29.03.2015 Views

Project Hurunui Wind Construction and Project Overview

Project Hurunui Wind Construction and Project Overview

Project Hurunui Wind Construction and Project Overview

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

<strong>Project</strong> <strong>Hurunui</strong> <strong>Wind</strong> <strong>Construction</strong> Effects <strong>and</strong> Management Report<br />

Concrete<br />

Component<br />

Estimated Dem<strong>and</strong><br />

(Turbine<br />

Foundations)<br />

Estimated<br />

Dem<strong>and</strong> Per<br />

Pour (Same<br />

Day)<br />

Approximate<br />

Indication of Average<br />

Dem<strong>and</strong><br />

Cement 3,200 tonnes 94 tonnes 3 x 23 tonne bulk<br />

carriers per day<br />

S<strong>and</strong> <strong>and</strong><br />

Aggregate<br />

27,000 tonnes 800 tonnes 13 x 23 tonne trucks<br />

per day<br />

Water 2.4 million litres 72,000 7 tankers (10,000 litre<br />

capacity) per day<br />

Table 11: Indicative Batching Plant Dem<strong>and</strong> on Materials<br />

We envisage that measures to contain any dust, spillage <strong>and</strong> wash down of plant or trucks<br />

will be outlined in the contractor’s management plan. Such measures are likely to include<br />

cement storage within a silo, aggregate storage bins, a temporary concrete slab beneath<br />

the loading area <strong>and</strong> containment bunding around the plant.<br />

3.2.7 Borrow Areas<br />

Basecourse material may be sourced within the project area from excavations for the<br />

access roads, working platforms <strong>and</strong> foundations wherever practicable. Basecourse<br />

material may also be sourced from borrow areas within the site. However, an appraisal on<br />

the availability of suitable material on-site for processing roading <strong>and</strong> platform basecourse<br />

would be undertaken at the detailed design phase to determine whether suitable material is<br />

available on site.<br />

In the event that locally won materials will be suitable for road construction, borrow areas<br />

would be established at locations within the site which meet the same criteria established<br />

for fill sites (outlined in Section 2.4). Extracted materials will be stockpiled at localised<br />

processing areas where a mobile crushing plant will be used to produce the required grade<br />

of basecourse material. Material may also be extracted from these borrow areas for<br />

roading fill where there is a shortfall of suitable material excavated from road construction.<br />

The total pessimistic volume of basecourse required for roads, turbine platforms <strong>and</strong><br />

laydown areas is approximately 41,000m 3 . Assuming this involves approximately 90% of<br />

the equivalent volume in overburden to extract this material <strong>and</strong> an average borrow site<br />

depth of approximately 3m the following construction footprint expected is approximately<br />

25,000m 2 . These details are summarised in Table 12 below.<br />

Total Volume of<br />

Basecourse (m 3 )<br />

Equivalent Volume<br />

of Overburden (m 3 )<br />

Total Combined<br />

Volume (m 3 )<br />

<strong>Construction</strong><br />

Footprint (m 2 )<br />

41,000 35,000 76,000 25,000<br />

5C-1604.02<br />

February 2011 32

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!