63From this rolled-up GANTT diagram, the following is evident:• Various project elements will have to overlap to a large extent to achieve todemands imposed by the milestones.• As the level of detail and the accuracy of estimates improve, a number ofmilestones and deliverables are required. These internal deliverables andmilestones are not visible on this summarised Gantt.• Even on the rolled-up task levels, the project has many elements and phases,which is an indication of the complexity of the project.1.6 PROJECT MANAGEMENT STRUCTURE1.6.1 IntroductionA project-specific approach is used as basis for the project management andconsultative structure. The project management and consultation principles areshown diagrammatically in Figure 10.Consultation PrincipleCONSULTATIONSTRUCTUREPROJECT MANAGEMENTSTRUCTUREBROADCOMMUNITYTCC &GRPSTEERING COMMITTEEREVIEWCOMMITTEEAd hocconsultation Ad hocconsultationPROJECTCOMMITTEECONSULTANTSFIGURE 10: PROJECT MANAGEMENT & CONSULTATION IN PRINCIPLEThe approach followed in this structure allows for high-level consultation atthe level where the strategic aspects of this study are considered anddecided, namely at the <strong>Gauteng</strong> Provincial Cabinet Cluster level. Moredetailed issues of local concern will be addressed by the Project ReviewCommittee, which will act in the format of a project management committee.<strong>Gauteng</strong> <strong>SDI</strong> <strong>Rail</strong> <strong>Link</strong> – Inception Report, 15 June 2000

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!