Rehabilitation Strategy<br />
• Conduct Sectional Repairs/re-coating<br />
• Complete planned mitigation measures<br />
– Replacement of the depleted ground bed at start of pipeline<br />
– Installment of a rectifier <strong>and</strong> deep well ground bed at 25<br />
miles or recoating of the last 5 miles of the pipeline<br />
– It is noted that if coating disbondment is a particular issue in<br />
this area, then either sectional replacement or recoating of<br />
the pipeline would be required <strong>to</strong> control the corrosion<br />
• Conduct re-inspection in 3 years, this will:<br />
– Ensure any further areas of coating disbondment are<br />
identified<br />
– Enable confirmation of external corrosion growth rates<br />
predicted here<br />
– Confirm the effectiveness of any planned mitigation<br />
measures<br />
– Ultimately assist in reducing the numbers of repairs required<br />
in subsequent years