access road plans are also provided from MXRoad<br />

which illustrate the construction footprint <strong>and</strong> location of road cuts <strong>and</strong> fills. These are<br />

shown on Drawing Sheets 11 to 14 with corresponding extreme cross sections shown on<br />

Drawing Sheets 15 to 19. Drawing Sheets 11 to 14 also identify the location of the access<br />

roads <strong>and</strong> turbines platforms in relation to areas of higher ecological value identified in the<br />

Ecological Values <strong>and</strong> Assessment of Effects report prepared by Boffa Miskell. These<br />

drawing sheets illustrate how the road alignments <strong>and</strong> turbine platforms have been<br />

designed to avoid these areas in all cases apart from the following areas:<br />

• The beginning of Road E prior to the junction between Turbines E1 <strong>and</strong> E2.<br />

Although Road E has been designed to avoid the majority of an area identified as<br />

having higher ecological value, it passes through the area’s eastern side as shown<br />

on Drawing Sheet 12. Avoiding the area completely by aligning Road E either further<br />

to the east or to the west would involve a greater impact by significantly increasing<br />

road cuts <strong>and</strong> earthwork volumes.<br />

• The northern corner of the platform for Turbine A11 affects a small section identified<br />

as having higher ecological value. The area affected may be reduced at detailed<br />

design stage when refinements to the turbine platform will be investigated.<br />

• One small section on Road A between Turbines A7 <strong>and</strong> A6.<br />

The access road alignments <strong>and</strong> turbine positions as indicated are based on available<br />

topographical <strong>and</strong> preliminary geotechnical information. During the detailed<br />

survey/investigation <strong>and</strong> design stage, access road alignments <strong>and</strong> turbine positions will be<br />

refined to optimise the design <strong>and</strong> suit terrain/geotechnical conditions. In this regard, it is<br />

recognised that it may be necessary to reposition turbines within a 100m radius placement<br />

area. The same 100m placement envelope will also apply to access roads. This approach<br />

has been approved by the Councils <strong>and</strong> Environment Court for <strong>Project</strong> West <strong>Wind</strong> <strong>and</strong><br />

Central <strong>Wind</strong>. Similarly this approach has been adopted <strong>and</strong> approved by Council for<br />

<strong>Project</strong> Mill Creek, currently awaiting an Environment Court Hearing decision.<br />

3.2.1 Detailed Description of Core Site Access Roads<br />

<strong>Project</strong> <strong>Hurunui</strong> <strong>Wind</strong> is sited in reasonably complex terrain <strong>and</strong> therefore turbines typically<br />

need to be placed on the ridge tops clear of localised topographic obstructions to minimise<br />

turbulence <strong>and</strong> capture higher mean wind speeds. While the total l<strong>and</strong> holding area of this<br />

project is approximately 34km 2 , only a small proportion of this is realistically available for<br />

turbine placement due to topographic constraints.<br />

5C-1604.02<br />

February 2011 17


<strong>Project</strong> <strong>Hurunui</strong> <strong>Wind</strong> <strong>Construction</strong> Effects <strong>and</strong> Management Report<br />

Approximately 22.2km of internal access roads will be required to access the turbine sites.<br />

These roads, designated alphabetically from Road A to H, have been planned with nominal<br />

widths of 6m <strong>and</strong> 7m. Roads on which main cranes are expected to traverse fully rigged<br />

have been planned with a nominal road width of 6m. The main access road which leads to<br />

the core site roads has also been planned with a nominal width of 7m. Additional minor<br />

tracks are required for construction of the transmission towers that support the transmission<br />

line between the proposed substation <strong>and</strong> external 66kV transmission line. These will be<br />

approximately 3.0m wide.<br />

The 22.2km of roads comprise approximately 5.2km of upgrading of existing farm tracks<br />

with the balance, approximately 17km, being new roads.<br />

The northern access road is the primary internal access road into the site <strong>and</strong> links with<br />

Road A at the northeastern section of the site. Road C provides the east to west link from<br />

Road A to Roads D, E, F, G <strong>and</strong> H.<br />

The layout of the roads to turbine sites will be reassessed during detailed design to align<br />

with the final turbine positions <strong>and</strong> terrain as determined after detailed survey <strong>and</strong><br />

geotechnical investigations. Each core site access road is described in detail below with<br />

references to photographs in Appendix B illustrating the location of roads <strong>and</strong> turbines in<br />

relation to the topography. The relationship between access roads <strong>and</strong> turbine platforms to<br />

the topography is also illustrated in the Truescape graphical attachments to the L<strong>and</strong>scape<br />

Assessment Report prepared by Peter Rough L<strong>and</strong>scape Architects Ltd.<br />

Northern Access Road<br />

The northern access road, at nominally 7m wide along its entire length, will be the principal<br />

access into site for all the construction plant, materials <strong>and</strong> WTG components. This road<br />

commences at a new entrance off Motunau Beach Road approximately 3.2km from SH1.<br />

From Motunau Beach Road this route runs across the Batchelor/Daly property. The initial<br />

section of this route runs west across a flat paddock before turning north in a wide<br />

sweeping bend adjacent to the proposed laydown area <strong>and</strong> site offices (refer Photographs<br />

1 <strong>and</strong> 2 in Appendix B).<br />

From this point the route runs just to the west of the Batchelor/Daly dwelling before turning<br />

west <strong>and</strong> climbing the beginning of a gentle ridge adjacent to some farm buildings as shown<br />

on Photograph 3 in Appendix B. From this point the route continues to ascend along the<br />

southern side of this gently rising ridge in a series of moderate sidling <strong>and</strong> box cuts at a<br />

gradient of approximately 11% to just prior to the forested section. The route then traverses<br />

through the forested section in a large box cut with a maximum height of approximately<br />

18m at a gradient of approximately 15%. This section is illustrated on Photograph 4 in<br />

Appendix B.<br />

The northern access road rejoins the existing track as it leaves the forested section <strong>and</strong><br />

follows it in a tight horizontal curve around a steep sided ridge in a sidling cut as illustrated<br />

in Photograph 5 in Appendix B. Just prior to the bend the route steepens to approximately<br />

16% before easing to approximately 7% as it enters the curve. Along with the section of cut<br />

through the forest this is the most technically challenging section of the route <strong>and</strong> will<br />

5C-1604.02<br />

February 2011 18


<strong>Project</strong> <strong>Hurunui</strong> <strong>Wind</strong> <strong>Construction</strong> Effects <strong>and</strong> Management Report<br />

comprise extensive earthworks with sidling cuts up to approximately 17m in height as<br />

shown on Photograph 5 in Appendix B.<br />

Once the route leaves the tight bend it continues to traverse the ridge in a sidling cut to the<br />

ridge top at a gradient of approximately 15%. From this location the route generally follows<br />

the ridge in a series of cuts <strong>and</strong> fills to join with Road A at Turbine A11 as shown on<br />

Photographs 6, 7 <strong>and</strong> 8 in Appendix B.<br />

Road A<br />

Road A is typically 6m wide (apart from the section between Turbines A11 <strong>and</strong> A9) <strong>and</strong><br />

generally runs along one of the two main project ridgelines running in a north-east to southwest<br />

direction. Road A begins in the northeast section of the site at turbine A11 <strong>and</strong><br />

terminates at the southwest section of the site at turbine A1.<br />

Road A runs along gentle to moderately undulating terrain in a series of moderate cuts <strong>and</strong><br />

fills from Turbine A11 to Turbine A8. The maximum gradient along this section is<br />

approximately 15% just prior to Turbine A8 with a corresponding maximum cut height of<br />

approximately 5m. Photograph 23 in Appendix B illustrates Road A between Turbines A9<br />

<strong>and</strong> A10 while the section just prior to Turbine A8 is shown on Photograph 13 in Appendix<br />

B.<br />

Between turbines A8 <strong>and</strong> A7 Road A generally descends following the ridgeline reaching a<br />

maximum gradient of about 13% prior to leveling out at Turbine A7. Beyond Turbine A7<br />

Road A descends at approximately 14% before rising along the ridgeline south towards<br />

Road C <strong>and</strong> Turbine A6. The section of Road A beyond Turbine A7 is illustrated on<br />

Photograph 14 in Appendix B.<br />

From Turbine A6 Road A descends gradually to turbine A2 generally following the broad<br />

ridgeline in minor cuts <strong>and</strong> fills. This section is shown on Photographs 15 to 20 in Appendix<br />

B.<br />

The final section of Road A from turbine A2 descends at a moderate gradient before rising<br />

sharply to turbine A1 which is located at the top of a steep sided knoll. In order to reach<br />

turbine A1 a box cut with a maximum cut height of approximately 7m will be required at a<br />

maximum gradient of approximately 20%. This section is illustrated on Photographs 21 <strong>and</strong><br />

22 in Appendix B.<br />

Road B<br />

Road B follows a secondary ridgeline which branches off from Road A between turbines A4<br />

<strong>and</strong> A3. Road B crosses the upper reaches of a gully, which will require a fill embankment<br />

<strong>and</strong> culvert, approximately 100m from its intersection with Road A. Road B descends at a<br />

moderate gradient reaching a maximum of 13% before leveling off to access Turbine B1.<br />

This section is shown on Photograph 24 in Appendix B. From Turbine B2 Road B<br />

descends for approximately 300m before climbing at a gradient of about 15% in a box cut<br />

with a maximum cut height of 5m over a distance of approximately 100m. The remaining<br />

section of Road B is relatively flat as it terminates at Turbine B1. Photograph 25 in<br />

Appendix B illustrates Road B at Turbine B1 while Photograph 26 shows Road B as viewed<br />

from Turbine A1. Road B is 6m wide.<br />

5C-1604.02<br />

February 2011 19


<strong>Project</strong> <strong>Hurunui</strong> <strong>Wind</strong> <strong>Construction</strong> Effects <strong>and</strong> Management Report<br />

Road C<br />

Road C links Road A with Road D as well as servicing turbine C1. Road C runs at a<br />

relatively flat gradient from Road A <strong>and</strong> rises at approximately 15% prior to traversing the<br />

upper slopes of a steep knoll. A maximum cut height of approximately 10m is reached as<br />

Road C traverses this knoll to access the turbine platform for Turbine C1. Beyond Turbine<br />

C1 Road C descends in a moderate gradient winding gently between knolls to Road D.<br />

Road C crosses the upper reaches of a small gully, which will require culverting, just prior to<br />

Road D. This section is illustrated on Photograph 27 in Appendix B.<br />

Road D<br />

Road D is approximately 6m wide <strong>and</strong> typically follows one of the main project ridgelines<br />

(the other being Road A) running in a north-east to south-west direction. Road D begins in<br />

the northeast section of the site at turbine D14 <strong>and</strong> terminates at the southwest section of<br />

the site at turbine D1.<br />

The route between turbines D14 <strong>and</strong> D13 descends at a maximum gradient of<br />

approximately 5% before leveling at a saddle. From the saddle Road D steadily climbs to<br />

reach the short link road to Turbine D13. A maximum gradient of approximately 20% is<br />

expected along this section prior to the link to Turbine D13. This section is illustrated on<br />

Photograph 28 in Appendix B.<br />

Road D rises gently from Turbine D13 to Turbine D12 along moderately undulating terrain.<br />

Between Turbines D12 <strong>and</strong> D11 Road D rises in an embankment fill at a maximum gradient<br />

of about 17% <strong>and</strong> a corresponding maximum embankment fill of approximately 5m in depth<br />

before leveling off just prior to Turbine D11. From Turbine D11 to Turbine D10 the<br />

horizontal alignment of the route is relatively straight <strong>and</strong> the gradients relatively flat. Minor<br />

earthworks are expected along this section.<br />

Between Turbine D10 <strong>and</strong> Turbine D7 Road D comprises sections of cuts <strong>and</strong> fills to<br />

maintain acceptable gradients as it continues to follow a broad ridgeline along gently<br />

undulating terrain. The cut heights along this section are modest <strong>and</strong> remain under 5m.<br />

Photograph 29 in Appendix B illustrates the terrain along this section of Road D.<br />

The topography changes between Turbines D7 <strong>and</strong> D2 where the ridgeline narrows <strong>and</strong><br />

undulates sharply constraining Road D to run in a succession of sidling cuts <strong>and</strong> saddle fills<br />

to achieve acceptable grades <strong>and</strong> alignments. Photograph 30 illustrates the section of<br />

Road D between Turbines D7 <strong>and</strong> D5 while Photograph 31 shows the section of Road D in<br />

the vicinity of Turbine D5. In order to ease the gradient of Road D prior to Turbine D5 a fill<br />

embankment is proposed across a narrow saddle as shown in Photograph 31. The<br />

maximum height of this fill embankment is approximately 16m <strong>and</strong> it is expected that<br />

suitable material from nearby road cuts will be used as structural fill. From Turbines D5 to<br />

D4 Road D descends along the sharply undulating ridgeline reaching a maximum gradient<br />

of approximately 15%. The maximum cut height along this section is approximately 10m<br />

which represents the largest road cut along Road D. Between turbines D4 to D2 the<br />

ridgeline, although narrow, is less undulating <strong>and</strong> road D descends in a series of modest<br />

cuts <strong>and</strong> fills reaching a maximum gradient of 15% over a length of approximately 300m.<br />

Photograph 32 shows this section of Road D between turbines D4 <strong>and</strong> D3 while<br />

Photograph 33 shows Road D between Turbines D3 <strong>and</strong> D2.<br />

5C-1604.02<br />

February 2011 20


<strong>Project</strong> <strong>Hurunui</strong> <strong>Wind</strong> <strong>Construction</strong> Effects <strong>and</strong> Management Report<br />

The route between Turbines D2 <strong>and</strong> D1 is relatively flat with minor earthworks expected.<br />

Road D comprises gently undulating broad ridgelines at the northeast <strong>and</strong> southwest ends<br />

of this route but more complex <strong>and</strong> technically challenging terrain along the middle section<br />

as described above.<br />

Road D1<br />

Road D1 provides access to Turbines D6 <strong>and</strong> D7 <strong>and</strong> runs along gently undulating terrain.<br />

