NAME OF THE WORK:<br />
FORM’C’<br />
RASHTRIYA ISPAT NIGAM LIMITED<br />
VISAKHAPATNAM STEEL PLANT<br />
WORKS CONTRACTS DEPARTMENT<br />
VISAKHAPATNAM-530031<br />
PHONE NO: (MAX)3691, TELEFAX NO:0891-2518763<br />
Common shutdown jobs, capital repair jobs and Maintenance <strong>of</strong> Heat<br />
Exchangers in Utilities Department <strong>of</strong> Visakhapatnam steel plant .<br />
PERIOD OF CONTRACT : 12 (Twelve) Months<br />
DEFECT LIABILITY PERIOD : 03 (Three) Months<br />
ENGINEER : AGM(M)-UT<br />
ISSUED TO SRI/ M/s.__________________________________________________________<br />
Note: Tenderer has to fill the data<br />
wherever and whatever required in<br />
the tender schedule without fail and<br />
sign all the pages<br />
1. E.M.D. PARTICULARS :<br />
No <strong>of</strong> pages <strong>of</strong> BOQ alone : 09 (Nine) pages only<br />
Total No. <strong>of</strong> pages : 39 (Thirty Nine) pages only<br />
(FOR OFFICE USE ONLY)<br />
2. Sl.No. : OUT OF TENDERS<br />
3. COVERING LETTER : NO. OF PAGES:<br />
4. REBATE OFFERED :<br />
5. RATE WRITTEN IN WORDS :<br />
6. VALIDITY OF TENDER : 4 MONTHS FROM THE DATE OF OPENING<br />
TENDER No : 72211-0<br />
TENDER NO: 72211-0<br />
SIGNATURE OF CONTRACT SIGNATURE OF FINANCE<br />
DEPT. REPRESENTATIVE DEPARTMENT REPRESENTATIVE<br />
1 <strong>of</strong> 39 Signature <strong>of</strong> the Tenderer
RASHTRIYA ISPAT NIGAM LIMITED<br />
VISAKHAPATNAM STEEL PLANT<br />
WORKS CONTRACTS DEPT., VISAKHAPATNAM -530031 (A.P.)<br />
TELEFAX: 0891-2518763 TEL NO: 0891-2758705, 2518763<br />
SHORT OPEN TENDER NOTICE NO: VSP/WC/UT/72211-0/SOT/2012-13 Dated 10.05.2012<br />
1. Sealed tenders along with Earnest Money Deposit (EMD) are invited from experienced and registered contractors<br />
for the following <strong>work</strong>:<br />
Tender No: Name <strong>of</strong> the <strong>work</strong><br />
72211-0 Common shutdown jobs, capital repair jobs and Maintenance <strong>of</strong> Heat<br />
Exchangers in Utilities Department <strong>of</strong> Visakhapatnam steel plant .<br />
Tender<br />
Number<br />
72211-0<br />
Cost <strong>of</strong> Tender Document<br />
(Non-refundable)<br />
By hand<br />
(`)<br />
600/-<br />
By<br />
download<br />
(`)<br />
600/-<br />
Eligibility/ experience requirements<br />
Registration Certificate under<br />
Category - 3.2<br />
Class - E<br />
TENDER No : 72211-0<br />
Earnest<br />
Money<br />
Deposit<br />
(`)<br />
17,500/-<br />
2.0. Cost <strong>of</strong> Tender document(s) shall be paid in the form <strong>of</strong> Demand Draft / Pay Order /<br />
Banker’s Cheque, obtained from any Nationalized or Scheduled Bank in India, drawn in favour <strong>of</strong><br />
RIN Lt d., pa yable a t V isakhapatnam a nd s hall be v alid f or a minimum pe riod <strong>of</strong> one month f rom<br />
the da te <strong>of</strong> o pening o f t ender i .e., E nvelope-1 (P re-qualification doc uments). THE COST OF<br />
TENDER DOCUMENT(S) RECEIVED ALONGWITH TENDER DOCUMENT WILL NOT BE REFUNDED<br />
UNDER ANY CIRCUMSTANCES UPON RECEIPT OF TENDER.<br />
NOTE: THE SUCCESSFUL TENDERER SHALL PRODUCE VAT REGISTRATION CERTIFICATE UNDER APVAT ACT,<br />
WHEREVER APPLICABLE, BEFORE SIGNING THE WORK ORDER / LOA AND SUBMIT A COPY OF THE<br />
SAME.<br />
3.0 The tenderers are requested to note that :<br />
3.1 The <strong>of</strong>fer shall be made in 02(two) envelopes:<br />
First envelope (to be super scribed as Envelope-1 with name <strong>of</strong> the <strong>work</strong>, tender no.) should contain the<br />
cost <strong>of</strong> the tender document in case the tender is down loaded from the web site (Tender can be<br />
purchased from the <strong>of</strong>fice <strong>of</strong> DGM(WC) I/c by paying tender cost in the form <strong>of</strong> DD/PO/BC as cited at<br />
para-2 above in which case tender cost need not be enclosed while submitting the tender), Earnest<br />
Money Deposit(EMD) separately in the form <strong>of</strong> DD/PO/BC etc (refer to instruction to tenderer) and<br />
pre-qualification documents[Criteria eligibility/experience and other documents etc.) as cited at para- 1.0<br />
above, duly signed / attested by the authorized representative <strong>of</strong> the company. Second envelope (to be<br />
super scribed as Envelope-2 with name <strong>of</strong> the <strong>work</strong>, tender no.) should contain price bid in its prescribed<br />
format along with the tender document.<br />
3.2 The first cover shall be opened initially and only on satisfying the eligibility criteria, adequacy <strong>of</strong> cost <strong>of</strong><br />
tender document ( incase <strong>of</strong> downloaded tender) and EMD etc., placed in it, the second envelope<br />
containing the price bid shall be opened. In case the price bid(s) is/are not opened immediately after<br />
opening <strong>of</strong> Envelope-1, then the date and time <strong>of</strong> opening <strong>of</strong> the price bid along with names <strong>of</strong><br />
successful tenderers in pre-qualification will be subsequently displayed in the notice board <strong>of</strong> Works<br />
Contracts only and no individual communication to tenderers will be made.<br />
3.3. The doc uments su bmitted i n t he f irst en velope b y t he tenderers i n r espect o f p re-qualification<br />
criteria are final and no further correspondence / clarifications / submissions in this regard shall<br />
be entertained.<br />
2 <strong>of</strong> 39 Signature <strong>of</strong> the Tenderer
TENDER No : 72211-0<br />
3.4 Scope <strong>of</strong> <strong>work</strong>, Bill <strong>of</strong> Quantities (BOQ), Terms & Conditions given in the tender documents (placed in the<br />
