Variance At Completion (VAC) Describes the difference between the totalbudgeted cost of the project and the cost ofthe project at completion Budget at Completion minus Estimate atCompletion VAC = BAC - EAC A Negative number is a budget overrun A Positive number is a budget underrun22 nd Annual <strong>NARPM</strong> <strong>Training</strong> <strong>Program</strong>22 nd Annual <strong>NARPM</strong> <strong>Training</strong> <strong>Program</strong>96