Minor earthworks are expected along this route which is shown on Photographs 38 <strong>and</strong> 39<br />

in Appendix B. This road is approximately 6m wide.<br />

Road D2<br />

Road D2 comprises a short section of road to access Turbine D9. This route is relatively<br />

flat <strong>and</strong> only minor earthworks are expected. Road D2 <strong>and</strong> Turbine D9 are shown on<br />

Photograph 37 in Appendix B.<br />

Road E<br />

Road E at approximately 6m wide commences at the intersection with Road D between<br />

Turbines D5 <strong>and</strong> D7 <strong>and</strong> circles around the outside of steep sided localised ridge in both<br />

sidling <strong>and</strong> box cuts to a point where both Turbines E1 <strong>and</strong> E2 can be accessed along<br />

alignments with reasonable gradients. The maximum cut height is approximately 7m with a<br />

corresponding maximum gradient of approximately 15% as Road B circles outside a steep<br />

sided ridge. Road E is shown on Photographs 34 <strong>and</strong> 35 in Appendix B.<br />

Road F<br />

Road F runs along a spur running approximately perpendicular to Road D near turbine D11.<br />

A series of moderate cuts <strong>and</strong> fills characterise Road F as it descends along moderately<br />

undulating terrain to reach turbine F1. Road F is approximately 6m wide.<br />

Road G<br />

Road G is approximately 6m wide <strong>and</strong> services turbine G1 which is located along a spur<br />

running perpendicular to the Road D ridgeline as shown on Photograph 36 in Appendix B.<br />

This route descends from Road D in a moderate sidling cut reaching a maximum down<br />

slope gradient of about 12% before leveling off in a fill embankment across a narrow<br />

saddle. Road G rises at a gentle gradient of approximately 5% from this saddle in a<br />

shallow box cut to reach turbine G1. The maximum cut height along Road G is<br />

approximately 6m.<br />

Road H<br />

Road H descends along a gently undulating spur running in a southeast direction<br />

perpendicular to Road D. The majority of the earthworks are concentrated at the latter<br />

section of this route where a maximum cut height of approximately 6m is expected. Road H<br />

is shown on Photograph 32 in Appendix B. Road H is approximately 6m wide.<br />

3.2.2 Access Road Formation<br />

Typical Cross Sections <strong>and</strong> Extent of Cuts<br />

5C-1604.02<br />

February 2011 21


<strong>Project</strong> <strong>Hurunui</strong> <strong>Wind</strong> <strong>Construction</strong> Effects <strong>and</strong> Management Report<br />

Table 2 indicates the typical access road cross sections for the different terrain types with<br />

cut slopes expected in the region of 1H:2V to 1H:4V. Fill slopes, where applied, are<br />

expected to be in the region of 2H:1V as tabulated in Table 3. Typical cross sections are<br />

illustrated on Drawing Sheet 10. Drawing Sheets 8 <strong>and</strong> 9 illustrate the sections of access<br />

road where these typical cross sections apply. The longitudinal extent of cuttings (length<br />

along the access roads) can be approximated to the linear length of each section identified.<br />

Side Slope at Road Location Typical Cut Slope Typical Cut Height<br />

Road running on ridgeline, in shallow<br />

box cut, or relatively flat l<strong>and</strong>.<br />

(Section A – Drawing Sheet 10)<br />

None<br />

through to 1H : 4V.<br />

Up to approximately<br />

1.5m.<br />

Road in sidling cut with side slopes up<br />

to 20% (1V:5H)<br />

(Section B – Drawing Sheet 10)<br />

Road in sidling cut with side slopes up<br />

to 40% (1V:3H)<br />

(Section C – Drawing Sheet 10)<br />

Box cuts on ridges, or in sidling cut<br />

situations. (Drawing Sheet 10)<br />

1H:2V<br />

1H:2V<br />

1H:2V<br />

2.5 to 3.5 metres.<br />

5 to 6 metres.<br />

1.5 to 6 metres.<br />

Table 2: Typical Cut Slope <strong>and</strong> Height<br />

Side Slope at Road Location Typical Fill Slope Typical Fill Depth<br />

Road running on relatively flat l<strong>and</strong> or<br />

gentle slopes.<br />

(Typical Section in Fill – Drawing<br />

Sheet 10)<br />

Table 3: Typical Fill Slope <strong>and</strong> Height<br />

2H:1V<br />

Varies, up to 5m<br />

Typical cut heights of 2.5m to 6m described in Table 2 will be similar in scale to some of<br />

those visible along the existing tracks. Photograph 6 in Appendix B illustrates such a cut on<br />

the existing track following the proposed alignment of the northern access road.<br />

Photographs F9 (taken at project Te Apiti) <strong>and</strong> F10 <strong>and</strong> F11 (taken at <strong>Project</strong> West <strong>Wind</strong>) in<br />

Appendix F illustrate road cuts with approximate heights between 7m to 8m.<br />

Table 4 summarises sections where extremities of cut height are expected (ie batter heights<br />

greater than or equal to approximately 6m.<br />

5C-1604.02<br />

February 2011 22


<strong>Project</strong> <strong>Hurunui</strong> <strong>Wind</strong> <strong>Construction</strong> Effects <strong>and</strong> Management Report<br />

Location<br />

(approx)<br />

Approx.<br />

Maximum<br />

Batter<br />

Height of<br />

Cut (m)<br />

Approx.<br />

Length of<br />

Individual<br />

Extreme<br />

Cuts (m)<br />

Approx.<br />

Maximum<br />

Earthworks<br />

Width &<br />

Location<br />

Indicative<br />

Section in<br />

Drawing<br />

Sheets 15<br />

to 18<br />

Northern Access Road (1.0km<br />

from Motunau Beach Road) 18 350 31m @ 1300m<br />

Section 1<br />

Northern Access Road (1.5km<br />

from Motunau Beach Road) 17 140 20m @ 1550m<br />

Section 2<br />

Road A (Between A1 & A2) 7 130<br />

14m @ 350m Section 3<br />

Road A (Between Road C & A2) 7 40<br />

19m @ 50m Section 4<br />

Road A (Between Road C & A2) 8 100<br />

19m@890m Section 5<br />

Road A (Between Road C & A11) 8 40<br />

18m @ 2300m Section 6<br />

Road A (Between Road C & A11) 7 70<br />

19m @2710 Section 7<br />

Road C 10 150<br />

19m @ 580m Section 8<br />

Road D (Between D1 & D3) 9 60<br />

15m @ 480m Section 9<br />

Road D (Between D3 & D7) 10 70<br />

15m @ 820m Section 10<br />

Road D (Between D3 & D7) 10 70<br />

18m @ 1020m Section 11<br />

Road D (Between D3 & D7) 9 80<br />

18m @ 1510m Section 12<br />

Road D (Between D3 & D7) 9 80<br />

17m @ 1730m Section 13<br />

Road D (Between D3 & D7) 7 40<br />

15m @ 2020m Section 14<br />

Road E (Between Road D & E1) 7 50<br />

14m @ 120m Section 15<br />

Road E (Between Road D & E1) 7 70 14m @ 290m Section 16<br />

Road G (Between Road D & G1) 6 100<br />

13m @ 550m Section 17<br />

Table 4: Extremities of Cut Height (Batter Cut Heights >= 6m)<br />

Typical Cut<br />

Slope<br />

1H:2V (Benching at 5m intervals)<br />

The cumulative length of sections where the cut height is greater than or equal to 6m is<br />

approximately 1.6km, which equates to approximately 7% of the proposed total access road<br />

network. In this respect, sections with cut heights greater than 6m only occur along a relatively<br />

small proportion of the entire access road network. We note that preliminary geotechnical<br />

investigations suggest that cut faces greater than 5m height should be benched at 5m intervals.<br />

Therefore these sections identified in Table 4 will be benched.<br />

The maximum batter height referred to in Table 4 is represented as the height of the cut face from<br />

the toe of the cut to the top of the batter. This measurement is illustrated in Figure 2 below.<br />

5C-1604.02<br />

February 2011 23


<strong>Project</strong> <strong>Hurunui</strong> <strong>Wind</strong> <strong>Construction</strong> Effects <strong>and</strong> Management Report<br />

Figure 2 – Batter Height of Cut<br />

Table 5 tabulates sections where fill depths are expected to exceed typical depths. Typical<br />

cross sections at these extremes are illustrated in Drawing Sheets 15 to 18. The total<br />

length of road with cuts greater than or equal to 6m is 1.58km.<br />

Location<br />

(approx)<br />

Approx.<br />

Maximum<br />

Fill<br />

Depth(m)<br />

Approx.<br />

Length of<br />

Individual<br />

Fill Sections<br />

(m)<br />

Road D (Between D1 & D3) 6 50<br />

Road D (Between D3 & D7) 16 170<br />

Road E (Between Road D & E1) 5 40<br />

Table 5: Extremities of Fill Depth (Fill Depths >= 5m)<br />

Approx.<br />

Maximum<br />

Earthworks<br />

Width &<br />

Location<br />

60m @<br />

STA1370<br />

13m @ STA<br />

2250<br />

22m @ STA<br />

50<br />

Indicative<br />

Section in<br />

Drawing<br />

Sheet 18<br />

Section 21<br />

Section 22<br />

Section 23<br />

Typical Fill<br />

Slope<br />

2H:1V<br />

Geotechnical investigations <strong>and</strong> observation during construction will also identify any areas<br />

of cutting with a potential for seepage, such as any areas with high groundwater pressure<br />

within the bedrock. Where seepage is likely to occur, measures such as horizontal<br />

drainage, or subsoil drains can be provided to control erosion. However, given the geology<br />

of the formation <strong>and</strong> observations on site, groundwater is unlikely to be of significant<br />

concern.<br />

As the works progress, the aim will be to rehabilitate (as appropriate) exposed cut <strong>and</strong> fill<br />

slopes as soon as is reasonably practicable. A requirement to this effect will be included in<br />

the construction contract documentation <strong>and</strong> will be included as part of the proposed<br />

conditions of consent. Rehabilitation for cuts in soil <strong>and</strong> fill slopes will use the most<br />

practical <strong>and</strong> effective re-vegetation techniques available at the time the work is required.<br />

Revegetation techniques are discussed in more detail in the Ecological Values <strong>and</strong><br />

Assessment of Effects report prepared by Boffa Miskell <strong>and</strong> incorporated in the<br />

Environmental Management Plan prepared by Tonkin <strong>and</strong> Taylor.<br />

5C-1604.02<br />

February 2011 24


<strong>Project</strong> <strong>Hurunui</strong> <strong>Wind</strong> <strong>Construction</strong> Effects <strong>and</strong> Management Report<br />

Estimated Cut Volumes<br />

The pessimistic volume of earthworks associated with formation of the access roads, based<br />

on the preliminary investigations to-date, is summarised in Table 6 below. The pessimistic<br />

earthworks volumes are calculated as 15% over <strong>and</strong> above the “most likely” earthworks<br />

volumes determined from MXRoad (computer-aided three dimensional design package).<br />

The volumes presented represent the upper bound of materials as we have assumed that<br />

earthworks will be undertaken on a cut-to-waste approach. Actual excess excavated<br />

material will be lower given that a cut-to-fill approach will be applied during detailed design.<br />

Table 6 below also shows that approximately 5.2km of access roading comprise of existing<br />

tracks which equates to approximately 22% of the total length of access roads.<br />

Road<br />

Approximate<br />

Length (km)<br />

Approx portion<br />

comprising upgraded<br />

existing tracks (km)<br />

Cut Only<br />

(m 3 )<br />

Northern Access Road 2.5 1.8 123,000<br />

Road A 5.8 1.4 98,000<br />

Road B 1.9 17,000<br />

Road C 1.4 30,000<br />

Road D 7.3 1.8 121,000<br />

Road D1 0.5 6,000<br />

Road D2 0.3 4,000<br />

Road E 0.9 11,000<br />

Road F 0.6 4,000<br />

Road G 0.8 16,000<br />

Road H 0.5 0.2 5,000<br />

<strong>Project</strong> Total 22.5 5.2 435,000<br />

Table 6: Estimated Access Road Excavation Volumes<br />

Access Road Surfacing<br />

Access roads will typically be unsealed with a basecourse running surface. Roads will be<br />

categorised as to the level of construction traffic on them with an expected design depth of<br />

basecourse between 100mm <strong>and</strong> 200mm depending on traffic levels <strong>and</strong> ground<br />

conditions.<br />

Initial geotechnical investigations suggest that material sourced within the project area from<br />

excavations for the access roads, working platforms <strong>and</strong> foundations is unlikely to be of<br />

sufficient strength to provide an adequate source of basecourse. We have observed that<br />

the quality of bedrock is variable (ranging from fresh <strong>and</strong> unweathered to exposed <strong>and</strong><br />

weathered). Further detailed geotechnical investigations will be required to confirm<br />

whether on-site material is suitable for use as a basecourse. In the event suitable material<br />

is available on site excavated materials can be stockpiled at localised processing areas<br />

5C-1604.02<br />

February 2011 25


<strong>Project</strong> <strong>Hurunui</strong> <strong>Wind</strong> <strong>Construction</strong> Effects <strong>and</strong> Management Report<br />

where a mobile crushing plant will be employed to produce the required grade of<br />

basecourse material. This is discussed in more detail in Section 3.2.8 on borrow areas.<br />

In some circumstances, where longitudinal grades of principal roads exceed 15-18%, it is<br />

possible that the 5m central portion of the road may be sealed to improve traction <strong>and</strong><br />

reduce maintenance needs. Any pavement seal is likely to comprise chip seal depending<br />

on the maintenance strategy developed during the detailed design stage.<br />

3.2.3 Turbine Platforms<br />

While the maximum foundation base is expected to be approximately 16m to 18m in<br />

diameter (depending on final turbine <strong>and</strong> ground conditions), a larger flat area is required to<br />

accommodate the main tower <strong>and</strong> turbine erection cranes. Drawing Sheet 80 of Appendix<br />

A.5 shows generic requirements for a flat working platform. The area required will depend<br />

on the final crane configuration <strong>and</strong> any site specific constraints.<br />