website) is final. On verification, at any time, whether the tenderer is successful or not, if any <strong>of</strong> the<br />
documents submitted by the tenderer including the documents downloaded from our website / issued are<br />
found tampered/altered/ incomplete, they are liable for actions like rejection <strong>of</strong> the tender, cancellation &<br />
termination <strong>of</strong> the contract, debarring etc., as per the rules <strong>of</strong> the company.<br />
3.5 It will be presumed that the tenderers have gone through the General Conditions, Special Conditions &<br />
Instructions to tenderer etc., <strong>of</strong> the contract available in the website which shall be binding on him/ them.<br />
3.6 The t enderer s hall do wnload t he “ TENDER S CHEDULE” available on t he website i n t otality a nd<br />
submit the same duly signed on each page. Any time prior to the deadline for submission <strong>of</strong> bids,<br />
Works Contracts department may, for any reason, modify the tender terms and conditions by way<br />
<strong>of</strong> an amendment, such amendment will be notified on RINL’s website at regular intervals.<br />
3.7 Tenders submitted against the NIT / Tender shall not be returned in case the tender opening date<br />
is extended/postponed. Tenderers desirous to modify their <strong>of</strong>fer / terms may submit their revised<br />
/ supplementary <strong>of</strong>fer(s) within the extended TOD, by clearly stating the extent <strong>of</strong> updation done to<br />
their o riginal o ffer an d the order o f prevalence o f r evised o ffer v is-à-vis original <strong>of</strong>fer.<br />
The employer reserves the right to open the original <strong>of</strong>fer along with revised <strong>of</strong>fer(s)<br />
4.0. The tender documents and other details can be downloaded from our web site: www.vizagsteel.com<br />
and the same are to be submitted to the Dy. General Manager (Works Contracts), Visakhapatnam <strong>Steel</strong><br />
Plant duly signed on each page by the tenderer on or before 03.00PM on 17.05.2012<br />
5.0. Non-transferable tender document can also be obtained from the <strong>of</strong>fice <strong>of</strong> Dy. General Manager (Works<br />
Contracts), VSP on written request on bidder’s letter head on payment <strong>of</strong> tender cost in the form <strong>of</strong><br />
DD/BC during <strong>work</strong>ing hours 10 AM to 4.30 PM on or before 04.30PM on 16.05.2012.<br />
6.0. Tenders will be received in the <strong>of</strong>fice <strong>of</strong> Dy. General Manager (Works Contracts), up t o 03.00 P M on<br />
17.05.2012 and Envelope-1 will be opened immediately there after.<br />
7.0 If it comes to the notice <strong>of</strong> VSP at any stage right from request for registration /tender document that any<br />
<strong>of</strong> the certificates /documents submitted by applicant for registration or by bidders are found to be false<br />
/fake/doctored, t he party w ill be de barred f rom pa rticipation i n a ll V SP t enders f or a pe riod <strong>of</strong><br />
05(FIVE) years i ncluding t ermination o f co ntract, i f aw arded. E .M.D/Security D eposit et c., i f an y<br />
will b e f orfeited. T he co ntracting ag ency i n su ch cases sh all make g ood t o V SP a ny l oss or<br />
damage r esulting from s uch t ermination. C ontracts i n ope ration a ny w here i n V SP will a lso be<br />
terminated with attendant fall outs like forfeiture <strong>of</strong> E.M.D./Security Deposit , if any, and recovery<br />
<strong>of</strong> risk and cost charges etc., Decision <strong>of</strong> V.S.P Management will be final and binding<br />
8.0 The date <strong>of</strong> opening <strong>of</strong> the pre-qualification cover ( envelope-1) shall be the date <strong>of</strong> tender opening in<br />
respect <strong>of</strong> both the single bid and two-bid ( techno-commercial and price-bid).<br />
9.0 Successful t enderer s hould be i n a pos ition t o pr oduce, a fter ope ning o f t he price bi ds, t he<br />
Original Certificates in support <strong>of</strong> the attested copies <strong>of</strong> relevant documents submitted along with<br />
tender d ocument. F ailure t o p roduce t he o riginal cer tificates at this st age i n su pport o f the<br />
attested copies <strong>of</strong> E lectrical License/any other d ocuments e tc. submitted ear lier would result in<br />
disqualification a nd f orfeiture <strong>of</strong> E MD a nd a lso l iable f or de barring from pa rticipation i n V SP<br />
tenders.<br />
10.0 Tender documents will be issued to tenderers based on their request and on payment <strong>of</strong> tender cost or<br />
same can be downloaded from our web site by submitting the cost <strong>of</strong> tender along with their <strong>of</strong>fer.<br />
However, RINL will not be responsible for any delay/loss/any website related problems in downloading<br />
the tender documents etc.. RINL reserve the right to (a) Issue or Refuse tender documents without<br />
assigning any reason. (b) Split and award the <strong>work</strong> to more than one agency, (c) reject any or all the<br />
tenders or to accept any tender wholly or in part or drop the proposal <strong>of</strong> receiving tenders at any time<br />
without assigning any reason there <strong>of</strong> and without being liable to refund the cost <strong>of</strong> tender documents<br />
thereupon.<br />
11.0 VSP after opening <strong>of</strong> tender/bid document may seek in writing, documents/clarifications which are<br />
necessary for evaluation <strong>of</strong> eligibility/prequalification stipulated in the NIT<br />
