4.3. Prior to abrasive blast cleaning remove all deposits of dirt, oil, grease, or other contaminants in<br />

accordance with SSPC-SP1.<br />

4.4. All immersion-service steel surfaces shall be prepared in accordance with SSPC-SP5, White<br />

Metal Blast Cleaning.<br />

4.4.1. All non-immersion areas can be prepared in accordance with SSPC-SP10, Near White Metal<br />

Blast Cleaning.<br />

4.5. All steel surfaces shall have a surface profile (anchor pattern) of 3 to 4 mils.<br />

4.5.1. Heavily corroded steel, containing grooving or pinholes, shall be opened up and sharp edges<br />

removed through the use of an appropriate mixture of non-metallic, abrasive blast media.<br />

4.5.2. The surface profile (anchor pattern) shall be verified through the use of replica tape in<br />

accordance with ASTM D4417, “Standard Test Methods for Field Measurement of Surface<br />

Profile of Blast Cleaned Steel”.<br />

4.6. All welds must be continuous. Skip or intermittent welds must be made continuous by welding.<br />

4.7. All welds must be clean and free of spatter or sharp projections.<br />

4.8. All welds must be ground to remove sharp edges, undercutting, pinholes or any other<br />

irregularities. Relative smooth, ripple finish welds are acceptable.<br />

4.9. All welds must meet NACE RP0178 Designation “C” as a minimum.<br />

4.10. All lap joints must receive a continuous fillet weld.<br />

4.11. All corners and sharp edges must be ground to a minimum 1/8” radius.<br />

4.12. All inlet and outlet ports must be welded pads or flanges, not threaded.<br />

4.13. All internal bracing or reinforcement with open ends must be capped and seal welded.<br />

4.14. Prior to coating application, all prepared surfaces shall be vacuumed or blown down with clean,<br />

dry compressed air to remove dust, grit, or abrasives.<br />

4.15. Surfaces to be coated shall be tested for soluble salts contamination. Salt contamination levels in<br />

excess of 40 micrograms per square centimeter shall be rejected, and additional cleaning with<br />

steam or fresh water to flush away the soluble salts will be required.<br />

4.16. Simultaneous coating application and abrasive blasting operations shall not be conducted where<br />

possible contamination of the coating can occur.<br />

4.17. If surface preparation is conducted in sections, no coating may be applied within six (6) inches of<br />

the temporary boundary of a cleaned area.<br />

4.18. Abrasive blasted surfaces shall be coated within eight (8) hours maximum and prior to any rust<br />

bloom occurring. No metal shall be coated that exhibits visible rust bloom.<br />

Page 3 of 9<br />

04/10 Irathane 155 Steel