The pessimistic volume of excavation associated with platform construction based on an<br />

upper bound 50m x 35m platform is summarised in Table 7.<br />

Road Nos. of Turbines Cut (m 3 )<br />

Road A 11 84,000<br />

Road B 2 11,000<br />

Road C 1 13,000<br />

Road D 12 69,000<br />

Road D1 1 6,000<br />

Road D2 1 2,000<br />

Road E 2 20,000<br />

Road F 1 3,000<br />

Road G 1 10,000<br />

Road H 1 7,000<br />

<strong>Project</strong> Total 33 225,000<br />

Table 7: Estimated Turbine Platform Excavation Volumes<br />

A maximum excavation depth of approximately 1.5m to 3m is typically required at sites on<br />

flat to gently rolling terrain to create the required platform area. However, sites with more<br />

undulating terrain require excavation greater than or equal to approximately 5m to create<br />

the required working platform area <strong>and</strong>/or to interface with the access road. Table 8<br />

summarises approximate average <strong>and</strong> maximum turbine platform excavation depths where<br />

the maximum platform cut height is expected to equal or exceed 5m. The approximate<br />

maximum cut depth presented, which represents the maximum height of cut that is likely to<br />

occur at the respective platform location, is illustrated in Figure 3 for three typical terrain<br />

types.<br />

5C-1604.02<br />

February 2011 26


<strong>Project</strong> <strong>Hurunui</strong> <strong>Wind</strong> <strong>Construction</strong> Effects <strong>and</strong> Management Report<br />

Photographs F12 <strong>and</strong> F13 in Appendix F show a turbine foundation at <strong>Project</strong> West <strong>Wind</strong><br />

before <strong>and</strong> after concreting <strong>and</strong> backfilling. Photographs F14 <strong>and</strong> F15 in Appendix F show<br />

a turbine foundation <strong>and</strong> platform at the operational stage of <strong>Project</strong> White Hill.<br />

Approx Max<br />

Cut<br />

Hillside cut<br />

Approx Max<br />

Cut<br />

Ridge cut<br />

Approx Max<br />

Cut<br />

Saddle cut<br />

Figure 3: Approximate Maximum Cut Depth Definition<br />

5C-1604.02<br />

February 2011 27


<strong>Project</strong> <strong>Hurunui</strong> <strong>Wind</strong> <strong>Construction</strong> Effects <strong>and</strong> Management Report<br />

Road<br />

Turbine<br />

Approx. Cut Depth (m)<br />

Average<br />

Maximum<br />

A2 4 7<br />

A3 4 10<br />

A7 3 8<br />

Road A<br />

A8 4 5<br />

A9 3 5<br />

A10 5 10<br />

A11 3 6<br />

Road B B1 3 5<br />

Road C C1 5 9<br />

D5 2 6<br />

D6 3 5<br />

Road D<br />

D7 3 5<br />

D10 3 5<br />

D12 4 5<br />

D14 4 7<br />

Road E<br />

E1 5 7<br />

E2 4 5<br />

Road G G1 3 5<br />

Table 8: Turbine Platforms - Excavation Expected to Equal or Exceed 5m in Height<br />

3.2.4 <strong>Construction</strong> Footprint of Roads & Turbine Platforms<br />

The construction footprint of core site access roads including turbine platforms calculated<br />

from MXRoad <strong>and</strong> illustrated on Drawing Sheets 11 to 14 in Appendix A (Appendix A.2<br />

Access Road Plans & Cross Sections) is shown in Table 9 Below.<br />

5C-1604.02<br />

February 2011 28


<strong>Project</strong> <strong>Hurunui</strong> <strong>Wind</strong> <strong>Construction</strong> Effects <strong>and</strong> Management Report<br />

Road<br />

Approximate<br />

Length (km)<br />

No. of Turbines<br />

Const.<br />

Footprint<br />

(m 2 )<br />

Northern Access Road 2.5 33,000<br />

Road A 5.8 11 82,000<br />

Road B 1.9 2 21,000<br />

Road C 1.4 1 9,000<br />

Road D 7.3 11 111,000<br />

Road D1 0.5 2 8,000<br />

Road D2 0.3 1 4,000<br />

Road E 0.9 2 13,000<br />

Road F 0.6 1 6,000<br />

Road G 0.8 1 11,000<br />

Road H 0.5 1 7,000<br />

<strong>Project</strong> Total 22.5 33 305,000<br />

Table 9: <strong>Construction</strong> Footprint of Core Site Roads <strong>and</strong> Turbine Platforms<br />

3.2.5 Spoil Fill Sites<br />

During the earthmoving operation excess excavated material will be placed at clearly<br />

defined spoil fill sites. These locations will be selected during detailed design/construction<br />

in accordance with the criteria outlined in Section 2.4. In some locations material may also<br />

be utilised to aid localised shaping of the adjacent ground to blend in the construction<br />

works.<br />

Based on observations of the site, the majority of spoil fill sites will occupy areas of pasture.<br />

The total area required to dispose of the pessimistic earthworks cut volumes, within the site<br />

assuming a conservative average fill depth of 2.5m, would be in the order of 250,000m 2<br />

(0.25km 2 ). This represents just under 1% of the total l<strong>and</strong> holding area of the site (34km 2 ).<br />

Given the l<strong>and</strong>form’s potential to provide well contained sites, the fact that earthworks<br />

quantities are likely to be lower than the pessimistic value quoted <strong>and</strong> the sites are<br />

generally capable of holding greater than 2.5m depth of fill, the total area of potential fill<br />

sites is expected to be smaller than the figure estimated above. Photographs 50 to 58 in<br />

Appendix B provide examples of typical well contained fill sites throughout the core site.<br />

The criteria for avoiding areas of high ecological value (areas not suitable for spoil fill sites)<br />

have been assessed in the Ecological Values <strong>and</strong> Assessment of Effects report. The<br />

detailed design/construction team will consult l<strong>and</strong>owners <strong>and</strong> other relevant stakeholders<br />

in the process of identifying <strong>and</strong> selecting the location <strong>and</strong> number of fill sites in accordance<br />

with the process outlined in the draft Environmental Management Plan (EMP) in Appendix<br />

5C-1604.02<br />

February 2011 29


<strong>Project</strong> <strong>Hurunui</strong> <strong>Wind</strong> <strong>Construction</strong> Effects <strong>and</strong> Management Report<br />

E. The extent <strong>and</strong> fill depths for each site will also be confirmed on the ground with<br />

l<strong>and</strong>owners/relevant stakeholders prior to construction <strong>and</strong> included within the<br />

Supplementary Environmental Management Plan.<br />

It is expected that the following typical measures would be incorporated into the design <strong>and</strong><br />

construction of the fill sites, as appropriate:<br />

• Strip topsoil <strong>and</strong> soft materials from the ground surface <strong>and</strong> stockpile.<br />

• Bench slopes as required to key in fill.<br />

• Install subsoil drainage in the base of gullies with branches to areas of observed<br />

seepage<br />

• Prepare surface drains within <strong>and</strong> on the periphery of the site to prevent erosion <strong>and</strong><br />

mitigate run-off as applicable.<br />

• Compact the fill adequately to ensure sufficient strength for stability <strong>and</strong> minimise<br />

settlements.<br />

• Adopt an appropriate fill profile for stability by considering the nature of the material<br />

<strong>and</strong> proposed fill height. The outer profile of the fill may vary between 3H:1V to<br />

2H:1V.<br />

• Where appropriate, surface cut off drains will be formed around the head of fill sites.<br />

Such drains are to have controlled outlets in stable locations clear of the fill area <strong>and</strong><br />

any areas of hillside instability.<br />

• Shape final surface of the fill to blend into the l<strong>and</strong>form.<br />

• The surface of the fill will generally be covered in topsoil (which has been previously<br />

removed <strong>and</strong> stockpiled) <strong>and</strong> vegetated with suitable <strong>and</strong> appropriate ground cover.<br />

The plant species shall be consistent with the species in the immediate vicinity of<br />

the exposed area, replacing “like with like”. Generally the site is covered in pasture<br />

<strong>and</strong> this is expected to be the predominant ground cover, with some areas of silver<br />

tussock.<br />

• Sediment control measures, as discussed in Section 3.3, will be installed to manage<br />

sediment run-off during construction <strong>and</strong> until ground cover is established.<br />

Examples of fill sites at other Meridian <strong>Wind</strong> Farm <strong>Project</strong>s are provided in Appendix F.<br />

These are described as follows:<br />

• Photograph F16 illustrates a fill site being prepared with benched slopes at <strong>Project</strong><br />

White Hill.<br />

• Photographs F17 <strong>and</strong> F18 show fill sites being prepared at <strong>Project</strong> West <strong>Wind</strong>.<br />

• Photograph F19 shows a disposal fill site at <strong>Project</strong> West <strong>Wind</strong> under rehabilitation.<br />

5C-1604.02<br />

February 2011 30


<strong>Project</strong> <strong>Hurunui</strong> <strong>Wind</strong> <strong>Construction</strong> Effects <strong>and</strong> Management Report<br />

• Photograph F20 illustrates a rehabilitated fill site at <strong>Project</strong> Te Apiti.<br />

3.2.6 Concrete Works<br />

Two foundation types may be used within the site depending on bedrock competency <strong>and</strong><br />

the depth of any overburden. These are a st<strong>and</strong>ard gravity pad or a rock anchor solution.<br />

Specific foundation details will be developed during the detailed design in conjunction with<br />

detailed geotechnical investigations <strong>and</strong> site specific testing. Indicative reinforced concrete<br />

foundation concepts are illustrated in Drawing Sheet 80 in Appendix A (Appendix A.5<br />

Typical Turbine Platform & External Turbine Transformer Details). The pessimistic volume<br />

of reinforced concrete associated with the gravity pad <strong>and</strong> rock anchor solution,<br />

respectively, is estimated to be approximately 400m 3 <strong>and</strong> 120m 3 per foundation.<br />

In order to provide an indication of resource inputs to the foundation construction a<br />

conservative scenario based on the use of st<strong>and</strong>ard gravity pad foundations at all sites has<br />

been adopted. Table 10 below summarises the approximate total volume of concrete <strong>and</strong><br />

the total number of concrete truck trips required based on this foundation type. We have<br />

assumed that concrete trucks will only be 75% full due to the gradients present (ie 4.5m 3<br />

per truck).<br />

Volume of Each Pad (m 3 ) Total Volume of 33<br />

Pads (m 3 ) (Including<br />

site concrete)<br />

No. of Trucks<br />

per pad<br />

Total No. of<br />

Trucks<br />

400 13,200 94-96 3,200<br />

Table 10: Concrete Pad Foundation Volumes <strong>and</strong> Truck Trips<br />

At these production volumes it is envisaged the contractor will establish an on-site concrete<br />

batching plant to minimise the number of truck movements on the public road network <strong>and</strong><br />

increase efficiency, i.e. fewer larger trucks delivering cement <strong>and</strong> aggregate. Such an<br />

approach on <strong>Project</strong> Te Apiti, White Hill <strong>and</strong> West <strong>Wind</strong> has demonstrated these benefits.<br />

Employing concrete batching plants is discussed in more detail in Section 7.<br />

We have assumed concrete aggregates will be sourced off site. Potential sources of<br />

concrete aggregates have been identified from quarries at local rivers such as the <strong>Hurunui</strong><br />

to the north/northwest <strong>and</strong> the Waipara to the south.<br />

Subject to approval from the <strong>Hurunui</strong> District Council, water supply for the batching plant<br />

may be sourced from the mains water supply network located throughout the site.<br />

Otherwise water will be delivered to site by tankers(Refer to section 3.2.17 for further<br />

information).<br />

It is estimated that 72,000 litres (72m 3 ) of water will be required for each 400m 3 foundation.<br />

Based on 33 gravity pad foundations, Table 11 indicates the average dem<strong>and</strong> on resources<br />

during turbine foundation construction.<br />

5C-1604.02<br />

February 2011 31


<strong>Project</strong> <strong>Hurunui</strong> <strong>Wind</strong> <strong>Construction</strong> Effects <strong>and</strong> Management Report<br />

Concrete<br />

Component<br />

Estimated Dem<strong>and</strong><br />

(Turbine<br />

Foundations)<br />

Estimated<br />

Dem<strong>and</strong> Per<br />

Pour (Same<br />

Day)<br />

Approximate<br />

Indication of Average<br />

Dem<strong>and</strong><br />

Cement 3,200 tonnes 94 tonnes 3 x 23 tonne bulk<br />

carriers per day<br />

S<strong>and</strong> <strong>and</strong><br />

Aggregate<br />

27,000 tonnes 800 tonnes 13 x 23 tonne trucks<br />

per day<br />

Water 2.4 million litres 72,000 7 tankers (10,000 litre<br />

capacity) per day<br />

Table 11: Indicative Batching Plant Dem<strong>and</strong> on Materials<br />

We envisage that measures to contain any dust, spillage <strong>and</strong> wash down of plant or trucks<br />

will be outlined in the contractor’s management plan. Such measures are likely to include<br />

cement storage within a silo, aggregate storage bins, a temporary concrete slab beneath<br />

the loading area <strong>and</strong> containment bunding around the plant.<br />

3.2.7 Borrow Areas<br />

Basecourse material may be sourced within the project area from excavations for the<br />

access roads, working platforms <strong>and</strong> foundations wherever practicable. Basecourse<br />

material may also be sourced from borrow areas within the site. However, an appraisal on<br />

the availability of suitable material on-site for processing roading <strong>and</strong> platform basecourse<br />

would be undertaken at the detailed design phase to determine whether suitable material is<br />

available on site.<br />

In the event that locally won materials will be suitable for road construction, borrow areas<br />

would be established at locations within the site which meet the same criteria established<br />

for fill sites (outlined in Section 2.4). Extracted materials will be stockpiled at localised<br />

processing areas where a mobile crushing plant will be used to produce the required grade<br />

of basecourse material. Material may also be extracted from these borrow areas for<br />

roading fill where there is a shortfall of suitable material excavated from road construction.<br />

The total pessimistic volume of basecourse required for roads, turbine platforms <strong>and</strong><br />

laydown areas is approximately 41,000m 3 . Assuming this involves approximately 90% of<br />

the equivalent volume in overburden to extract this material <strong>and</strong> an average borrow site<br />

depth of approximately 3m the following construction footprint expected is approximately<br />