For Deputy General Manager (Works Contracts) I/c<br />
3 <strong>of</strong> 39 Signature <strong>of</strong> the Tenderer
Ref. Tender No.<br />
FORM – A<br />
Name <strong>of</strong> the Work : Common shutdown jobs, capital repair jobs and Maintenance <strong>of</strong><br />
Heat Exchangers in Utilities Department <strong>of</strong> Visakhapatnam steel plant<br />
To<br />
Deputy General Manager<br />
Works Contracts Department<br />
Visakhapatnam <strong>Steel</strong> Plant<br />
Visakhapatnam-530 031.<br />
Sirs,<br />
With reference to the Notice Inviting Tender, I/We have gone through the tender documents issued to us. I/We have also gone through<br />
the General Conditions <strong>of</strong> Contract <strong>of</strong> VSP available in VSP web site and noted the contents therein. I/We hereby confirm that I/We<br />
shall abide by Terms and Conditions <strong>of</strong> General Conditions <strong>of</strong> the Contract including Form <strong>of</strong> Tender, Invitation to Tender, Articles <strong>of</strong><br />
Agreement etc. I/We hereby declare that, I/We have visited, inspected and examined the site and its surroundings and satisfied<br />
ourselves before submitting this tender, obtained information about the nature <strong>of</strong> <strong>work</strong>, facilities that may be required and obtained<br />
necessary information about Working Conditions, risk contingencies etc., which may influence this tender. We hereby <strong>of</strong>fer to execute<br />
& maintain the <strong>work</strong> during the defect liability period in conformity with the tender conditions at the respective rates quoted by us.<br />
I/We have deposited the EMD, which amount is not to bear any interest and I/We do hereby agree that this sum shall be forfeited by<br />
me/us if I/We revoke/withdraw/cancel my/our tender or if I/We vary any terms in our tender during the validity period <strong>of</strong> the tender<br />
without your written consent and/or if in the event <strong>of</strong> Visakhapatnam <strong>Steel</strong> Plant accepting my/our tender and I/We fail to deposit the<br />
required security money, execute the Agreement and/start the <strong>work</strong> within reasonable time (to be determined by the Engineer) after<br />
written acceptance <strong>of</strong> my/our Tender.<br />
• Status <strong>of</strong> the firm (mark)<br />
• Proprietary /Partnership/others (Specify)<br />
* Authority to Sign:<br />
a) Proprietor<br />
b) Managing Partner<br />
c) Power <strong>of</strong> attorney holder<br />
Name <strong>of</strong> Partners:<br />
1)<br />
2)<br />
3)<br />
72211-0<br />
Following Details are to be furnished by the<br />
tenderer compulsorily (neat & legible) while<br />
submitting the tender schedule<br />
Income Tax PAN No.<br />
Status/Reason for not<br />
having PAN No.<br />
OFFICIAL ADDRESS<br />
Phone No:<br />
Cell No :<br />
Fax No.:<br />
e-mail address:<br />
Yours faithfully,<br />
(Signature <strong>of</strong> Contractor)<br />
Name:…………………………………<br />
TENDER No : 72211-0<br />
4 <strong>of</strong> 39 Signature <strong>of</strong> the Tenderer
INSTRUCTIONS TO TENDERERS<br />
TENDER No : 72211-0<br />
1.a) Tenders shall be submitted in the <strong>of</strong>fice <strong>of</strong> the Deputy General Manager (Works Contracts)I/C, Visakhapatnam<br />
<strong>Steel</strong> Plant, Visakhapatnam – 530 031.<br />
b) Tenders shall be submitted in the prescribed form issued by VSP. The Tender documents issued are not<br />
transferable. Tender documents issued/downloaded shall be submitted wholly without detaching any part.<br />
c) The Tenderer shall agree to VSP’s terms and conditions, specifications/<strong>scope</strong> <strong>of</strong> <strong>work</strong>, etc., and quote their “Total<br />
Amount only” accordingly.<br />
d) Tender shall be for the entire <strong>scope</strong> <strong>of</strong> <strong>work</strong> mentioned in the tender documents.<br />
e) Tenderer “Shall quote only the Total Amount in figures and in words”. Over writing is not permitted and<br />
corrections are to be essentially initialed. Amount quoted in words shall govern in case <strong>of</strong> variance between<br />
figures and words.<br />
f) The “ Total Amount quoted in figures and words shall be tallied” before submission <strong>of</strong> the tender and all mistakes<br />
corrected and initialed. Quotation shall preferably be type written or written in neat and legible handwriting. All<br />
the pages <strong>of</strong> tender documents shall be signed by the tenderer.<br />
g) If by any reason the tender opening is postponed to any other date, the details will be displayed in the notice board<br />
<strong>of</strong> Works Contract Department. Tenderers shall see the notice board regularly and keep themselves informed in<br />
this matter.<br />
h) Before quoting, the tenderer shall necessarily contact the “Engineer” and fully understand the job, <strong>scope</strong> <strong>of</strong> <strong>work</strong>,<br />
unit <strong>of</strong> measurement, mode <strong>of</strong> measurement, <strong>scope</strong> <strong>of</strong> supply <strong>of</strong> materials by VSP if any, <strong>work</strong>ing conditions,<br />
shutdown arrangements, Labour deployment requirements, risk contingencies and such other factors which may<br />
affect their tender.<br />
i) General Conditions <strong>of</strong> Contract <strong>of</strong> VSP for Works Contracts are available in the Office <strong>of</strong> DGM (Works Contracts)<br />
I/C and also in VSP’s web site for reference. The tenderers shall study and understand all the relevant provisions<br />
before quoting.<br />
