(4) The lay-out of the fire fight<strong>in</strong>g po<strong>in</strong>t and its equipment shall take <strong>in</strong>to account the control ofsmoke, <strong>in</strong> particular to protect people who use the self-evacuation facilities to access the safearea.4.2.1.8 Emergency communicationThis specification applies to all <strong>tunnels</strong> of more than 1 km <strong>in</strong> length.(a) Radio communication between the tra<strong>in</strong> and the <strong>in</strong>frastructure manager control centre shall beprovided <strong>in</strong> each tunnel with GSM-R.(b) Radio cont<strong>in</strong>uity shall be provided for permitt<strong>in</strong>g the emergency response services to communicatewith their on-site command facilities. The system shall allow the emergency response services to usetheir own communication equipment.4.2.2. Subsystem EnergyThis section applies to the <strong>in</strong>frastructure part of the subsystem Energy.4.2.2.1. Segmentation of overhead l<strong>in</strong>e or conductor railsThis specification applies to <strong>tunnels</strong> of more than 5 km <strong>in</strong> length.(a) The traction energy supply system <strong>in</strong> <strong>tunnels</strong> shall be divided up <strong>in</strong>to sections, each not exceed<strong>in</strong>g 5km. This specification applies only if the signall<strong>in</strong>g system permits the presence of more than one tra<strong>in</strong> <strong>in</strong>the tunnel on each track simultaneously.(b) The location of the switches shall be arranged so that the number of switches <strong>in</strong> the tunnel ism<strong>in</strong>imised.(c) Remote control and switch<strong>in</strong>g of each ‘switch<strong>in</strong>g section’ shall be provided.(d) A means of communication and light<strong>in</strong>g shall be provided at the switch<strong>in</strong>g location to enable safemanual operation and ma<strong>in</strong>tenance of the switch<strong>in</strong>g equipment.4.2.2.2. Overhead l<strong>in</strong>e or conductor rail earth<strong>in</strong>gThis specification applies to all <strong>tunnels</strong> of more than 1 km length.(a) Earth<strong>in</strong>g devices shall be provided at tunnel access po<strong>in</strong>ts and, if the earth<strong>in</strong>g procedures allow theearth<strong>in</strong>g of a s<strong>in</strong>gle section, close to the separation po<strong>in</strong>ts between sections. These shall be eithermanually or remotely controlled fixed <strong>in</strong>stallations.(b) Communication and light<strong>in</strong>g means necessary for earth<strong>in</strong>g operations shall be provided.(c) Procedures and responsibilities for earth<strong>in</strong>g shall be def<strong>in</strong>ed between the Infrastructure Managerand the emergency response services, based on the emergency scenarios considered with<strong>in</strong> theemergency plan.21