25,000m 2 . These details are summarised in Table 12 below.<br />

Total Volume of<br />

Basecourse (m 3 )<br />

Equivalent Volume<br />

of Overburden (m 3 )<br />

Total Combined<br />

Volume (m 3 )<br />

<strong>Construction</strong><br />

Footprint (m 2 )<br />

41,000 35,000 76,000 25,000<br />

5C-1604.02<br />

February 2011 32


<strong>Project</strong> <strong>Hurunui</strong> <strong>Wind</strong> <strong>Construction</strong> Effects <strong>and</strong> Management Report<br />

Table 12: Potential Basecourse Volumes <strong>and</strong> Borrow Areas<br />

Should all basecourse be sourced on site the potential construction footprint would be<br />

approximately 25,000m 2 . This is minimal compared to the construction footprint of 285,000<br />

m 2 estimated for disposal fill areas associated with core site access roads <strong>and</strong> turbines<br />

(less than 10%).<br />

We expect the following activities <strong>and</strong> typical measures would be incorporated into the<br />

identification, design <strong>and</strong> operation of borrow areas, as appropriate:<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

A site appraisal by the design/construction team, in consultation with l<strong>and</strong>owners<br />

<strong>and</strong> other relevant stakeholders, to identify suitable borrow areas in line with the<br />

EMP. Areas of ecological value, particularly around rocky outcrops, as described in<br />

the road layout <strong>and</strong> fill site selection (Sections 2.3 <strong>and</strong> 2.4), will be avoided.<br />

Detailed soil investigation involving deep boring <strong>and</strong> trial pits at identified locations<br />

to confirm suitability for material extraction.<br />

Initial establishment of borrow area by site clearance followed by stripping <strong>and</strong><br />

stockpiling topsoil.<br />

Establishing a mobile crushing plant. A typical mobile crushing plant comprises a<br />

hopper, jaw crusher, conveyor <strong>and</strong> screen attached to a tracked wheel vehicle. An<br />

excavator generally fills the hopper with material for processing into basecourse.<br />

Excavation, processing <strong>and</strong> stockpiling of materials.<br />

Fill of excess or unwanted materials at suitable fill site locations.<br />

Mitigation to control run-off <strong>and</strong> sedimentation. Sediment control measures, as<br />

discussed in Section 3.3 below, will be provided to manage sediment run-off during<br />

operation <strong>and</strong> until ground cover is established after rehabilitation of the borrow<br />

area..<br />

Reshaping the borrow areas to blend in with the surrounding terrain, re-topsoiling<br />

(with material which has been removed <strong>and</strong> stockpiled) <strong>and</strong> re-vegetating. Measures<br />

will be discussed <strong>and</strong> agreed with l<strong>and</strong>owner. Note that the overburden material<br />

extracted from borrow areas <strong>and</strong> other surplus material from the civil works may be<br />

used to fill in borrow areas prior to topsoiling.<br />

At <strong>Project</strong> West <strong>Wind</strong> a mobile crushing plant was established on site at a borrow area near<br />

Oteranga Bay to produce materials for core site access roading <strong>and</strong> turbine platform<br />

basecourse. This mobile crushing plant <strong>and</strong> borrow area is illustrated on Photograph F21<br />

in Appendix F.<br />

3.2.8 Soil Stockpile Areas<br />

Topsoil will be stockpiled throughout the site for re-topsoiling fill sites, platform areas <strong>and</strong> so<br />

on. Long-term stockpiles will be temporarily stabilised by hydroseeding or hydro-mulching,<br />

if necessary, to reduce erosion <strong>and</strong> sediment generation.<br />

5C-1604.02<br />

February 2011 33


<strong>Project</strong> <strong>Hurunui</strong> <strong>Wind</strong> <strong>Construction</strong> Effects <strong>and</strong> Management Report<br />

3.2.9 Site Lay Down Areas<br />

WTG components will be delivered from port to site ahead of installation. Therefore lay<br />

down or stockpile areas will be required for temporary storage of turbine components, as<br />

well as other materials such as electrical cables. Rather than creating multiple large lay<br />

down areas for the bulk storage of turbine components, Meridian proposes to store turbine<br />

components near turbine locations using the turbine platforms <strong>and</strong> storage lay-bys adjacent<br />

to access roads where possible. This is to allow for sufficient components/materials to be<br />

stockpiled on site to meet the dem<strong>and</strong> of construction crews as well as to accommodate the<br />

arrival of several large shipments of components. Photographs F2 to F6 in Appendix F<br />

show how turbine platforms have been used to store turbine components while being lifted<br />

<strong>and</strong> assembled at both <strong>Project</strong> White Hill <strong>and</strong> <strong>Project</strong> West <strong>Wind</strong>. Photograph F22 shows a<br />

typical lay down area to store turbine blades at <strong>Project</strong> West <strong>Wind</strong>.<br />

The optimum <strong>and</strong> most strategic locations for storage lay-bys will be dependent on a more<br />

detailed study of the construction <strong>and</strong> installation sequences. At this stage potential<br />

storage lay-bys have been identified at the following locations:<br />

Near Turbine A9 along existing air strip as shown on Photograph 23 in Appendix B.<br />

<br />

Adjacent to the initial section northern access road as shown on Photograph 2 in<br />

Appendix B.<br />

3.2.10 Internal Cable Reticulation<br />

A 33kV or 22kV <strong>and</strong> fibre optic internal cable reticulation system is required to link the<br />

turbines to the substation. The internal cable layout developed for this project is a series of<br />

separate cable strings leading from the substation connecting all turbines along each main<br />

access road. These cables will generally be placed in trenches running along the formed<br />

access roads. It may be necessary to adopt some overhead reticulation to avoid hard,<br />

unstable or boggy ground or avoid a longer underground route only where the overhead<br />

line can be masked, or hidden from the skyline. For example an overhead line will be<br />

required to span a gully between Road D <strong>and</strong> Road A. Note this overhead line is internal to<br />

the site <strong>and</strong> any overhead reticulation would be constructed from monopole structures no<br />

taller than 20m.<br />

Typical trench dimensions could be 400mm to 600mm wide <strong>and</strong> 800mm to 1000mm deep.<br />

Where two cables run along a common road trenches will be located on either side of the<br />

road. Where off-road routes are required, trenching operations may require a working<br />

corridor of up to 5m (to form a cable trench) depending on the number <strong>and</strong> type of cables.<br />

Cable trenches will typically have a granular backfill to meet required thermal resistivity <strong>and</strong><br />

engineered fill with pavement or topsoil (material which has been removed <strong>and</strong> stockpiled)<br />

layer above as appropriate.<br />

Where overhead routes are employed, routes will be selected to follow the access road <strong>and</strong><br />

existing tracks/fencing corridors where possible. In the event a cross country route cannot<br />

be avoided, it is envisaged that overhead line construction will require the establishment of<br />

an appropriate corridor including access to any transmission poles.<br />

5C-1604.02<br />

February 2011 34


<strong>Project</strong> <strong>Hurunui</strong> <strong>Wind</strong> <strong>Construction</strong> Effects <strong>and</strong> Management Report<br />

Indicative cable trenching details are illustrated on Drawing Sheet 102 in Appendix A<br />

(Appendix A.7 Substation, Underground Cabling & Transmission Line Details). Photograph<br />

F23 in Appendix F shows a typical buried cable being constructed.<br />

3.2.11 Substation<br />

Substation Platform<br />

A substation will be required to connect the turbines to the Transmission grid. The<br />

proposed location for the substation is just south of Turbine D11 on the western side of<br />

Road D as shown on Drawing Sheets 81, 82 <strong>and</strong> 83 in Appendix A (Appendix A.7<br />

Substation, Underground Cabling & Transmission Line Details). The substation compound<br />

area will occupy an area approximately 79m by 46m. A maximum cut height of<br />

approximately 5m will be required on the edges of the construction footprint to create a<br />

single level platform for this substation as shown on Drawing Sheet 83. The indicative<br />

construction footprint, including batter slopes, <strong>and</strong> the pessimistic volume of excavated cut<br />

are shown in Table 13 below.<br />

Indicative Substation Footprint (m 2 ) Cut (m 3 )<br />

5,000 16,000<br />

Table 13: Substation <strong>Construction</strong> Footprint <strong>and</strong> Cut Volumes<br />

Although detailed geotechnical assessment of the site has not been completed at this<br />

stage, ground conditions are unlikely to present any problems. Once the substation site is<br />

established, the surrounding area that has been disturbed will be re-vegetated as<br />

appropriate.<br />

Substation Buildings & <strong>Construction</strong> Activities<br />

The following activities will be required at this substation:<br />

<br />

<br />

<strong>Construction</strong>, maintenance <strong>and</strong> use of a substation switch room for housing a<br />

switchgear suite <strong>and</strong> associated equipment. The dimensions of the switchgear<br />

building are approximately 14m long, 11m wide <strong>and</strong> a height of no more than 6m.<br />

The switchgear building will be located within the substation perimeter fence.<br />

<strong>Construction</strong>, maintenance <strong>and</strong> operation of a switchyard located within the<br />

climb/predator/pest-proof fenced substation area. The switchyard will include<br />

switching gear, insulators, circuit breakers <strong>and</strong> a main transformer, lightning<br />

protection masts up to 20m tall), communication equipment <strong>and</strong> other associated<br />

equipment. The communication equipment will consist of either a maximum of two<br />

dishes mounted on the side of the substation building or on a 5m mast beside the<br />

building.<br />

The transformer will be oil filled <strong>and</strong> located within appropriately designed bunds to retain<br />

any oil leakage <strong>and</strong> avoid any contamination of the stormwater runoff in the unlikely event<br />

of an oil spillage. As such, it is envisaged that a low concrete bund will be provided around<br />

5C-1604.02<br />

February 2011 35


<strong>Project</strong> <strong>Hurunui</strong> <strong>Wind</strong> <strong>Construction</strong> Effects <strong>and</strong> Management Report<br />

the transformer together with a concrete ground slab. Oil-water interceptor tanks will be<br />

constructed below the bunded area to separate <strong>and</strong> collect any spilt oil from rainwater.<br />

The substation switching gear, insulators, circuit breakers <strong>and</strong> main transformers will be<br />

less than 7m in height.<br />

A boundary stock proof fence (approximately 1.2m high wire mesh) will be constructed<br />

around the perimeter of the substation site <strong>and</strong> an internal 2.3m high wire mesh security<br />

fence at a distance of 10m within the boundary fence.<br />

Drawing Sheet 84 in Appendix A (Appendix A7 Substation, Underground Cabling &<br />

Transmission Line Details) shows indicative layout details of the substation facilties<br />

together with the services building discussed below.<br />

3.2.12 66 kV Transmission Line Connection<br />

A multi span single line 66 kV overhead connection is proposed to connect the substation to<br />

the Mainpower 66kV Line, which runs adjacent to the western side of the project. The<br />

proposed transmission line is approximately 2.7km long <strong>and</strong> supported on 12 transmission<br />

line structures. The transmission line structures proposed are concrete double pole<br />

structures, known as Pi Poles, no greater than 22m high. Indicative details on the layout<br />

<strong>and</strong> the proposed structures are shown on Drawing Sheets 85 <strong>and</strong> 103 in Appendix A<br />

(Appendix A.7 Substation, Underground Cabling & Transmission Line Details). The<br />

majority of pole structures will be supported by guy wires to reduce the size of the pole<br />

foundations. We expect each pole foundation will comprise a bored hole approximately<br />

800mm in diameter <strong>and</strong> approximately 2 metres deep filled with concrete. It is likely the<br />

foundations supporting the guy wires will also be concrete filled bored holes. The total<br />

volume of concrete per pole structure is expected to be minimal at approximately 10m 3 .<br />

The potential effects of the proposed transmission line route <strong>and</strong> structures have been<br />

minimised by:<br />

• Reducing visual impact by avoiding ridgelines.<br />

• Avoiding constructing access roads to each transmission structure by locating the<br />

transmission structures near existing established farm tracks.<br />

• Reducing the number of structures by reducing the number of turn angles<br />

Within the substation a single gantry no greater than 20m high will provide the overhead<br />

link to the main 66kV transmission line. Photograph F24 in Appendix F shows a typical<br />

gantry structure (<strong>Project</strong> White Hill) similar to the one proposed for this project. It is<br />

important to note that the gantry structure shown in Photograph F24 is a double gantry<br />

whereas this project proposes a single gantry structure.<br />

3.2.13 Services Building<br />

A permanent services building, including car-parking, for post construction maintenance is<br />

required. The services building will house a workshop, control room (for managing<br />

turbines) <strong>and</strong> amenities. The dimensions of the services building are approximately 33m x<br />

11m. The services building will be single story portal frame structure with steel cladding.<br />

5C-1604.02<br />

February 2011 36


<strong>Project</strong> <strong>Hurunui</strong> <strong>Wind</strong> <strong>Construction</strong> Effects <strong>and</strong> Management Report<br />

The maximum height of the services building is 7m. The services building will be serviced<br />

for water, sewerage <strong>and</strong> stormwater as described above for the switchgear building. The<br />

Services building will also support some communication equipment for operation of the<br />

wind farm site. This equipment may include up to two communications dishes mounted on<br />

the side of the building.<br />

The services building will be serviced in the following manner:<br />

<br />

<br />

<br />

Water supply: It is likely the building will rely on a rainwater collection system with<br />

on-site storage tank or tanks, or use the local mains supply if authorised by the<br />

<strong>Hurunui</strong> District Council.<br />

Sewerage: Any foul water will be directed to a septic tank located within the site<br />

area. Foul water flows are expected to be minimal, being generated from a single<br />

toilet, washbasin <strong>and</strong> kitchen area. Flows are likely to be managed easily by the<br />

soakage field contained within the site. Prior to design a soakage test will be<br />

undertaken to confirm the size of soakage field required.<br />

Stormwater: Runoff is expected to be minimal given the intention to collect rainfall<br />

runoff. Excess rainwater will be directed on to l<strong>and</strong>/adjacent undisturbed areas.<br />

3.2.14 Meteorological Masts (<strong>Wind</strong> Monitoring Towers)<br />

Two wind monitoring towers up to approximately 80m in height will be installed on the site<br />

to provide wind data for operational purposes. The proposed location of the wind monitoring<br />

masts are shown on Drawing Sheet 1 in Appendix A (Appendix A.1 Overall Site<br />

