<strong>Project</strong> <strong>Hurunui</strong> <strong>Wind</strong> <strong>Construction</strong> Effects <strong>and</strong> Management Report<br />

that platform areas around the basecourse hardst<strong>and</strong> areas are backfilled with top soil with<br />

a slight cross fall, <strong>and</strong> regrassed to avoid erosion.<br />

Drainage provision may be provided to the foundation excavation by way of a trench or filter<br />

drain with suitable stabilised outlet.<br />

Fill sites <strong>and</strong> lay down areas<br />

The proposed treatment for fill sites is discussed in Section 2.4. Finished ground profiles<br />

will be shaped to ensure that natural drainage paths are maintained. On completion of<br />

construction, these sites will be re-topsoiled (with material which has been removed <strong>and</strong><br />

stockpiled) <strong>and</strong> re-vegetated as appropriate with runoff direct onto grassed l<strong>and</strong> on<br />

surrounding catchments.<br />

Lay down areas will have a general crossfall, allowing stormwater run off in the direction of<br />

the general slope of the l<strong>and</strong>. Sedimentation <strong>and</strong> erosion control measures as described in<br />

Section 3.3.1 above will be applied. On completion of construction, lay down areas will be<br />

rehabilitated in the same manner as fill sites.<br />

3.3.3 New Culverts at Stream or Gully Crossings in the Core Site<br />

No stream crossings have been identified within the core site however there are locations<br />

where upper gully crossings <strong>and</strong> existing open channel drain crossings will require culverts.<br />

Table 15 below summarises the proposed culverts identified along core site access roads.<br />

Culvert sizes have been based on flows for flood return periods of 20 years with provision<br />

for secondary flow paths across purposely lowered sections of the access road (for<br />

overtopping for longer return periods).<br />

We envisage no gully crossings in addition to those tabulated given the layout of the access<br />

roads are generally close to or on ridge tops where the terrain is relatively gentle. However,<br />

where new culverts are required per the detailed design (consequent to adjusting the<br />

turbine platforms <strong>and</strong> access roads within a 100m radius placement area), culverts will be<br />

sized as described above.<br />

The approximate height of the embankment at the culvert inlet of the majority of all culverts<br />

is less than 1m apart from one culvert on Road D which has an embankment height of<br />

approximately 1.5m at the culvert inlet. Given the embankment heights at culvert inlets are<br />

not significant no locations have been identified where an embankment fill could essentially<br />

form a ‘dam’ across upper valleys. However, if a significant embankment fill arises<br />

consequent to adjusting the turbine platforms <strong>and</strong> access roads (within a 100m radius<br />

placement area) the culvert will be sized on flows for flood return periods of 100 years to<br />

address the effects of ‘heading up’ associated with culverts with significant embankment<br />

fills.<br />

Based on this design criteria, the required culvert sizes are indicated in the following table.<br />

The final size of the culvert, where required, will be determined during the detailed design<br />

stage. This table also identifies a range of characteristics associated with each culvert.<br />