Development projects in the first half of the financial year 1 April <strong>2008</strong> – <strong>30</strong> <strong>Sep</strong>tember <strong>2008</strong><br />

PROPERTIES COMPLETED DURING THE PERIOD UNDER REVIEW – IN PORTFOLIO<br />

City Street Use Area<br />

in m 2<br />

Germany<br />

20 <strong>SEB</strong> ImmoInvest<br />

Transfer of<br />

risks and<br />

rewards of<br />

ownership/<br />

Completion<br />

Construction status Letting rate<br />

Düsseldorf Peter-Müller-Strasse 20 Office 6,073 05/<strong>2008</strong> Completed 100%<br />

Netherlands<br />

Deventer Hunneperkade/Hanzeweg Office 3,051 06/<strong>2008</strong> Completed 100%<br />

Rotterdam George Hintzenweg 77 Office 5,683 08/<strong>2008</strong> Completed 100%<br />

Rotterdam George Hintzenweg 89 Office 12,027 04/<strong>2008</strong> Completed 100%<br />

Zwolle Ceintuurbaan/Dokter van<br />

Finland<br />

Deenweg, Gebäude A<br />

Office 6,662 09/<strong>2008</strong> Completed 100%<br />

Helsinki Opus 1, Hitsaajankatu 24 Office 7,010 06/<strong>2008</strong> Completed 100%<br />

(rental guarantee<br />

2 years)<br />

PROPERTIES UNDER CONSTRUCTION – IN PORTFOLIO<br />

City Street Use Planned<br />

Netherlands<br />

Zwolle Ceintuurbaan/Dokter van<br />

Deenweg, Building B<br />

PROPERTIES UNDER CONSTRUCTION – NOT YET IN PORTFOLIO<br />

area<br />

in m 2<br />

City Street Use Planned<br />

Germany<br />

Scheduled<br />

completion<br />

date<br />

Construction status Letting rate<br />

Office Approx. 6,662 12/<strong>2008</strong> Completed apart from tenant<br />

area<br />

in m 2<br />

Transfer of<br />

risks and<br />

rewards of<br />

ownership/<br />

Scheduled<br />

completion date<br />

fit-outs (approx. 85%)<br />

Frankfurt Werfthaus, Speicherstrasse Office 14,194 11/2009 Shell construction on<br />

100%<br />

(rental guarantee<br />

10 years)<br />

Construction status Letting rate<br />

second storey<br />

Freiburg Schnewlinstrasse Office/retail Approx. 15,400 11/<strong>2008</strong> Tenant fit-outs Approx. 70%<br />

(rental guarantee<br />

3 years)<br />

Hamburg Drehbahn 47–48,<br />

Dammtorwall 7<br />

Office<br />

Phase 1: 7,500<br />

Phase 2: 9,000<br />

to<br />

11,000<br />

Phase 1: 1 Dec. <strong>2008</strong><br />

Phase 2: Mid-2010<br />

Phase 1: Completed.<br />

Phase 2: Revitalisation of property<br />

expected<br />

to begin 11/<strong>2008</strong><br />

100%<br />

100%<br />

(rental guarantee<br />

2 years)<br />

Karlsruhe Haid-und-Neu-Strasse 13 Office 7,352 10/<strong>2008</strong> Completed 100%<br />

(rental guarantee<br />

2 years)<br />

Mannheim Galilei, Galileistrasse 3 Office 15,162 12/<strong>2008</strong> Shell construction completed;<br />

tenant fit-out underway<br />

Approx. <strong>30</strong>%<br />

(rental guarantee<br />

2 years)<br />

Salzgitter Albert-Schweitzer-Strasse 1 Retail 11,420 11/<strong>2008</strong> Completed Over 90%<br />

(rental guarantee<br />

2 years)<br />

Stuttgart Z-UP, Heilbronner Str. 29 Office 14,903 04/2009 Shell construction completed;<br />

Netherlands<br />

tenant fit-out underway<br />

Amsterdam Changiweg Office Approx. 22,000 09/2009 Shell construction on<br />

second storey<br />

Rotterdam Wilhelminakade Office Approx. 38,120 11/2009 Shell construction on<br />

Singapore<br />

eleventh storey<br />

Approx. 70%<br />

(rental guarantee<br />

2 years)<br />

100%<br />

100%<br />

(rental guarantee<br />

10 years)<br />

Singapore Ubi Tech Park Office 38,350 03/2009 Overall completion 85% Approx. 60%