Development Plans).<br />

The wind tower is likely to comprise a steel truss structure on a concrete foundation pad of<br />

approximately 8.6m x 8.6m x 1m thick. Indicative wind monitoring tower details of a lattice<br />

tower is presented on Drawing Sheet 101 in Appendix A (Appendix A.9 Indicative <strong>Wind</strong><br />

Monitoring Mast Details). Guyed towers may also be utilised.<br />

The position of the wind monitoring tower is determined by the location of the turbines <strong>and</strong> it<br />

may be necessary to reposition the wind monitoring tower within a 150m radius of the<br />

indicated placement area.<br />

<strong>Construction</strong> of the tower will require the preparation of a flat working platform of<br />

approximately 12m x 12m to accommodate a crane <strong>and</strong> other construction vehicles. The<br />

sites as indicated have been selected in view of their relatively gentle grades in order to<br />

minimise earthworks. Working platform preparation <strong>and</strong> rehabilitation is envisaged to be<br />

similar to that for turbine platforms (but minor in comparison) as described in Section 3.2.3<br />

above.<br />

3.2.15 Estimated Earthwork Volumes & <strong>Construction</strong> Footprint - Summary<br />

The pessimistic estimate of the all l<strong>and</strong> disturbing activities within the core site is<br />

summarised in Table 14 below.<br />

5C-1604.02<br />

February 2011 37


<strong>Project</strong> <strong>Hurunui</strong> <strong>Wind</strong> <strong>Construction</strong> Effects <strong>and</strong> Management Report<br />

L<strong>and</strong> Disturbing Activity Cut (m 3 )<br />

Footprint<br />

(m 2 )<br />

Footprint/<br />

L<strong>and</strong>holding<br />

Area (34km 2 )<br />

Core Site Access Roads 435,000<br />

Turbine Platforms 225,000<br />

305,000 0.90%<br />

Substation & Services Building 16,000 5,000 0.01%<br />

Lay down Areas & Site Office 9,000 26,000 0.08%<br />

Trenching & New Tracks for Transmission Line 12,000 6,000 0.02%<br />

Borrow Areas 76,000 25,000 0.07%<br />

Spoil Fill Sites n/a 309,000 0.91%<br />

Erosion & Sediment Controls at Spoil Fill Sites n/a 15,000 0.04%<br />

<strong>Project</strong> Total 773,000 691,000 2.03%<br />

Table 14: Summary of Pessimistic Excavation Volumes within Core Site<br />

3.2.16 <strong>Construction</strong> Footprint in Relation to Hydrological Catchment Areas<br />

Drawing Sheet 22 in Appendix A (Appendix A.6 Hydrological Catchment Area Plan)<br />

identifies the various hydrological catchment areas which encompass the project area. This<br />

drawing illustrates the proportion of the project footprint to the catchment area <strong>and</strong> the<br />

remoteness of the project footprint to streams within each catchment area. Table 15,<br />

below, complements this drawing <strong>and</strong> shows:<br />

• Pessimistic earthworks cut volumes generated within each hydrological catchment<br />

area based on a pessimistic earthworks cut-to-waste volume of 683,000m 3 derived<br />

from Table 14.<br />

• Corresponding disposal fill areas from earthworks cut volumes within each<br />

hydrological catchment area based on an average fill site depth of 2.5m.<br />

• The construction area footprint within each hydrological catchment area.<br />

• The percentage of construction area to catchment area including the overall<br />

construction area to catchment area.<br />

5C-1604.02<br />

February 2011 38


<strong>Project</strong> <strong>Hurunui</strong> <strong>Wind</strong> <strong>Construction</strong> Effects <strong>and</strong> Management Report<br />

Hydrological<br />

Catchment<br />

Catchment<br />

Area (km 2 )<br />

Cut-to-Waste<br />

(m 3 )<br />

Disposal Fill<br />

Area (From<br />

Cut-to -<br />

Waste<br />

Material)<br />

(m 2 )<br />

<strong>Construction</strong><br />

Area (Turbine<br />

Platform,<br />

<strong>Construction</strong><br />

Road & Other<br />

Footprint (m 2 )<br />

Total<br />

Area (m 2 )<br />

Total<br />

Area/Catch<br />

ment Area<br />

(%)<br />

1 (North) 6.16 72,000 40,000 39,000 79,000 1.28%<br />

2 (Tipapa) 3.79 107000 25,000 40,000 65,000 1.72%<br />

3 (Cave) 6.89 196,000 45,000 89,000 134,000 1.94%<br />

4 (Motunau<br />

East)<br />

5 (Motunau<br />

Upper)<br />

4.32 48000 28,000 21,000 49,000 1.13%<br />

12.11 210000 79,000 105,000 184,000 1.52%<br />

6 (West) 4.26 17000 28,000 9,000 37,000 0.87%<br />

7 (North<br />

West)<br />

9.96 123,000 65,000 78,000 143,000 1.44%<br />

<strong>Project</strong> Total 47.49 773,000 310,000 381,000 691,000 1.46%<br />

Table 15: Earthworks Volumes <strong>and</strong> Areas Summarised by Catchment Area<br />

Table 15 illustrates that the proportion of the total construction footprint area to hydrological<br />

catchment area is very minor <strong>and</strong> overall represents approximately just 1.34% of the total<br />

hydrological catchment area. However Table 15 also identifies that hydrological catchment<br />

area No.3 (Cave) has the highest proportion of construction footprint area to catchment<br />

area followed by No.2 (Tipapa) <strong>and</strong> No.5 (Motunau Upper). Where possible the<br />

construction footprint area has been redirected from the more ecologically sensitive areas<br />

such as Cave <strong>and</strong> Motunau Upper to the less sensitive northern catchment areas including<br />

Tipapa. At detailed design more refinement to the road alignments <strong>and</strong> turbine platforms<br />

should result in more of the construction area positioned in the less sensitive catchment<br />

areas.<br />

A large fill site is proposed at a saddle along Road D just north of Turbine D5. This site will<br />

be a combination of structural fill to form the core of Road D as well as spoil fill to form the<br />

batters. This fill straddles the northwest catchment area <strong>and</strong> the more sensitive Motunau<br />

Upper catchment. Specific controls at this fill site will be required to manage sediment<br />

particularly where sediment run-off is within the Motunau Upper catchment.<br />

Measures to avoid, remedy or mitigate the potential adverse effects from discharges,<br />

including sediment run-off are discussed in the next section <strong>and</strong> in Appendix E (draft<br />

<strong>Construction</strong> Environmental Management Plan).<br />

5C-1604.02<br />

February 2011 39


<strong>Project</strong> <strong>Hurunui</strong> <strong>Wind</strong> <strong>Construction</strong> Effects <strong>and</strong> Management Report<br />

3.2.17 Water Dem<strong>and</strong>s<br />

As discussed in section 3.2.6 a water supply will be required to supply any onsite concrete<br />

batching, together with other site construction activities including dust suppression,<br />

stabilization <strong>and</strong> re-vegetation, pavement construction <strong>and</strong> for any mobile crushing plant.<br />

Indicative estimates of potential water dem<strong>and</strong> are summarised below in table 16.<br />

Activity<br />

Peak Daily<br />

Dem<strong>and</strong> (m 3 )<br />

Maximum<br />

Total Water<br />

Dem<strong>and</strong> (m 3 )<br />

Time Period<br />

Dust Suppression (non potable) 80 17,000 26 days per month for 8 months<br />

Stabilisation & Revegetation (non<br />

potable)<br />

15 3,100 26 days per month for 8 months<br />

Pavement <strong>Construction</strong> (non potable) 10 1,300 26 days per month for 5 months<br />

Mobile Crushing Plant (non potable) 5 1,000 26 days per month for 8 months<br />

Turbine Foundations & Other<br />

Concreting (potable)<br />

80 2,600 2 per week over 4 months<br />

Total 190 25,000<br />

Table 16: Indicative Estimates of Potential Water Dem<strong>and</strong><br />

Preliminary discussions with <strong>Hurunui</strong> District Council (HDC) suggest that a significant<br />

proportion of this dem<strong>and</strong> may be met via supply from the HDC water mains. Water supply<br />

from the mains <strong>and</strong> permitted abstraction rates will need to be negotiated with HDC at the<br />

appropriate time, however it is envisaged that temporary water storage tanks would be<br />

established on site to enable the buildup of water storage volume.<br />

Any shortfall in water requirement can be met via tanker delivery from offsite, from the<br />

creation of temporary stock ponds, or by stream abstraction within any consented or<br />

permitted limits.<br />

3.3 Discharges<br />

3.3.1 Erosion, Sediment <strong>and</strong> Dust Control<br />

We recognise that the construction of this wind farm will require extensive earthworks.<br />

However, the potential impact from erosion, sediment run-off <strong>and</strong> dust emissions are likely<br />

to be minor given the environmental management measures that will be applied. Details on<br />

the environmental management measures are discussed in detail in Appendix E (draft<br />

Environmental Management Plan) while the impact from erosion, sediment run-off <strong>and</strong> dust<br />

emission is addressed in the Ecological Values <strong>and</strong> Assessment of Effects report prepared<br />

by Boffa Miskell. One of Meridian’s prime objectives for the construction of this wind farm is<br />

to ensure that any potential adverse effects on the environment from any erosion, or<br />

sediment <strong>and</strong> dust discharges are avoided, remedied or mitigated. To achieve this<br />

Meridian will:<br />

<br />

Ensure that environmental management is a core requirement in the management<br />

process.<br />

5C-1604.02<br />

February 2011 40


<strong>Project</strong> <strong>Hurunui</strong> <strong>Wind</strong> <strong>Construction</strong> Effects <strong>and</strong> Management Report<br />

<br />

<br />

<br />

<br />

<br />

Prepare <strong>and</strong> implement a robust EMP <strong>and</strong> site specific SEMPs.<br />

Ensure a partnership approach between Meridian <strong>and</strong> the contractor(s).<br />

Ensure adequate resourcing of environmental management activities.<br />

Monitor <strong>and</strong> audit the project works to determine the effectiveness of the<br />

environmental management activities being undertaken.<br />

Ensure all incidents are reported to the <strong>Project</strong> Environmental Manager.<br />

The following outlines the approach that Meridian will implement to mitigate the impact of<br />

construction activities on the environment.<br />

a) Contract Requirements<br />

Although Meridian will be ultimately responsible for ensuring EMP <strong>and</strong> consent condition<br />

compliance, the construction contract will place specific responsibilities on the contractor for<br />

environmental management. The contract will require the contractor to:<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

Comply with the Environmental Management Plan (EMP) <strong>and</strong> Supplementary<br />

Environmental Management Plans (SEMPs). Refer to Appendix E for details on the<br />

EMP <strong>and</strong> SEMPs process.<br />

Have read <strong>and</strong> comply with resource consent conditions.<br />

Take all necessary measures to ensure no adverse effects arise from dust<br />

discharges.<br />

Attend environmental compliance meetings.<br />

Ensure all plant <strong>and</strong> equipment is clean <strong>and</strong> well maintained.<br />

Foster an environmentally responsible attitude on behalf of the contractor <strong>and</strong> his<br />

employees.<br />

Follow Meridian’s Accidental Discovery Protocol for archaeological or cultural<br />

remains.<br />

b) Erosion, Sediment <strong>and</strong> Dust Control Plans<br />

The main tool for avoiding or mitigating potential adverse effects from erosion, sediment<br />

<strong>and</strong> dust discharges is by preparing <strong>and</strong> implementing SEMPs for each major component of<br />

the work. There are four steps in preparing <strong>and</strong> implementing each SEMP:<br />

Plan Preparation<br />

Separate SEMPs will be prepared for specific locations <strong>and</strong> activities (as outlined in the<br />

EMP). To get construction underway as soon as possible, plans for partial sections of<br />

works may be prepared.<br />

5C-1604.02<br />

February 2011 41


<strong>Project</strong> <strong>Hurunui</strong> <strong>Wind</strong> <strong>Construction</strong> Effects <strong>and</strong> Management Report<br />

The first stage in plan preparation will be a walk over of the area to be covered by the plan.<br />

The walk over will involve the contractor, Meridian’s <strong>Construction</strong> Manager, Meridian’s<br />

Engineer, Meridian’s Environmental Manager, <strong>and</strong> an Environment Canterbury<br />

representative/s <strong>and</strong> <strong>Hurunui</strong> District Council representative/s (for some components). The<br />

purpose of the walk over is to identify the measures needed for minimising erosion <strong>and</strong><br />

sediment generation, e.g. cut off drains <strong>and</strong> treatment options for storm water runoff such<br />

as silt ponds, grit traps <strong>and</strong> so on. Based upon these discussions a draft SEMP will be<br />

prepared by the contractor assisted by Meridian’s Environmental Manager.<br />

The SEMP will include the following:<br />

<br />

<br />

<br />

<br />

A method statement covering health <strong>and</strong> safety matters, construction method,<br />

monitoring <strong>and</strong> contingencies.<br />

A plan or series of plans showing spoil areas to be used, cut off drains, culverts,<br />

surface water control works, silt ponds <strong>and</strong> any other sediment control measures.<br />

Inspection <strong>and</strong> reporting schedule particularly in response to adverse weather<br />

conditions.<br />

A list of maintenance activities.<br />

In addition, the SEMP will cover revegetation requirements, storage <strong>and</strong> h<strong>and</strong>ling of fuel,<br />

<strong>and</strong> management of waste.<br />

There are five location specific SEMP areas proposed for this project. At this stage an<br />

indicative SEMP plan for one of these areas has been prepared demonstrating the intended<br />

approach for such plans. Details on the SEMP area boundaries <strong>and</strong> the indicative SEMP<br />

plan are provided in Appendix E.<br />

Review<br />

The draft SEMPs will be submitted to both Environment Canterbury <strong>and</strong> <strong>Hurunui</strong> District<br />