j) Tenders shall be kept open for acceptance for a period 4 (Four) MONTHS from the date <strong>of</strong> opening <strong>of</strong> tender i.e..,<br />
Envelope-1.<br />
k) After opening <strong>of</strong> tender, the tenderers may be called for negotiations and the details like date, time etc. will be<br />
displayed on the notice board <strong>of</strong> Works Contract Department. The tenderers shall see the notice board regularly<br />
and keep themselves informed in this matter and promptly attend negotiations without fail.<br />
l) Purchase Preference will be given to PSU’s where applicable as per DPE guidelines.<br />
m) The local Small Scale Industries as approved by VSP and registered with Works Contracts Department <strong>of</strong><br />
Visakhapatnam <strong>Steel</strong> Plant in the category <strong>of</strong> Industrial Paint Manufactures for supply and application <strong>of</strong><br />
industrial Paints to various structurals, equipment pipelines etc., are eligible for purchase preference as per the<br />
policy <strong>of</strong> VSP in force from time to time. The local small-scale industries, those who are technically and<br />
commercially acceptable shall be considered for extension <strong>of</strong> Purchase Preference, if the <strong>of</strong>fer is within 15% above<br />
L-1 price and upon their matching with L-1 price.<br />
n) The date <strong>of</strong> opening <strong>of</strong> pre-qualification envelope-1 shall be the date <strong>of</strong> tender opening in respect <strong>of</strong> both the<br />
SINGLE BID AND TWO- BID(Techno-commercial and Price bid) tenders.<br />
o) Respective tenderers participating in the tenders due for opening on the scheduled day, can witness the opening<br />
<strong>of</strong> tenders/price bid on production <strong>of</strong> valid identity card/gate pass, or alternately, shall give a duly signed<br />
authorization to their designated representatives who are nominated if they wish to witness the tender/price bid<br />
opening. However, if the tenderer/designated representative participates for other than his tender his gate pass<br />
will be cancelled for a period <strong>of</strong> 01 (ONE) year.<br />
2) EARNEST MONEY DEPOSIT (EMD)<br />
a) In case <strong>of</strong> Earnest Money Deposit being less than or equal to Rs.5 Lakhs, Earnest Money Deposit shall be in the<br />
form <strong>of</strong> Demand Draft / Pay Order / Banker’s Cheque obtained from any Nationalized or scheduled commercial<br />
bank in India, drawn in favour <strong>of</strong> Rashtriya Ispat Nigam Ltd., Visakhapatnam <strong>Steel</strong> Plant, payable at<br />
Visakhapatnam and shall be valid for a minimum period <strong>of</strong> one month from the Envelope-1 (Pre-qualification<br />
documents) opening date. No other mode <strong>of</strong> payment will be accepted. However, in case EMD exceeds Rs.5<br />
Lakhs, tenderers have the option to submit the same in the form <strong>of</strong> Bank Guarantee (In the format as enclosed to<br />
the GCC) from any Scheduled Commercial Bank, encashable at Visakhaptnam. Bank Guarantees shall be valid for<br />
a minimum period <strong>of</strong> 04(Four) months from the date <strong>of</strong> opening <strong>of</strong> Envelope-1 (Pre-qualification documents).<br />
The above shall supercede the instructions regarding “form <strong>of</strong> EMD” elsewhere in the tender document.<br />
The above shall supercede the instructions regarding “Form <strong>of</strong> EMD” elsewhere in the tender document.<br />
b) Public Sector Enterprises <strong>of</strong> State / Central Government Undertakings are exempted from submission <strong>of</strong> Earnest<br />
Money Deposit (EMD) provided they submit a letter requesting for exemption from submission <strong>of</strong> EMD along<br />
with their <strong>of</strong>fer.<br />
c) The Small Scale Industries who are registered with Industries Department, Government <strong>of</strong> Andhra Pradesh or<br />
the National Small Industries Corporation Ltd., (NSIC) are exempted from submission <strong>of</strong> Earnest Money Deposit<br />
and Security Deposit and shall submit a self-attested copy <strong>of</strong> the valid registration <strong>of</strong> their Small Scale Industries<br />
along with their Tender. Such SSI or NSIC shall submit “Performance Guarantee Bond” in lieu <strong>of</strong> Security<br />
Deposit. The Small Scale Industries who are registered for the particular trade/item for which this tender is<br />
5 <strong>of</strong> 39 Signature <strong>of</strong> the Tenderer
TENDER No : 72211-0<br />
relevant will be exempted from submission <strong>of</strong> Earnest Money Deposit and Security Deposit. Such industries<br />
having provisional/temporary registration or/and not registered for the particular trade/item for which tender is<br />
being invited would not eligible for such exemption from Earnest Money Deposit and Security Deposit.<br />
d) EMDs <strong>of</strong> unsuccessful tenderers will be refunded after reasonable time without interest.<br />
3) MODE OF SUBMISSION OF TENDER<br />
a) Tender shall be submitted in two separate sealed covers. In case <strong>of</strong> single bid tender, the first cover shall contain<br />
the D.D. / Pay Order / Banker’s Cheque for Earnest Money Deposit / Cost <strong>of</strong> Tender Document / EMD exemption<br />
documents for PSUs & SSI units, other pre-qualification documents etc. and the second cover shall contain the<br />
tender.<br />
b) In case <strong>of</strong> two bid system, the first cover shall contain the techno-commercial bid part <strong>of</strong> tender, along with the<br />
