Quality Control Manual Page 1 of 1<br />

<strong>Industrial</strong> <strong>Piping</strong>, <strong>Inc</strong>. Revision 0<br />

8.1.0 GENERAL<br />

SECTION 8<br />

HEAT TREATMENT<br />

(PWHT)<br />

8.1.1 The heat treatment as described in this section shall be adhered to for all shop and field<br />

Code work including all Code repair work.<br />

8.2.0 PROCEDURE<br />

8.2.1 Heat treatment, when required by the Code will be done in accordance with a written<br />

procedure. This written procedure will be approved by the Fabrication Engineer with<br />

the acceptance of the Quality Control Manager and shall be in compliance with the<br />

Code. As a minimum, this procedure will specify heating and cooling rates, time and<br />

temperature, thermocouple method of attachment, location, record, and equipment<br />

calibration requirements.<br />

8.2.2 The QC Mgr will oversee all PWHT operations both internally and externally. This<br />

includes but is not limited to the equipment and controls, procedures and calibration<br />

records.<br />

8.2.3 Records of heat treatment such as strip or dial charts shall reference the <strong>Industrial</strong><br />

<strong>Piping</strong>, <strong>Inc</strong>. Purchase Order, and job order numbers. The job record and/or charts shall<br />

be signed and dated by the operator or other supervision personnel. The<br />

time/temperature charts and any other applicable records will be reviewed, approved<br />

and retained by the Quality Control Manager and made available to the Authorized<br />

Inspector for his review.<br />

8.2.4 A metal identification tag will be attached to the item to be heat treated to identify<br />

materials and parts sent to the subcontractor's facilities. The Quality Control Manager<br />

shall perform a receiving inspection of the heat treated item upon receipt of the item<br />

from the subcontractor.<br />

8.2.5 Any tests required by an applicable Code Section, shall be performed either by<br />

<strong>Industrial</strong> <strong>Piping</strong>, <strong>Inc</strong>., or the subcontractor. Where performed by the subcontractor, the<br />

requirements shall be specified in the written procedure.