Council as well as Meridian's Engineer <strong>and</strong> Environmental Manager for review. Comments<br />

from the review will be provided to the contractor who will finalise the plan. The final plan<br />

will be provided to the regional <strong>and</strong> district councils for their information <strong>and</strong> to satisfy any<br />

resource consent requirements.<br />

Implementation & Monitoring<br />

Implementing the SEMPs will be the responsibility of the contractor. Where required the cut<br />

off drains, silt ponds <strong>and</strong> other similar works will be installed in advance of earthworks<br />

commencing.<br />

The construction works will be monitored on a regular basis by Meridian or Meridian’s<br />

advisors. The frequency of this monitoring will be dictated by the work programme. A<br />

summary of the inspection will be copied to Meridian's Engineer. Work will only commence<br />

once Meridian’s <strong>Construction</strong> Manager is satisfied that appropriate measures to avoid<br />

potential adverse effects are in place or planned to be implemented. Examples of erosion<br />

<strong>and</strong> sediment control measures proposed for this project are detailed in the draft EMP in<br />

5C-1604.02<br />

February 2011 42


<strong>Project</strong> <strong>Hurunui</strong> <strong>Wind</strong> <strong>Construction</strong> Effects <strong>and</strong> Management Report<br />

Appendix E. Erosion <strong>and</strong> sediment controls will be designed <strong>and</strong> installed in accordance<br />

with Environment Canterbury's Erosion <strong>and</strong> Sediment Control Guidelines (2007).<br />

Auditing<br />

Ensuring an audit of compliance with the SEMPs will be the responsibility of Meridian’s<br />

Environmental Manager. It is proposed the audit will involve an inspection of site works <strong>and</strong><br />

a meeting that involves the contractor, Meridian’s <strong>Construction</strong> Manager <strong>and</strong> Environmental<br />

Manager. Environment Canterbury <strong>and</strong> <strong>Hurunui</strong> District Council will be invited to be part of<br />

this audit process.<br />

A programme for the audit meetings will be set once the construction programme is known.<br />

Any recommendations resulting from the audit process will be recorded <strong>and</strong> used to modify<br />

the current <strong>and</strong> subsequent SEMPs.<br />

(c) Reporting<br />

Initially, a weekly report shall be prepared by the contractor to identify the erosion, sediment<br />

<strong>and</strong> dust control activities undertaken, to provide comment on their effectiveness, <strong>and</strong> to<br />

identify any improvements which are required. This report will be reviewed by Meridian's<br />

Engineer. The reporting timetable will be reviewed on an ongoing basis as the project<br />

progresses.<br />

3.3.2 Permanent Stormwater Run-off<br />

Access roads<br />

Stormwater runoff control through cut sections of road will consist of unlined open side<br />

drains at the base of each cut. Depending on the ground conditions at any steep sections<br />

of access road, there may be a need to incorporate short lengths of concrete lining to limit<br />

erosion. On steeper sections, it is envisaged that stormwater flow velocity will be controlled<br />

(to minimise scour) with the use of rip-rap dissipaters or other similar devices.<br />

Water from the side drains will be discharged by either 300mm (approximately) diameter<br />

culverts under the access roads <strong>and</strong> fluming to gullies, or by fluming direct to gullies as<br />

appropriate. Given that the access roads are generally located at the upper reaches of<br />

catchment areas, water from most side drains will be discharged on to l<strong>and</strong> in dry gullies.<br />

However, where existing streams are present, such as that indicated by existing culverts,<br />

water will be discharged into the stream.<br />

Riprap or other similar stabilisation measures will be utilised at points of discharge. The<br />

position <strong>and</strong> intervals of the culverts will be determined during detailed design. The aim is<br />

to retain run-off within the existing natural catchment area.<br />

Turbine platforms<br />

Given the general nature of platform areas (e.g. small areas at the top of catchments), no<br />

particular permanent stormwater drainage measures are envisaged other than ensuring<br />

5C-1604.02<br />

February 2011 43


<strong>Project</strong> <strong>Hurunui</strong> <strong>Wind</strong> <strong>Construction</strong> Effects <strong>and</strong> Management Report<br />

that platform areas around the basecourse hardst<strong>and</strong> areas are backfilled with top soil with<br />

a slight cross fall, <strong>and</strong> regrassed to avoid erosion.<br />

Drainage provision may be provided to the foundation excavation by way of a trench or filter<br />

drain with suitable stabilised outlet.<br />

Fill sites <strong>and</strong> lay down areas<br />

The proposed treatment for fill sites is discussed in Section 2.4. Finished ground profiles<br />

will be shaped to ensure that natural drainage paths are maintained. On completion of<br />

construction, these sites will be re-topsoiled (with material which has been removed <strong>and</strong><br />

stockpiled) <strong>and</strong> re-vegetated as appropriate with runoff direct onto grassed l<strong>and</strong> on<br />

surrounding catchments.<br />

Lay down areas will have a general crossfall, allowing stormwater run off in the direction of<br />

the general slope of the l<strong>and</strong>. Sedimentation <strong>and</strong> erosion control measures as described in<br />

Section 3.3.1 above will be applied. On completion of construction, lay down areas will be<br />

rehabilitated in the same manner as fill sites.<br />

3.3.3 New Culverts at Stream or Gully Crossings in the Core Site<br />

No stream crossings have been identified within the core site however there are locations<br />

where upper gully crossings <strong>and</strong> existing open channel drain crossings will require culverts.<br />

Table 15 below summarises the proposed culverts identified along core site access roads.<br />

Culvert sizes have been based on flows for flood return periods of 20 years with provision<br />

for secondary flow paths across purposely lowered sections of the access road (for<br />

overtopping for longer return periods).<br />

We envisage no gully crossings in addition to those tabulated given the layout of the access<br />

roads are generally close to or on ridge tops where the terrain is relatively gentle. However,<br />

where new culverts are required per the detailed design (consequent to adjusting the<br />

turbine platforms <strong>and</strong> access roads within a 100m radius placement area), culverts will be<br />

sized as described above.<br />

The approximate height of the embankment at the culvert inlet of the majority of all culverts<br />

is less than 1m apart from one culvert on Road D which has an embankment height of<br />

approximately 1.5m at the culvert inlet. Given the embankment heights at culvert inlets are<br />

not significant no locations have been identified where an embankment fill could essentially<br />

form a ‘dam’ across upper valleys. However, if a significant embankment fill arises<br />

consequent to adjusting the turbine platforms <strong>and</strong> access roads (within a 100m radius<br />

placement area) the culvert will be sized on flows for flood return periods of 100 years to<br />

address the effects of ‘heading up’ associated with culverts with significant embankment<br />

fills.<br />

Based on this design criteria, the required culvert sizes are indicated in the following table.<br />

The final size of the culvert, where required, will be determined during the detailed design<br />

stage. This table also identifies a range of characteristics associated with each culvert.<br />

5C-1604.02<br />

February 2011 44


<strong>Project</strong> <strong>Hurunui</strong> <strong>Wind</strong> <strong>Construction</strong> Effects <strong>and</strong> Management Report<br />

An ecological assessment of these locations is discussed in the Ecological Values <strong>and</strong><br />

Assessment of Effects report prepared by Boffa Miskell.<br />

Road<br />

Culvert<br />

ID<br />

Indicative<br />

Culvert Size<br />

(mm dia.)<br />

Indicative<br />

Culvert<br />

Length (m)<br />

Approx<br />

Catchment<br />

Area (Ha)<br />

Approx Height of<br />

Embankment at<br />

Inlet (m)<br />

(from ground<br />

level)<br />

Northern A1A 375 15 4 ≤1.0<br />

Access Road A1B 375 14 4 ≤1.0<br />

Road A A1 300 15 1.2 ≤1.0<br />

A2 450 14 3.0 ≤1.0<br />

A3 600 13 3.8 ≤1.0<br />

A4 300 11 0.7 ≤1.0<br />

A5 300 11 0.5 ≤1.0<br />

Road B B1 375 13 2.1 ≤1.0<br />

Road D D1 300 20 1.1 1.5<br />

D2 300 18 0.3 ≤1.0<br />

D3 300 20 0.7 ≤1.0<br />

Road G G1 600 14 4.4 ≤1.0<br />

Table 17: Culverts at Gully Crossings within the Core Site<br />

The culvert location plan is shown on Drawing Sheets 23 to 26 while typical culvert details<br />

are shown on Sheet 27 in Appendix A (Appendix A.4 Culvert Location Plans & Typical<br />

Details).<br />

3.3.4 Upgrading Existing Culverts Along Motunau Beach Road<br />

One culvert along Motunau Beach Road, just south of the proposed site entrance, will<br />

require lengthening to accommodate the proposed widening of the road shoulder along this<br />

section. The existing 450 diameter concrete culvert, which serves an open channel drain<br />

from within the Batchelor/Daly property will require lengthening on the eastern side of<br />

Motunau Beach Road as shown on Drawing Sheet 205 in Appendix A8.<br />

3.3.5 Culvert <strong>Construction</strong> Methodology<br />

Installing culverts will involve bed preparation, laying of pipe culverts, construction of<br />

headwalls <strong>and</strong> backfilling/compaction. There are no stream crossings therefore stream<br />

diversions will not be required.<br />

4 Minor Shoulder Widening At Motunau Beach Road<br />

4.1 Shoulder Road Widening Opposite Site Entrance<br />

Directly opposite the proposed site entrance the shoulder of the southbound lane will be<br />

widened approximately 3m to provide an overall sealed width of approximately 6m from the<br />

centerline as shown on Drawing Sheet 205 in Appendix A8. The widening is provided to<br />

facilitate vehicles turning right into the site from the south. The proposed widening will<br />

5C-1604.02<br />

February 2011 45


<strong>Project</strong> <strong>Hurunui</strong> <strong>Wind</strong> <strong>Construction</strong> Effects <strong>and</strong> Management Report<br />

extend over an existing road culvert which will need to be lengthened as described in<br />

Section 3.3.4 above.<br />

The existing permanent stormwater network of side drains will be maintained on the eastern<br />

side of Motunau Beach Road by forming a new side drain at the toe of the proposed<br />

widened section. This side drain will also discharge into the existing open channel drain just<br />

east of Motunau Beach Road. On the western side the existing side drain will follow a new<br />

side drain formed at the site entrance <strong>and</strong> will discharge into the existing open channel<br />

drain in the Batchelor/Daly property.<br />

The widened area will be formed with minor quantities of compacted basecourse <strong>and</strong><br />

sealed with chipseal or harder wearing asphaltic concrete surfacing to match the existing<br />

surfacing.<br />

5 Geotechnical Assessment<br />

5.1 Geotechnical Appraisal<br />

A preliminary geotechnical appraisal of the site was completed in 23 August 2009 <strong>and</strong> is<br />

presented in Appendix D. This appraisal primarily examined the seismic risk of the site <strong>and</strong><br />

the potential slope instability along access roads <strong>and</strong> at turbine locations. Seismic risk <strong>and</strong><br />

potential instability are discussed below.<br />

5.2 Geotechnical Risk<br />

5.2.1 Potential Slope Instability<br />

Slopes observed in the preliminary geotechnical appraisal visits were considered to be<br />

stable. The site reconnaissance did not identify any areas of deep-seated instability in the<br />

areas proposed for use as access roads or turbine sites. Shallow seated slides (up to 1.0m<br />

deep) <strong>and</strong> creep-type failures within the overburden material on slopes were observed at<br />

localised areas throughout the site but restricted to slopes over 28 degrees. Turbine sites<br />

<strong>and</strong> access roads are setback from steep slopes, generally located on ridge tops (where<br />

the overburden is relatively thin). <strong>Construction</strong> activities will be outside the areas of shallow<br />

seated slides <strong>and</strong> creep-type failures <strong>and</strong> therefore unlikely to be affected by any slope<br />

instability.<br />

Where road cuttings are close to, or down slope of turbine foundations, roads are<br />

positioned so that cuttings are adequately set back from the base of the foundations. This<br />

is to reduce the risk of undermining turbine foundations. Access routes have been chosen<br />

to follow existing tracks, ridge lines <strong>and</strong> to generally avoid steep slopes (slopes equal to, or<br />

greater than 28 degrees in the project area) to minimise the potential for creating instability<br />

due to slope undercutting. Avoiding areas with steep side slopes also serves to minimise<br />

the height of cuts, <strong>and</strong> therefore maximise stability. Drawing Sheet 10 in Appendix A<br />

(Appendix A.2 Access Road Plans & Cross Sections) shows the typical cross slopes along<br />

each road length. In addition, Figure 4 in Appendix D demonstrates that all turbine<br />

platforms <strong>and</strong> the vast majority of all access roads avoid slopes equal to, or greater than 28<br />

degrees. However any access roads which run through these areas will typically be<br />

5C-1604.02<br />

February 2011 46


<strong>Project</strong> <strong>Hurunui</strong> <strong>Wind</strong> <strong>Construction</strong> Effects <strong>and</strong> Management Report<br />

assigned an acceptable risk profile of “low” at the detailed design stage <strong>and</strong> special<br />

measures taken to reduce the risk of instability. Therefore the construction effects of this<br />

project on shallow seated instability will be no more than minor.<br />

Siting the turbine foundations will involve detailed geotechnical investigation of each<br />

platform to refine each turbine’s position <strong>and</strong> setback from any adjacent slopes. Such siting<br />

will ensure there is a very low risk for any natural slope instability to undermine a turbine<br />

foundation. For road cuttings geotechnical investigation will ensure global stability of<br />

cuttings through appropriate batter design. Some small localised material loss from the<br />

face can be tolerated given the low accessibility of the roads beyond the construction<br />

period.<br />

Existing farm access tracks were typically at grade, with some generally low height (1.0 –<br />

1.5 m) cuts. In general the low height cuts st<strong>and</strong> at close to vertical. Deeper existing road<br />

cuts range in height between approximately 3.0m to 4.5m high at slope angles<br />

approximately 63 degrees (1H:2V). The bedrock was observed to be stable at these slope<br />

angles up to heights of about 8m. No obvious rock failures were observed in existing cuts.<br />

Photograph 6 in Appendix B shows a cut slope on an existing track ranging up to<br />

approximately 4m to 5m cut height.<br />

In view of such observations of the site, the process proposed, <strong>and</strong> based on knowledge of<br />

proposed road <strong>and</strong> turbine positioning, the risk of l<strong>and</strong>slides, or large scale soil movement<br />

being mobilised by the proposed works is considered low. This preliminary assessment of<br />

slope failure risk is also affirmed by the generally shallow depth of surficial soils overlying<br />

the more stable (barring bedding planes) bedrock. Final cut batter angles, or requirements<br />

for benching will be adjusted as necessary during detailed design to suit any geotechnical<br />

recommendations.<br />

Local bearing capacity can affect the feasibility of turbine sites in some situations. Since<br />

these turbines are typically located on ridge tops where the bedrock is relatively shallow,<br />

bearing capacity of the soil/rock is unlikely to constrain turbine positioning.<br />