other bank instruments / documents indicated in para 3(a) above, and the second cover shall contain only the<br />
price bid part <strong>of</strong> tender.<br />
c) The two sealed covers as mentioned above shall be stapled / tied together and submitted. The first cover will be<br />
opened first and only if the submitted documents / instruments are found to be as per NIT requirement, will the<br />
second cover containing the price bid be opened.<br />
d) Tenders not satisfying the requirements as per NIT will not be opened.<br />
SPECIAL CONDITIONS OF CONTRACT (SCC)<br />
1. General: The special conditions <strong>of</strong> the contract (SCC) are complementary to and shall be read in conjunction with<br />
General Conditions <strong>of</strong> Contract (GCC) <strong>of</strong> VSP for <strong>work</strong>s contracts. Scope <strong>of</strong> <strong>work</strong>, Bill <strong>of</strong> Quantities and other<br />
documents form part <strong>of</strong> the Tender Documents. In case <strong>of</strong> any conflict <strong>of</strong> meaning between SCC & GCC,<br />
provisions <strong>of</strong> SCC shall over ride the Provisions <strong>of</strong> GCC.<br />
2. Visakhapatnam <strong>Steel</strong> Plant reserves the right to accept or reject the lowest or any other tender without assigning<br />
any reason and the <strong>work</strong> may be awarded to one <strong>of</strong> the Tenderers or to more than one tenderer.<br />
3. The contract shall be treated as having been entered into from the date <strong>of</strong> issue <strong>of</strong> the letter <strong>of</strong> intent/<strong>work</strong> order<br />
to the successful tenderer, unless otherwise specified.<br />
4. WATER, POWER AND COMPRESSED AIR: Unless otherwise specified to the contrary in the tender schedule, the<br />
contractor is entitled to use in the <strong>work</strong> such supplies <strong>of</strong> water, power and compressed air (Basing on availability)<br />
from VSP’s sources from approved tapping points, free <strong>of</strong> cost. The contractor shall make his own arrangement<br />
for drawing the same to the <strong>work</strong> spot.<br />
5. The successful tenderer shall produce Registration Certificate under APVAT Act, wherever applicable, before<br />
signing the Work Order / Letter <strong>of</strong> Acceptance and submit a copy <strong>of</strong> the same.<br />
6. Immediately on receipt <strong>of</strong> <strong>work</strong> order, the successful tenderer shall obtain and submit the following documents to<br />
the Engineer with a copy to ZPE/Manager (Pers)/CLC before start <strong>of</strong> <strong>work</strong>.<br />
a(i) ESI registration certificate with the contractor’s Code no. covering all the <strong>work</strong>men under ESI Scheme,<br />
which shall be effective from the date <strong>of</strong> start <strong>of</strong> contract and cover for the entire period <strong>of</strong> contract<br />
including extended period/defect liability period, if any.<br />
a(ii) Insurance policy for payment <strong>of</strong> exgratia amount <strong>of</strong> Rs.5,00,000/- (Rupees Five lakhs only) per head in<br />
case <strong>of</strong> fatal accidents while on duty, to the contract labour engaged by him in addition to the coverage<br />
under ESI Scheme / Workmen Compensation Insurance Policy whichever is applicable. As and when a<br />
fatal accident takes place while on duty along with the benefits under the ESI Scheme / Workmen<br />
Compensation, whichever is applicable, the contractor is required to pay the ex-gratia amount within 30<br />
(Thirty) days from the date <strong>of</strong> accident to the legal heir <strong>of</strong> the deceased. In case <strong>of</strong> any delay in paying<br />
the ex-gratia amount as above, the Employer has the right to pay such amount directly to the legal heir <strong>of</strong><br />
the deceased and recover the same from the contractor’s running / future bills. This insurance policy is<br />
to be taken by the contractor over and above the provisions specified under Clause No. 6.13 (Third Party)<br />
and 6.14 (ESI Act) <strong>of</strong> the General Conditions <strong>of</strong> Contract.<br />
a(iii) Copy <strong>of</strong> the policy for third party insurance as stipulated in Clause 6.13 <strong>of</strong> the GCC.<br />
b) Labour License obtained from Assistant Labour Commissioner (Central), Visakhapatnam.<br />
c) PF Registration Certificate issued by PF Authorities<br />
d) Safety clearance from Safety Engineering Department <strong>of</strong> VSP.<br />
7. The contractor shall submit wage records, <strong>work</strong> commencement/completion certificate etc. and obtain necessary<br />
clearance from Contract Labour Cell <strong>of</strong> VSP for bills clearance.<br />
8. The contractor shall ensure strict compliance with provisions <strong>of</strong> the Employee’s Provident Fund Act, 1952 and the<br />
scheme framed there under in so far as they are applicable to their establishment and agencies engaged by them.<br />
The contractor is also required to indemnify the employer against any loss or claim or penalties or damages<br />
whatsoever resulting out <strong>of</strong> non- compliance on the part <strong>of</strong> the contractor with the provisions <strong>of</strong> aforesaid act<br />
and the schemes framed there under. A copy <strong>of</strong> the provident fund membership certificate/PF CODE number<br />
shall be submitted by the contractor.<br />
9. The contractor shall follow the provisions <strong>of</strong> Indian Factories Act and all rules made there under from time to time<br />
