13.07.2015 Views

Power System Reliability Report - RTE

Power System Reliability Report - RTE

Power System Reliability Report - RTE

SHOW MORE
SHOW LESS
  • No tags were found...

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

R-AUDIT-SG-DAR-MAS-11-2011/022010 <strong>Reliability</strong> <strong>Report</strong>Page : 25/408 juillet 2011start of the year and one on December 16th. It is important to support and develop this process in thelong term.More generally, in its “Brittany electricity pact”, <strong>RTE</strong> has favoured distributed load adjustmentexperimentation in the St Brieuc area.In the South-East, <strong>RTE</strong> is participating in different regional energy control experiments (Premio,Reflexe) through which the Var and Alpes-Maritimes departments have been able to analyse theirregional consumption.To increase the availability of industrial consumer withdrawal offers on the MA, and considering thelimited but positive results of contracts signed in 2009 and 2010, <strong>RTE</strong> renewed the contracts for thistype of product at the end of 2010 so that a volume of 110 MW, that may be activated 20 times in2011 and 120 MW, that may be activated 12 times from May 1 st 2011, would be available during tensesituations.For the MA, the volume available from offers made up through the aggregation of withdrawals fromsmall consumers is low, between 10 and 15 MW; these were essentially activated in the last quarter.In order to assess the potential of having adjustment proposals for products that can be activatedrapidly, within a few minutes, which would be completely appropriate to help manage the problemsposed by frequency variations on the hour (see §2.2), for which it was interesting to examine thewithdrawal potentials, <strong>RTE</strong> organised a test tender. 3 one month contracts were granted for 51 MWfor industrial or distributed withdrawals. Feedback, showing the pertinence of the approach, wastaken into account in the technical and financial definition (attribution of a bonus in the interfiling ofresponses to the tender) of the requested products in the context of the tender for "rapid andcomplementary reserves", sent out at the end of 2010 in view of renewing the contract ending in April2011.4.2 Structure of the system and its design rulesIn 2010, <strong>RTE</strong> updated the 2009 provisional supply & demand balance report for electricity in France.Its conclusions were confirmed: the reliability of electricity procurement should be stable until 2013,taking into account production facilities expected to come on line, and the increase in consumptionpeaks during cold spells is a cause for concern.<strong>RTE</strong> has continued the work started in 2009 aiming to revise the network development policy andstudy methods, to adapt them to the context of coming years: new technical solutions, European grid,generation flow pattern, objection to projects, etc. The framework for a multi-criteria analysis must bedefined, to be a credible response to the multi-dimensional problem of assessing possibledevelopment strategies, using as inspiration the theoretical conclusions from the European projectRealisegrid. Work in 2010 led, for example, to a definition of the determining parameter values (costsof loss and undistributed energy, etc.). In parallel to this, a 400kV target grid project has been definedfor 2030, but remains to be detailed in relation to the corresponding work at ENTSO-E level.As concerns decisional studies, the different <strong>RTE</strong> teams concerned are working on bringing togetherboth development and operating methods and tools to further take into account future operationalconstraints in development decisions (operation during planned outages, voltage management,withdrawal PLCs). This can be seen in the introduction of a single study platform (Convergence) andthe gradual setting up of common training programme. However, this progress which is important fornetwork reliability in years to come, is far from complete; in 2010, an analysis of low voltage problemstudy methods was started, but needs to be continued. Similarly, the late identification of the issuesarising from the integration of new current level limits in development studies shows the need tostrengthen coordination.As concerns network development in the coming years, we see that <strong>RTE</strong> has worked in closecollaboration with the government services to identify the constraints that will be created on thetransmission network given the locations considered for off-shore wind power production installationsin the call for tender prepared by the public authorities.Copyright <strong>RTE</strong>. This document is the property of <strong>RTE</strong>. Any communication, reproduction, publication even partial is forbidden without the express written authorisationElectricity Transmission <strong>System</strong> operator (<strong>RTE</strong>)

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!