Detailed geotechnical investigations at the detail design stage <strong>and</strong> on-site assessment<br />

during construction will be undertaken to confirm the above preliminary conclusions <strong>and</strong> to<br />

establish appropriate cut slopes around the road network. We recognise that some<br />

ongoing maintenance of steeper cut slopes may be necessary during the life of the wind<br />

farm.<br />

5.2.2 Seismic Hazard<br />

With reference to the preliminary geotechnical appraisal in Appendix D, the seismicity of the<br />

site is governed by the presence of the following faults:<br />

• Omihi Fault (borders the northwest of the site)<br />

• Kaiwara Fault (5 km to the north of the site)<br />

• <strong>Hurunui</strong> Bluff Fault (15 km to the northwest of the site)<br />

5C-1604.02<br />

February 2011 47


<strong>Project</strong> <strong>Hurunui</strong> <strong>Wind</strong> <strong>Construction</strong> Effects <strong>and</strong> Management Report<br />

• Hope Fault (45 km to the north of the site)<br />

• The southern Alpine Fault (95 km northwest of the site)<br />

• Pegasus Bay Fault (an offshore fault, which lies approximately 30km to the<br />

southeast of the site)<br />

Other minor faults are mapped within the wind farm area, some of which may be active.<br />

Fault Rupture<br />

Based on geological evidence, the recurrence interval for the Omihi <strong>and</strong> Kaiwara Fault is<br />

2000 to 5000 years, having last ruptured more than 10,000 years ago. The southern Alpine<br />

Fault has a recurrence interval of 500 years <strong>and</strong> evidence suggests it last ruptured between<br />

340 <strong>and</strong> 410 years ago. The Hope Fault is considered to have the shortest recurrence<br />

interval of 120 years, with the last rupture 121 years ago. Records of the Hope fault<br />

earthquake indicate magnitudes greater than 7.<br />

An interim guideline to assist resource management planners in New Zeal<strong>and</strong> “Planning for<br />

Development of L<strong>and</strong> on or Close to Active Faults”, Ministry for the Environment, 2003<br />

defines the fault avoidance zone as a zone that extends 20m on either side of the active<br />

fault line, shown on a plan as an active fault trace. The guideline requires that structures<br />

with special post disaster functions (Building Importance Category 4 structures) are not built<br />

in the fault avoidance zone. For this project, all turbines will be located at distances<br />

substantially larger than 20m from active faults <strong>and</strong> therefore are not expected to be<br />

adversely affected by rupture of the known faults. In addition to separation from fault<br />

zones, wind loading <strong>and</strong> operational fatigue dominate the foundation design for the<br />

turbines. Therefore, the risk of damage to wind turbines associated with fault rupture is<br />

assessed to be low. Roads <strong>and</strong> cables crossing the fault rupture zones would be affected,<br />

but these can be readily repaired <strong>and</strong> reinstated following such an event.<br />

Ground Shaking<br />

<strong>Wind</strong> turbines are designed to withst<strong>and</strong> the large wind forces imposed by extreme wind<br />

storms that may occur during the life of the turbines. Therefore the turbines have a large<br />

reserve of strength available to resist the forces imposed by earthquake ground shaking,<br />

including shaking resulting from rupture of any of the faults listed above.<br />

Liquefaction<br />

There is no possibility that the ground beneath the turbine foundations will liquefy under<br />

earthquake as they will be founded on rock.<br />

Earthquake Induced Slope Failures<br />

Earthquake-induced failures (in the form of debris flow <strong>and</strong> slips) can be expected in the<br />

weaker overburden materials, but such failures would not affect the wind turbine<br />

foundations, as all the wind turbines will be founded on the bedrock, or set back from slope<br />

edges.<br />

5C-1604.02<br />

February 2011 48


<strong>Project</strong> <strong>Hurunui</strong> <strong>Wind</strong> <strong>Construction</strong> Effects <strong>and</strong> Management Report<br />

6 Other Proposed Activities<br />

6.1 Detailed Geotechnical Investigations<br />

As part of the detailed design investigations there will be a need to undertake more<br />

comprehensive site investigations <strong>and</strong> testing to determine site specific geotechnical design<br />

parameters for road <strong>and</strong> turbine platforms as well as turbine foundations. Types of intrusive<br />

testing that are likely to be employed include:<br />

• Trial pits <strong>and</strong> borehole investigations in the vicinity of potential borrow areas, large<br />

cuts, embankments, the substation location <strong>and</strong> at turbine sites.<br />

• Borehole <strong>and</strong> possible rock anchor pullout tests to confirm detail design<br />

assumptions for turbine foundations.<br />

• Trial pits to test the suitability of material for thermal bedding / backfill for<br />

transmission cables<br />

6.2 Controlled Blasting<br />

Based on visual inspection of the site, together with the preliminary geotechnical appraisal,<br />

excavation is most likely to be achieved by the use of hydraulic excavators, large bulldozers<br />

with ripping attachments, <strong>and</strong> motor scrapers.<br />

In the event that harder material (particularly moderately/slightly weathered or intact rock) is<br />

encountered it may be necessary to utilise controlled blasting operations to achieve<br />

economic working rates.<br />

If employed, it is anticipated that small amounts of explosives will be used to break up rock<br />

masses into more manageable pieces. Rock drilling to plant the explosives will also be<br />

required. Management measures <strong>and</strong> methodologies for controlled blasting operations will<br />

be documented in the contractor’s management plan in advance of any work commencing.<br />

This will set out management measures, OSH requirements, blast design, methods, site<br />

protocols, storage requirements, warning systems, <strong>and</strong> noise monitoring requirements as<br />

required under current HSNO Regulations.<br />

7 Indicative <strong>Construction</strong> Methodology, Noise <strong>and</strong> Lighting<br />

7.1 Indicative <strong>Construction</strong> Methodology<br />

The project implementation timeframe, based on experience from other wind farm projects<br />

(Te Apiti, White Hill <strong>and</strong> West <strong>Wind</strong>) is likely to be in the order of 18 months depending on<br />

the sequencing adopted <strong>and</strong> weather conditions.<br />

The initial construction priorities are likely to focus on civil earthworks for the key access<br />

route (Northern Access Road), platforms <strong>and</strong> the substation. Following on from the initial<br />

construction phase the construction priorities are likely to focus on turbine foundation<br />

construction <strong>and</strong> erection as well as civil earthworks on the remaining access roads<br />

5C-1604.02<br />

February 2011 49


<strong>Project</strong> <strong>Hurunui</strong> <strong>Wind</strong> <strong>Construction</strong> Effects <strong>and</strong> Management Report<br />

sequenced over the project implementation timeframe. The likely sequence of construction<br />

for the site is:<br />

• Site mobilisation including establishment of temporary site offices, workshops,<br />

stores <strong>and</strong> other facilities.<br />

• Installing erosion & sedimentation control measures.<br />

• Upgrading key access routes to core site.<br />

• Preparing initial fill sites <strong>and</strong> haulage routes. Haulage routes will typically follow the<br />

proposed access routes <strong>and</strong> existing access tracks, as appropriate.<br />

• Excavating <strong>and</strong> forming access roads with any surplus cut material transported,<br />

placed <strong>and</strong> compacted at fill sites.<br />

• Upgrading existing <strong>and</strong> constructing new culverts.<br />

• Preparing lay down areas <strong>and</strong> substation platform.<br />

• Constructing the substation.<br />

• Constructing the overhead transmission line from the substation to existing external<br />

66kV transmission line.<br />

• Constructing cranage <strong>and</strong> turbine platforms.<br />

• Progressive excavation <strong>and</strong> construction of reinforced concrete turbine foundations,<br />

as platforms become available.<br />

• Cut/fill slope <strong>and</strong> fill site rehabilitation (this will be undertaken on a progressive<br />

basis).<br />

• Progressively installing internal transmission network (cables) typically along the line<br />

of formed access roads, or across country as appropriate.<br />

• Progressively delivering turbine towers <strong>and</strong> generators.<br />

• Progressively installing <strong>and</strong> commissioning (turbines <strong>and</strong> substation).<br />

• Removing temporary services <strong>and</strong> site offices, rehabilitating lay down areas <strong>and</strong><br />

general site reinstatement.<br />

Figure 4 below shows an indicative project implementation timeline, with broad construction<br />

activities, over an 18 month period. A more detailed programme will be developed by the<br />

Meridian Implementation Team prior to construction.<br />

5C-1604.02<br />

February 2011 50


<strong>Project</strong> <strong>Hurunui</strong> <strong>Wind</strong> <strong>Construction</strong> Effects <strong>and</strong> Management Report<br />

<strong>Construction</strong> Activity<br />

<strong>Construction</strong> Period (Months)<br />

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18<br />

Site Establishment/Civil Mobilisation<br />

Civil Earthworks/Roading<br />

Concrete Batching<br />

Substation & O/H Transmission<br />

<strong>Construction</strong><br />

Turbine Foundation <strong>Construction</strong> &<br />

Turbine Installation<br />

Turbine Commissioning<br />

Site Rehabilitation<br />

End <strong>Project</strong><br />

Figure 4: Indicative <strong>Construction</strong> Timeline<br />

7.2 <strong>Construction</strong> Noise<br />

Typical plant likely to be employed for the construction work may include:<br />

• Hydraulic excavators.<br />

• Scrapers <strong>and</strong> dumpers.<br />

• Bulldozers (with ripping attachments).<br />

• Mobile crushers for processing basecourse.<br />

• Main <strong>and</strong> assistant turbine erection cranes Graders <strong>and</strong> rollers.<br />

• On-site batching plant with concrete mixer trucks.<br />

• Portable generators.<br />

• Drilling rigs for detailed geotechnical investigations, possible installation of rock<br />

anchors <strong>and</strong> testing.<br />

<strong>Construction</strong> noise may also result from blasting if employed.<br />

<strong>Construction</strong> works will require a noise management plan in accordance with NZS<br />

6803:1999 to manage noise emissions from construction activities involving the above<br />

types of plant <strong>and</strong> activities. Potential noise impacts are assessed <strong>and</strong> discussed in the<br />

<strong>Project</strong> <strong>Hurunui</strong> Acoustic Assessment report by URS.<br />

7.3 Lighting <strong>and</strong> Night Works<br />

Certain works may take place at night (outside regular working hours). In this respect, it is<br />

envisaged that work may progress on a 24 hour basis for turbine sites <strong>and</strong> access roads<br />

remote from any dwellings while complying with the recommended noise limits at any<br />

neighbouring dwellings.<br />

Where works after sunset or night works are permissible, portable lighting rigs will be<br />

employed.<br />

5C-1604.02<br />

February 2011 51


<strong>Project</strong> <strong>Hurunui</strong> <strong>Wind</strong> <strong>Construction</strong> Effects <strong>and</strong> Management Report<br />

7.4 On Site <strong>Project</strong> Office<br />

The location of the main project site office including stores <strong>and</strong> initial lay down area is<br />

proposed in the front paddock of the Batchelor/Daly property adjacent to the initial section<br />

of the Northern Access Road. The layout of any other temporary site offices, workshops,<br />

stores <strong>and</strong> other construction facilities, such as the concrete batching plant, will be<br />

determined following further detailed investigations of the construction <strong>and</strong> installation<br />

strategy.<br />

One security gatehouse will be located just in from the Northern Access Road, off Motunau<br />

Beach Road, to control access in <strong>and</strong> out of the site.<br />

An indicative main site office layout is shown on Drawing Sheet 203 in Appendix A<br />

(Appendix A.8 Indicative Site Office & Lay-down Area Plan). This drawing shows the<br />

indicative dimensions <strong>and</strong> layout of the proposed structures which make up the temporary<br />

site office facilities. In general the site office structures will comprise single storey s<strong>and</strong>wich<br />

panel prefabricated structures with a combined area of approximately 380m 2 . These<br />

structures are typically 2.8m high (not including the footings) <strong>and</strong> come in two st<strong>and</strong>ard<br />

colours, green <strong>and</strong> white. Allowance has been made for a communication mast<br />

(approximately 6m high), diesel generator <strong>and</strong> diesel fuel tank. The diesel generator <strong>and</strong><br />

fuel tank will be located in a bunded area to retain any fuel leakage. Sewerage <strong>and</strong> waste<br />

water will be directed to a holding tank <strong>and</strong> removed off site. At completion of the<br />

construction phase these temporary buildings will be removed off site.<br />

7.5 Bulk Fuel Storage Facility<br />

A bulk storage facility will be located at or near the site offices or close to the active<br />

construction area. The bulk storage facility will provide fuel to specialist mini tankers that<br />

will service all vehicles on site. In special circumstances where mini tanker access is not<br />

possible, a towable tanker will be used to service the vehicles. This facility is discussed in<br />

more detail in the EMP in Appendix E of this report.<br />

7.6 On Site Batching Plant<br />

The contractor will require a concrete batching plant to minimise the number of truck trips<br />

on the public road network <strong>and</strong> increase efficiency. Photograph F25 in Appendix F shows<br />

the concrete batching plant established at <strong>Project</strong> West <strong>Wind</strong>. This photograph illustrates<br />

an indicative layout <strong>and</strong> the structures which comprise a typical concrete batching plant<br />

proposed for this project.<br />

The likely structures <strong>and</strong> facilities which comprise a typical concrete batching plant<br />

including indicative dimensions are:<br />

• Control room <strong>and</strong> storage building (6m long, 2.8m high, 2.4m wide).<br />

• Prefabricated office <strong>and</strong> amenities structure (4.8m long, 2.8m high, 3m wide).<br />

• Mobile batching plant unit which includes, but is not limited to, hoppers, aggregate<br />

storage bins, compressor, cement silos <strong>and</strong> conveyors (18m long, 4m wide, 7m high<br />

(highest point)).<br />

5C-1604.02<br />

February 2011 52


<strong>Project</strong> <strong>Hurunui</strong> <strong>Wind</strong> <strong>Construction</strong> Effects <strong>and</strong> Management Report<br />