as applicable and shall indemnify the employer against all claims <strong>of</strong> compensations under the provisions <strong>of</strong> the act<br />
in respect <strong>of</strong> <strong>work</strong>men employed by the contractor in carrying out the <strong>work</strong> against all costs, expenses and<br />
penalties that may be incurred by the employer in connection therewith.<br />
6 <strong>of</strong> 39 Signature <strong>of</strong> the Tenderer
TENDER No : 72211-0<br />
10. a) Total amount quoted shall be inclusive <strong>of</strong> all taxes, levies, duties, royalties, overheads and the like but<br />
excluding service tax prevailing as on the date <strong>of</strong> submission <strong>of</strong> bids.<br />
b) During the operation <strong>of</strong> the contract if any new taxes/duties/levies etc are imposed or rates undergo<br />
changes, as notified by the Government and become applicable to the subject <strong>work</strong>s, the same shall be<br />
reimbursed by VSP on production <strong>of</strong> documentary evidence in respect <strong>of</strong> the payment <strong>of</strong> the same.<br />
Similarly benefits accruing to agency on account <strong>of</strong> withdrawal/reduction in any existing taxes and<br />
duties shall be passed on to VSP.<br />
C) The benefit <strong>of</strong>fered by the agency (other than Service Tax) will be deducted from each bill on the <strong>of</strong>fered<br />
percentage basis. Amount so recovered shall be released, limiting to the percentage <strong>of</strong> benefit <strong>of</strong>fered on<br />
the quoted price, only on receipt <strong>of</strong> credit by VSP.<br />
d) The prices are exclusive <strong>of</strong> Service Tax. RINL-VSP will pay Service Tax as applicable on submission <strong>of</strong><br />
Invoices in accordance with Rule 4A (1) <strong>of</strong> Service Tax Rules 1994.<br />
The contractor will be paid Service Tax by RINL-VSP along with monthly service charge bills for further<br />
deposit with Central Excise Authorities. The contract will, in turn, submit the documentary evidence in<br />
support <strong>of</strong> payment <strong>of</strong> Service Tax <strong>of</strong> each month along with subsequent month RA Bills.<br />
11. ADVANCE: No advance <strong>of</strong> any sort will be given by VSP.<br />
12. PAYMENT TERMS: Payment will be made monthly on recommendations <strong>of</strong> the Engineer basing on the<br />
quantities executed, at accepted rates.<br />
13. MEASUREMENTS: The contractor shall take measurements jointly with the Engineer or his<br />
representative and keep joint records for the same. Bills shall be prepared and submitted by the contractor basing<br />
on agreed measurements.<br />
14. INITIAL SECURITY DEPOSIT (ISD): Initial Security Deposit for the <strong>work</strong> shall be @ 2% <strong>of</strong> contract price.<br />
Earnest Money Deposited by the successful tenderer shall be adjusted against ISD, and the difference between ISD<br />
and EMD shall be deposited in the manner mentioned in the <strong>work</strong> order/letter <strong>of</strong> intent.<br />
15. RETENTION MONEY: Retention Money for contracts up to a value <strong>of</strong> Rs. 100 lakhs, at the rate <strong>of</strong> 7.5% <strong>of</strong> the bills<br />
for <strong>work</strong>s with defective liability period not NIL and at the rate <strong>of</strong> 5.0% for <strong>work</strong>s with defective liability period<br />
“NIL” will be deducted from each bill until this amount together with the Initial Security Deposit reach the limit<br />
<strong>of</strong> retention which is 7.5% or 5.0% as the case may be for the value <strong>of</strong> <strong>work</strong>. The Retention Money shall be<br />
released after the satisfactory completion <strong>of</strong> defect liability period after liquidating the defects. For contracts <strong>of</strong><br />
value above Rs.100 Lakhs, the limit <strong>of</strong> retention money shall be Rs.7.5 lakhs plus 5% <strong>of</strong> the value exceeding<br />
Rs.100 lakhs.<br />
16. Security Deposit: : The Public Sector Enterprises or State/Central Government Undertakings/ SSI units registered<br />
with Govt. <strong>of</strong> AP/NSIC will not be required to submit Security Deposit, but however they shall submit<br />
“Performance Guarantee Bond” in lieu <strong>of</strong> Security Deposit in the prescribed pr<strong>of</strong>orma equivalent to the value <strong>of</strong><br />
Security Deposit covering the period <strong>of</strong> contract + defect liability period + 6 months (Claim period).<br />
17. Recovery <strong>of</strong> income tax at source will be made from contractor’s bill and deposited with Income Tax<br />
Department as per rules. Recovery <strong>of</strong> sales tax applicable shall be made from the contractor’s bills.<br />
18 . SAFETY:<br />
a) The contractor and his <strong>work</strong>ers must strictly take all safety precautions and shall supply to his <strong>work</strong>ers<br />
dependable safety appliances like hand gloves, safety boots, safety belt, safety helmets, duster cloth, dust<br />
mask/nostril filter etc. In addition to this, contractor shall also provide additional safety appliances as<br />
per requirement and follow safe <strong>work</strong>ing practices like using fully insulated electrode holders etc. He<br />
shall also ensure that his <strong>work</strong>men intelligently use only dependable safety appliances supplied to them.<br />
b) The contractor shall take adequate safety precaution to prevent accidents at site. The contractor shall<br />
also ensure that his employees observe the statutory safety rules and regulations and also those laid down<br />
