<strong>WBS</strong> NUMBER<br />
L1 L2 L3 L4 L5<br />
<strong>LCLS</strong> <strong>WBS</strong> DICTIONARY - ACTIVE NO's<br />
TITLE DESCRIPTION<br />
2 04 03 05 Focusing Magnets This area contains elements related to construction of the 4 spare<br />
Quadrupole Magnets.<br />
2 04 03 06 Undulator Magnetic Measurement Facility This element covers the OPC for the setup of the MMF at SLAC, the<br />
(SLAC)<br />
magnetic measurements, fiducialization and assembly of the undulator<br />
system components, and the design and construction of the position<br />
monitoring systems<br />
2 04 03 08 Fixed Supports This area contains elements related to construction of the Fixed<br />
Supports.<br />
2 04 04 Vacuum System Total Center for the OPC Spares of the Undulator Vacuum System. This<br />
center includes all vacuum components from the upstream treaty valve<br />
to the downstream treaty valve.<br />
2 04 04 02 Undulator Vacuum Chamber Assembly Total Center for the spare Undulator Vacuum Chamber and supports for<br />
the Undulator System. This element covers the labor and materials for<br />
(7) spare chambers and (4) spare supports. This includes effort for<br />
procurement and receiving of the unit.<br />
2 04 04 03 Beam-line Bellows Module Assembly This element covers the labor and materials for (7) spares. This includes<br />
effort for procurement and receiving of the unit. The (7) spare Bellows<br />
Modules will be used in the Short and Long Diagnostics Breaks along<br />
with the Entrance and Exit Sections.<br />
2 04 04 04 Single Undulator Test(SUV) Vacuum Total cost of Vacuum Components to be used in the Single Undulator<br />
Test including: design, procurement, and quality assurance. This<br />
element includes material and labor charges. These are the temporary<br />
units that be used until actual units are available.<br />
2 04 04 05 Short Diagnostic Break (SDB) Assembly The SDB Assembly is composed of diagnostic devices and vacuum<br />
components that reside in the area of the short breaks between the<br />
undulators. SDB Assembly and related equipment includes the effort<br />
required for procuring the technical equipment including issuing of<br />
purchase requests and billing.<br />
2 04 04 06 Long Diagnostic Break (LDB) Assembly The LDB Assembly is composed of diagnostic devices and vacuum<br />
components that reside in the area of the long breaks between the<br />
undulators. LDB Assembly and related equipment includes the effort<br />
required for procuring the technical equipment including issuing of<br />
purchase requests and billing.<br />
2 04 05 Undulator System Diagnostics [OPC] Total Center for the OPC Spares of the Undulator System<br />
2 04 05 05 RFBPM The RFBPM will be used to precisely measure the position of the<br />
electron beam in all the breaks between the undulators. Total Center for<br />
RFBPM Spares for the Undulator System. This element covers the labor<br />
and materials for (4) spares of the production devices. This includes<br />
effort for procurement and receiving of the units.<br />
2 04 05 06 Beam Finder Wire The Beam Finder Wire will be used to precisely measure the position of<br />
the electron beam in all the breaks between the undulators. Total Center<br />
for Beam Finder Wire Spares for the Undulator System. This element<br />
covers the labor and materials for (4) spares of the production devices.<br />
This includes effort for procurement and receiving of the units.<br />
2 04 05 08 Beam Loss Monitoring This element covers to the spares costs for the beam loss monitor<br />
system installed in the undulator system and used to protect it from<br />
significant radiation doses.<br />
2 04 05 10 SIngle Undulator Test (SUT)-Diagnostics Support single undulator testing.<br />
2 04 06 LTU/Undulator/Dump Commissioning Maintenance support during the commissioning of Undulator systems.<br />
Commissioning begins after installation and ends when commissioning<br />
goals are met and the system is operational.<br />
2 04 06 01 LTU/Undulator/Dump Commissioning Maintenance support during the commissioning of Undulator systems.<br />
Commissioning begins after installation and ends when commissioning<br />
goals are met and the system is operational.<br />
2 05 X-RAY TRANSPORT & DIAGNOSTICS<br />
SYSTEMS (OPC)<br />
OPC Summary for the X-Ray Transport, Optics and Diagnostics System.<br />
It includes effort and costs associated with Spares, and Modeling and<br />
Simulation.<br />
2 05 01 System Management & Integration This summary element covers the management and integration for the X-<br />
Ray Transport system.<br />
2 05 01 01 Management This <strong>WBS</strong> element covers the management of R&D issues associated<br />
with component design and layout at the conceptual level.<br />
9/17/2007 Page 35 of 37 Rev. 0