06 Underground Construction<br />
Tunnels for Roads and<br />
Motorways<br />
Pfänder Tunnel, Second Tube, A14 / Bosruck Tunnel, Second Tube, A9<br />
ABT <strong>is</strong> the main contractor for the construction of the second tubes of the Pfänder and Bosruck<br />
tunnels. Both are 2-lane motorway tunnels. New Austrian <strong>Tunnelling</strong> Method (NATM) <strong>is</strong> used for<br />
the second tube of Bosruck Tunnel and was also used for the construction of the first tube of<br />
Pfänder Tunnel, which ABT built in the years 1977-1981.<br />
Jagdberg Tunnel, A4<br />
After the construction of Heidkopf Tunnel, a twin-tube 2-lane motorway tunnel, completed in<br />
2006, another contract with DEGES followed in the form of the Jagdberg Tunnel. Th<strong>is</strong> 3-lane<br />
motorway tunnel between Jena/Göschwitz and Magdala <strong>is</strong> beeing executed using the NATM<br />
method.<br />
Pfänder Tunnel, Second Tube <strong>is</strong> the first road<br />
tunnel to be built by TBM in Austria.<br />
FEATURES<br />
Pfänder Tunnel, Second Tube // The challenge <strong>is</strong> the ground – a “molasse” cons<strong>is</strong>ting<br />
of conglomerate, sandstone, marl-sandstone, marl and clay-marl, and soil. Execution <strong>is</strong><br />
being carried out by Single Shield TBM, lining with pre-cast concrete segments, crosspassages<br />
and soil by NATM.<br />
Bosruck Tunnel, Second Tube // The construction includes 14 crosspassages and<br />
seven lay-by enlargements. Excavation <strong>is</strong> being effected by drill & blast and excavator<br />
(NATM).<br />
Jagdberg Tunnel // Excavation of a 140 m deep ventilation-shaft by ra<strong>is</strong>eboring<br />
(Ø 1.5 m) and shaft sinking (Ø 8 m).<br />
Pfänder Tunnel, Second Tube<br />
Location: Bregenz-Lochau / AT<br />
Total length: 6,744 m<br />
Value: € 123.197 million<br />
Construction Period: 2007-2012<br />
Bosruck Tunnel, Second Tube<br />
Location: Spittal/Pyhrn-Ardning / AT<br />
Total length: 5,424 m<br />
Value: € 129.628 million<br />
Construction Period: 2009-2013<br />
Jagdberg Tunnel<br />
Location: Jena/Göschwitz-Magdala / DE<br />
Total length: 6,144 m<br />
Value: € 127.072 million<br />
Construction Period: 2008-2012