by the employer from time to time and promptly submit report <strong>of</strong> accident and state the measures taken<br />
by him to prevent their recurrence and also keep the employer indemnified <strong>of</strong> all claims arising out <strong>of</strong><br />
such accidents.<br />
c) No Workmen shall be engaged on the <strong>work</strong> without proper safety induction and without using required<br />
PPE. Use <strong>of</strong> safety helmet and shoe is must excepting in painting <strong>work</strong>s where shoe will not be used.<br />
d) All the safety appliances required for safe <strong>work</strong>ing as decided by SED/Contract operating deprtment shall<br />
be provided by the contractor to his <strong>work</strong>men.<br />
e) Clearance to start the job will be obtained by the contractor in form ‘A&B’ before start <strong>of</strong> <strong>work</strong>. The forms<br />
may be obtained from the dept. concerned.<br />
f) Works at height cannot be started without clearance from Zonal Safety Officer. The <strong>work</strong>ers engaged for<br />
<strong>work</strong> at height shall possess height pass from SED. The names <strong>of</strong> <strong>work</strong>men <strong>work</strong>ing at height or in<br />
hazardous areas will be written on the body <strong>of</strong> form “B”.<br />
g) Contravention <strong>of</strong> any safety regulation <strong>of</strong> VSP in vogue from time to time will result into <strong>work</strong> stoppage,<br />
levying penalties and ultimately in contract termination.<br />
h) “The contractor shall ensure that the Welders and Gas Cutters wear cotton dress and leather apron.<br />
They shall not wear nylon/synthetic dress. This is required to avoid any fire accident. This must be<br />
followed strictly”.<br />
7 <strong>of</strong> 39 Signature <strong>of</strong> the Tenderer
TENDER No : 72211-0<br />
19. SHUTDOWNS:<br />
A) Necessary shutdowns will be arranged by VSP to the contractor for carrying out the <strong>work</strong> based on<br />
requirement. No claims on account <strong>of</strong> delayed/prolonged shutdown will be entertained.<br />
B) The <strong>work</strong>s assigned to the contractor by the Engineer from time to time shall be completed within the<br />
time schedule fixed by the Engineer in each case, within the approved shut down period.<br />
20. LABOUR DEPLOYMENT:<br />
A) The contractor shall deploy his labour as per requirement and as instructed by the Engineer. It may be<br />
necessary to carryout the <strong>work</strong> round the clock based on requirement and shutdown provided. The<br />
contractor’s rate shall cover such eventualities.<br />
B) Only trained, experienced, safety inducted <strong>work</strong>ers acceptable to the Engineer shall be engaged on this<br />
<strong>work</strong>, <strong>work</strong> shall be executed as per specifications to the satisfaction <strong>of</strong> the Engineer.<br />
C) As and when need arises in the Annual <strong>work</strong>s from time to time either for extra requirement <strong>of</strong> <strong>work</strong> or<br />
as a replacement in running contracts or a contract commencing for the first time, the contractor shall<br />
ensure that Displaced Persons (DPs) are engaged in unskilled category <strong>of</strong> <strong>work</strong>ers to the extent <strong>of</strong> 50%<br />
(fifty percent). The contractor shall contract the Engineer-in-charge for this purpose.<br />
21. SECURITY REGULALTIONS: The contractor shall abide by and also observe all security regulations promulgated<br />
from time to time by the employer.<br />
22. STORING/STACKING OF MATERIALS: Storing/Stacking/Placing <strong>of</strong> materials shall be only at the places designated<br />
by the engineer.<br />
23. The contractor, his supervisors and <strong>work</strong>men shall observe entry and exit timings strictly.<br />
24. After completion <strong>of</strong> <strong>work</strong> activity, the site has to be cleared <strong>of</strong> all debris, construction material and the like.<br />
25. The successful tenderer shall start the <strong>work</strong> immediately after obtaining gate passes and safety induction training<br />
and clearance from the Employer.<br />
26. NOTICES: Any notice to be given to the contractor under terms <strong>of</strong> the contract shall be considered duly served, if<br />
the same has been delivered to, left for or posted by registered post to the contractors principal place <strong>of</strong> business<br />
(or in the event <strong>of</strong> the contractor being a company, its registered <strong>of</strong>fice), at the site or to their last known address.<br />
27. DEFAULT BY TENDERERS: The successful tenderer may be debarred at the discretion <strong>of</strong> the company, from issue <strong>of</strong><br />
further tender documents, <strong>work</strong> orders etc., for a specified period to be decided by the employer in case <strong>of</strong> :<br />
“Undue delay in starting and execution <strong>of</strong> <strong>work</strong> awarded, poor performance, backing out from the tender, non<br />
accepting <strong>work</strong> order/LOI during the validity <strong>of</strong> tender or non observance <strong>of</strong> safety rules and regulations,<br />
misappropriation <strong>of</strong> company’s materials/property, non payment <strong>of</strong> due wages to labour or such similar<br />
defaults”.<br />
28. Successful tenderer should be in a position to produce the Original Certificate in support <strong>of</strong> the attested copies <strong>of</strong><br />
relevant documents enclosed along with pre-qualification documents or afterwards, after opening <strong>of</strong> the Price<br />
