L35 Series<br />
<strong>Installation</strong> Guide<br />
Connecting Switch Inputs<br />
The L35 Series Controller comes standard with 24 programmable switch input capacity. The 24 termination points are divided into<br />
three sections of eight, with each section containing one ground point ( all three grounds are common ). All points are numbered,<br />
and ground points are labeled “G”. Do not apply AC voltage to any of the terminals. Switch inputs location and labeling on the L35<br />
Series Controller are shown below.<br />
Figure 8<br />
J5<br />
Ground<br />
J7<br />
Switch inputs 17-24<br />
J6<br />
Ground<br />
Switch inputs<br />
1-8<br />
Switch inputs<br />
9-16<br />
Ground<br />
The inputs can be momentary on, momentary off, momentary on/off, maintained, linked, or state change. Each section has an<br />
accompanying jumper that sets whether its associated eight inputs will be up to 24 VDC or dry (0 VDC).<br />
Table 1 lists the switch inputs and associated jumpers.<br />
Table 1<br />
Switch Input Section Associated Jumper<br />
1- 8 J6<br />
9-16 J7<br />
17-24 J5<br />