• Water tank.<br />

• Aggregate stockpile area (50m x 20m).<br />

• Truck washdown area.<br />

A concrete batching plant occupies a relatively small area for a relatively short duration<br />

(approximately 5 months) of the construction period as the plant is only on site during the<br />

foundation construction stage of the construction programme. The concrete batching<br />

process proposed under this application is a dry batching process which involves mixing<br />

dry materials in the batching plant. The dry material is then transferred into a normal<br />

concrete mixing truck <strong>and</strong> only then is water added. Minor dust discharges potentially arise<br />

from the transfer of materials into the plant <strong>and</strong> again, into the mixing truck. It is envisaged<br />

that measures to contain any dust will be outlined in the EMP or relevant SEMP. Such<br />

measures are likely to include cement storage within a silo <strong>and</strong> aggregate storage bins.<br />

Given that the concrete is mixed in the truck, rather than in the batching plant, the wash<br />

down requirements associated with conventional concrete batching plants are significantly<br />

reduced. The dry batching process ensures that there are no requirements to wash down<br />

wet concrete within the batching plant. Measures to contain any dry cement spillage in the<br />

event of a batching plant failure will be outlined in the EMP or relevant SEMP. Such<br />

measures are likely to include a temporary concrete slab beneath the loading area <strong>and</strong><br />

containment bunding around the plant incorporating a 2 stage settling pond or sediment<br />

control pond. The concrete batching plant will not be located within 100m of any<br />

permanent watercourse.<br />

On completion of the works the site office areas <strong>and</strong> batching plant areas will be stripped of<br />

any basecourse, re-topsoiled (with material which has been removed <strong>and</strong> stockpiled) <strong>and</strong><br />

ground cover replanted as appropriate.<br />

8 Summary <strong>and</strong> Conclusions<br />

<strong>Construction</strong> of the civil works elements for <strong>Project</strong> <strong>Hurunui</strong> <strong>Wind</strong> will require excavation; fill<br />

site creation; potential on-site extraction; potential crushing <strong>and</strong> processing of basecourse<br />

pavement materials; construction of culverts; substation <strong>and</strong> transmission line construction;<br />

internal site cable trenching <strong>and</strong> placement; concreting works <strong>and</strong> site regeneration.<br />

The key measure we have proposed to minimise the overall environmental effect of<br />

construction is to adopt the general design philosophy of following existing tracks <strong>and</strong> tops<br />

of ridges wherever possible. Following this general design philosophy will typically<br />

• Minimise the volume of excavation.<br />

• Avoid gullies & undisturbed watercourses.<br />

• Improve geotechnical aspects.<br />

5C-1604.02<br />

February 2011 53


<strong>Project</strong> <strong>Hurunui</strong> <strong>Wind</strong> <strong>Construction</strong> Effects <strong>and</strong> Management Report<br />

This report has demonstrated that potential effects within the site resulting from<br />

construction activities typically include:<br />

• Site stability issues.<br />

• Discharges to l<strong>and</strong> <strong>and</strong> water from sediment run-off.<br />

• Stormwater discharges.<br />

• Flooding within the catchments affected by road embankments incorporating<br />

culverts.<br />

• Visual effects.<br />

• Local traffic effects.<br />

• Dust & noise nuisance.<br />

The potential effects <strong>and</strong> measures proposed to avoid, remedy or mitigate these effects are<br />

summarised as follows:<br />

Potential Effects<br />

L<strong>and</strong> disturbance<br />

at the recently<br />

covenanted QEII<br />

within the Turnbull<br />

property <strong>and</strong> the<br />

totara forest<br />

remnant within the<br />

Batchelor/Daly<br />

property<br />

Site Stability of<br />

Roads, Turbine<br />

Platforms,<br />

Substation,<br />

Transmission <strong>and</strong><br />

Met Masts<br />

Site Stability of<br />

Disposal Fill Sites<br />

Measures to Avoid, Remedy<br />

or Mitigate Effects<br />

Avoid construction works within<br />

these areas.<br />

Avoid large slips <strong>and</strong> steep<br />

slopes.<br />

Avoid sidling fill situations on<br />

steep cross slopes.<br />

Avoid access roads undercutting<br />

turbine platforms.<br />

Ensure detailed geotechnical<br />

investigations are carried out at<br />

detailed design.<br />

Avoid steep areas.<br />

Select sites to suit depressions,<br />

Comments<br />

These two areas are recognised as having<br />

significant natural features. However these<br />

areas are outside the construction<br />

footprint.<br />

Natural slopes <strong>and</strong> existing cuttings in the<br />

project area are generally observed to be<br />

stable. In this respect the risk of<br />

l<strong>and</strong>slides or large scale soil movement is<br />

considered low.<br />

Damp (soft) ground is not expected to be<br />

an issue as turbines <strong>and</strong> roads have been<br />

placed to avoid these areas.<br />

Road, Turbine & Substation Platforms<br />

Typical cut slopes to form roads <strong>and</strong><br />

platforms are not typically expected to<br />

exceed 6m in height. Extreme cut heights<br />

of between 6m <strong>and</strong> 18m account only for<br />

approximately 7% of the total road length<br />

5C-1604.02<br />

February 2011 54


<strong>Project</strong> <strong>Hurunui</strong> <strong>Wind</strong> <strong>Construction</strong> Effects <strong>and</strong> Management Report<br />

or tops of natural gentle sided<br />

small or shallow valleys with<br />

good containment.<br />

Key <strong>and</strong> compact fill into<br />

surrounding l<strong>and</strong>.<br />

Install subsoil drainage.<br />

in the core site area (24km). Based on<br />

materials observed on site, cut slopes of<br />

1H:4V are expected to be stable up to<br />

1.5m in height <strong>and</strong> cut slopes of 1H:2V are<br />

expected to be stable up to 5m in height<br />

<strong>and</strong> stable beyond this provided benching<br />

is employed at 5m intervals.<br />

Further geotechnical investigation <strong>and</strong><br />

observation will be completed during<br />

detailed design to confirm design<br />

parameters.<br />

Site Stability –<br />

Seismic Risk<br />

Locate wind farm site away from<br />

major active faults.<br />

Disposal Fill Sites<br />

Fill site selection <strong>and</strong> design will follow a<br />

structured approach, as suggested in this<br />

report <strong>and</strong> will take place under the<br />

framework of the Environmental<br />

Management Plan (EMP) <strong>and</strong><br />

Supplementary<br />

Environmental<br />

Management Plan (SEMPs). There is<br />

sufficient fill site capacity to accommodate<br />

the pessimistic earthworks cut volume.<br />

Overhead Transmission to 66kV Main<br />

The construction effects of the connection<br />

to the 66kV Mainpower Line on<br />

undisturbed l<strong>and</strong> are expected to be minor<br />

<strong>and</strong> will remain within proposed<br />

transmission line construction envelope.<br />

Internal 33/22 kV cable reticulation<br />

Apart from one overhead section all<br />

33/22kV cables are expected to be<br />

installed under the access roads. As<br />

trenching works are typically undertaken<br />

within the road corridor, underground<br />

cabling is not expected to cause any<br />

additional l<strong>and</strong> disturbance.<br />

Given the active faults are outside the<br />

wind farm area, no structural or foundation<br />

failure is expected in relation to rupture of<br />

any of the faults<br />

Discharges<br />

L<strong>and</strong> & Water<br />

to<br />

Staged construction.<br />

Revegetation <strong>and</strong> site<br />

A layer of basecourse will be provided to<br />

roads <strong>and</strong> platforms during construction.<br />

At steeper road sections, a sealed<br />

5C-1604.02<br />

February 2011 55


<strong>Project</strong> <strong>Hurunui</strong> <strong>Wind</strong> <strong>Construction</strong> Effects <strong>and</strong> Management Report<br />

rehabilitation throughout the<br />

construction phase.<br />

Environmental Management<br />

Plans to control erosion <strong>and</strong><br />

treat sediment run-off.<br />

pavement may be provided. This will<br />

provide a clean running/working surface<br />

as well as minimise erosion.<br />

Turbine platforms will be rehabilitated upto<br />

the edge of basecourse hardst<strong>and</strong> areas<br />

with appropriate ground cover after<br />

construction.<br />

Sediment Run-off<br />

Discharges to the<br />

Cave <strong>and</strong> Motunau<br />

Catchment Areas<br />

Avoid where possible by<br />

redirecting works <strong>and</strong>/or<br />

discharges from sediment<br />

control structures to northern<br />

(including Tipapa) catchments<br />

assessed as having lower<br />

comparable ecological values.<br />

Ensure specific erosion <strong>and</strong><br />

sediment controls at fill site just<br />

north of Turbine D5, in particular<br />

Some potential fill areas <strong>and</strong> lay down<br />

areas will involve the removal of existing<br />

topsoil <strong>and</strong> vegetation. The measures<br />

outlined in this report will ensure that these<br />

fill sites <strong>and</strong> lay down areas are blended<br />

back into the existing environment<br />

following their rehabilitation.<br />

In the likely event that an on-site batching<br />

plant is deployed, an SEMP will be<br />

developed to outline measures to manage<br />

any dust, sediment, cement <strong>and</strong> wash<br />

water discharges. Such measures are<br />

likely to include cement storage within a<br />

silo, aggregate storage bins, a temporary<br />

concrete slab beneath the loading area<br />

<strong>and</strong> containment bunding around the<br />

plant.<br />

Appropriate substation design such as<br />

bunding <strong>and</strong> interceptor tanks will ensure,<br />

in the unlikely event of transformer oil<br />

spillage, that the risk of oil discharge is<br />

low.<br />

Sewerage <strong>and</strong> waste water from the<br />

services building will be directed to a<br />

septic tank. Flows are expected to be low.<br />

In areas where the construction works<br />

border catchments, road alignments <strong>and</strong><br />

fill sites can be adjusted to remain within<br />

catchments with lower comparable<br />

ecological values.<br />

The draft SEMP details specific measures<br />

at this area.<br />

5C-1604.02<br />

February 2011 56


<strong>Project</strong> <strong>Hurunui</strong> <strong>Wind</strong> <strong>Construction</strong> Effects <strong>and</strong> Management Report<br />

Flooding<br />

Catchments<br />

Affected<br />

Culverts<br />

Within<br />

by<br />

where run-off is directed within<br />

the Motunau Upper catchment.<br />

Provide for overflows.<br />

Select road alignments which<br />

minimize catchment areas.<br />

Stormwater<br />

Discharges From<br />

Roads <strong>and</strong> Turbine<br />

Platforms<br />

Visual Effects of<br />

Roads, Disposal<br />

Fill Sites &<br />

Substation<br />

Provide permanent stormwater<br />

runoff management.<br />

Provide unlined open side<br />

drains, sumps, culverts &<br />

flumes.<br />

Direct discharges to l<strong>and</strong> or<br />

adjacent undisturbed areas.<br />

Retain runoff within each<br />

existing natural catchment area.<br />

Select fill sites in areas “internal”<br />

to the site.<br />

Select substation site in low<br />

lying areas internal to the site.<br />

Utilise internal access roads <strong>and</strong><br />

farm tracks as much as<br />

possible.<br />

Select alignments of new roads<br />

<strong>and</strong> platforms to be visible<br />

internal to the site as much as<br />

possible.<br />

Appropriate roadside drainage design<br />

employing measures such as fluming <strong>and</strong><br />

riprap will reduce the risk of scouring <strong>and</strong><br />

erosion. Roadside drains will generally<br />

discharge on to l<strong>and</strong>. However, roadside<br />

drains may discharge into existing streams<br />

(ephemeral or otherwise) if located<br />

nearby.<br />

Measures as described in this report to<br />

mitigate stormwater run-off from turbine<br />

platforms, fill sites <strong>and</strong> lay down areas will<br />

ensure that natural drainage paths are<br />

maintained <strong>and</strong> erosion minimised. As<br />

platforms will be graded to the fall of the<br />

l<strong>and</strong>, runoff will generally discharge<br />

directly into undisturbed l<strong>and</strong>.<br />

As most new roads are close to or on<br />

ridge tops, new roads generally do not<br />

cross any streams or dam gullies. Where<br />

natural flow paths are affected by new<br />

roads, appropriate cross culverts will be<br />

provided to ensure that drainage paths are<br />

maintained.<br />

Some potential fill areas <strong>and</strong> lay down<br />

areas will involve the removal of existing<br />

topsoil <strong>and</strong> vegetation. The measures<br />

outlined in this report will ensure that these<br />

fill sites <strong>and</strong> lay down areas are blended<br />

back into the existing environment<br />

following their rehabilitation.<br />

5C-1604.02<br />

February 2011 57


<strong>Project</strong> <strong>Hurunui</strong> <strong>Wind</strong> <strong>Construction</strong> Effects <strong>and</strong> Management Report<br />

Avoid rocky outcrops, significant<br />

natural features <strong>and</strong> areas of<br />

higher ecological value<br />

Local Traffic<br />

Effects of<br />

<strong>Construction</strong><br />

Works<br />

Reduce truck trips by exploring<br />

potential to source on site<br />

materials for roading<br />

basecourse.<br />

Reduce truck trips by utilising on<br />

site concrete batching plant.<br />

Dust & Noise<br />

Nuisance<br />

Adopt environmental control<br />

measures under the framework<br />

of the Environmental<br />

Management Plan (EMP) <strong>and</strong><br />

Supplementary Environmental<br />

Management Plans (SEMPs).<br />

Appropriate requirements will be<br />

incorporated into the construction works<br />

documents to manage noise emissions<br />

from construction activities, including, but<br />

not limited to, preparation of a noise<br />

management plan in accordance with NZS<br />

6803:1999 to manage emissions from<br />

construction activities.<br />

We recognise that works to create <strong>Project</strong> <strong>Hurunui</strong> <strong>Wind</strong> will result in visible cuttings, soil<br />

disturbance, vegetation clearance as well as associated discharges to l<strong>and</strong> <strong>and</strong> water.<br />

However, most of the construction effects are short term as opposed to long term, <strong>and</strong><br />

potentially adverse effects resulting from such construction effects can be mitigated by the<br />

approach to design/construction <strong>and</strong> application of measures identified in this report.<br />

.<br />

5C-1604.02<br />

February 2011 58

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!