Project Management - (NARPM) Training Program
Project Management - (NARPM) Training Program
Project Management - (NARPM) Training Program
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
Variance At Completion (VAC) Describes the difference between the totalbudgeted cost of the project and the cost ofthe project at completion Budget at Completion minus Estimate atCompletion VAC = BAC - EAC A Negative number is a budget overrun A Positive number is a budget underrun22 nd Annual <strong>NARPM</strong> <strong>Training</strong> <strong>Program</strong>22 nd Annual <strong>NARPM</strong> <strong>Training</strong> <strong>Program</strong>96