ČEZ <strong>Distribuce</strong>, a. s.<br />
Information on the Company’s Core Business<br />
Information on the Company’s<br />
Core Business<br />
032<br />
The company’s main mission is to distribute electricity to private individuals and legal entities and to continually improve the<br />
quality and reliability of supplies to all customers. The company administers the assets comprising the distribution grid, the<br />
operation of which it controls through a technical dispatch (grid control center).<br />
In 2<strong>012</strong>, the distribution grid was operated and maintained in compliance with quality standards and the Rules of Preventive<br />
Maintenance. Smooth operation of the distribution grid during the year was negatively impacted by eight extraordinary grid<br />
failures brought about by unfavorable weather conditions. During the failures, 485 extraordinary interruptions in electricity<br />
distribution lasting longer than three minutes and affecting at least one customer occurred. Aside from the extraordinary<br />
failures, technical dispatch recorded 50 faults in the HV system, 7,438 faults in the MV system, and 30,514 faults in the LV system,<br />
all lasting longer than three minutes and affecting at least one customer.<br />
Damaged circuit breakers in customer breaker or cable boxes were replaced in 6,686 cases.<br />
The company monitors and evaluates indicators relating to the quality and reliability of electricity supply and distribution, as<br />
well as other service quality indicators.<br />
Total Duration of Electricity Supply Interruptions Per Customer (minutes)<br />
0 50 100 150 200 250<br />
Total<br />
2011<br />
282.172<br />
2<strong>012</strong><br />
289.955<br />
One of these indicators is SAIDI (System Average Interruption Duration Index), which expresses the total average duration of<br />
electricity supply interruption per customer for the entire year. This figure includes all failures and planned interruptions that<br />
occurred during the year directly in the company’s distribution grid. Outages caused by unfavorable weather conditions are<br />
considered an exception and are not included in the calculation.<br />
www.cezdistribuce.cz