Bids.<br />
29. Failure to produce the original certificates at this stage in support <strong>of</strong> the attested copies <strong>of</strong> PF<br />
Registration/ITCC/Electrical License/Experience/Qualification any other documents etc., submitted earlier would<br />
result in disqualification and forfeiture <strong>of</strong> EMD and also liable for debarring from participation in VSP tenders.<br />
30. If it comes to the notice <strong>of</strong> VSP at any stage right from request for registration/tender document that any <strong>of</strong> the<br />
certificates/documents submitted by applicant for registration or by bidders are found to be false/fake/doctored,<br />
the party will be debarred from participation in all VSP tenders for a period <strong>of</strong> 05 (FIVE) YEARS including<br />
termination <strong>of</strong> Contract, if awarded. EMD / Security Deposit etc., if any, will be forfeited. The Contracting Agency<br />
in such cases shall make good to VSP any loss or damage resulting from such termination. Contracts in operation<br />
any where in VSP will also be terminated with attendant fall outs like forfeiture <strong>of</strong> E.M.D. / Security Deposit, if<br />
any, and recovery <strong>of</strong> risk and cost charges etc. Decision <strong>of</strong> V.S.P. Management will be final and binding.<br />
31. Failure to execute the <strong>work</strong> after LOI/WORK ORDER is given, will make the party liable for debarring for a period<br />
<strong>of</strong> 2 (TWO) YEARS.<br />
32. In case it is found before/after award <strong>of</strong> <strong>work</strong> to the person/agency through Limited Tender Enquiry (LTE) that<br />
the same person/agency is proprietor/proprietress/partner <strong>of</strong> two or more separate agencies and quoted for the<br />
same <strong>work</strong>, then punitive action to the extent <strong>of</strong> debarring up to 02 (Two) years from participating in VSP tenders<br />
will be taken.<br />
33. In case the Tenderers revoke/withdraw/cancel their tender or they vary any terms <strong>of</strong> their tender during the<br />
validity period <strong>of</strong> the tender without the written consent <strong>of</strong> Visakhapatnam <strong>Steel</strong> Plant (VSP) or in the event <strong>of</strong> VSP<br />
accepting their tender and fail to deposit the required security money, execute the Agreement and fail to start the<br />
<strong>work</strong> within reasonable time (to be determined by the Engineer) after written acceptance <strong>of</strong> their tender – EMD<br />
submitted by them will be forfeited by VSP.<br />
34. Contractor shall note that:<br />
i) Time for mobilization after issue <strong>of</strong> FAX Letter <strong>of</strong> Intent/detailed Letter <strong>of</strong> Intent / Work Order shall be;<br />
a. 03 (Three) days for Capital Repairs<br />
b. 15 days for Civil Works<br />
c. 60 days for painting <strong>work</strong>s <strong>of</strong> Structural Engineering Department<br />
8 <strong>of</strong> 39 Signature <strong>of</strong> the Tenderer
d. 07 (Seven) days for Annual Mechanical, Electrical and <strong>work</strong>s <strong>of</strong> technological<br />
assistance/cleaning.<br />
ii) Re-starting the <strong>work</strong> after disruption shall be within 04 (Four) to 06 (Six) hours after the cause <strong>of</strong><br />
disruption is removed as decided by the HOD.<br />
iii) Notice period for Contract Termination shall be - 03 (Three) hours in the event <strong>of</strong> breakdowns, 02 (Two)<br />
days in Capital Repairs and 10 days in other <strong>work</strong>s.<br />
Failure to adhere to above stipulations may result in Termination <strong>of</strong> contract at risk & cost and will make the party<br />
liable for debarring for a period o 2 (Two) years.<br />
35. Agencies are required to submit Bank Guarantee for the value as decided by the Engineer as a Security while<br />
taking out Equipment/Components/materials <strong>of</strong> VSP to their <strong>work</strong>shop situated outside the VSP premises for<br />
carrying out repairs.<br />
36. In case <strong>of</strong> revision in RINL / VSP approved wage rate, consequent to the revision in the minimum wages (either in<br />
Basic Wage or Living Allowances) as notified by the Regional Labour Commissioner (Central), Hyderabad,<br />
Escalation amount to the contract shall be payable as per the following formula:<br />
V = L x W x (X-Xo)<br />
Xo<br />
WHERE:<br />
V= Escalation Payable<br />
L= Labour Content as Percentage <strong>of</strong> the Work is 70% (Seventy) Percent<br />
W= Gross value <strong>of</strong> <strong>work</strong> done on the basis <strong>of</strong> Contract Rates for the period for which variation is<br />
applicable<br />
X= Revised weighted average <strong>of</strong> RINL/VSP approved wage rates <strong>of</strong> Unskilled Worker, Semi-skilled<br />
Worker and Skilled Worker based on the minimum wages as notified by the Regional Labour<br />
Commissioner (Central), Hyderabad, for the period under consideration for the contract on the basis<br />
<strong>of</strong> actual man days present by different categories <strong>of</strong> contract labour during the billing period.<br />
Xo = Weighted average <strong>of</strong> existing RINL/VSP approved wage rates <strong>of</strong> Unskilled Worker, Semi-skilled<br />
Worker and Skilled Worker considered in the estimate which is indicated in the Quote Sheet – Form<br />
“G” / BOQ <strong>of</strong> the Tender document on the basis <strong>of</strong> actual man days present by different categories <strong>of</strong><br />
contract labour during the billing period.<br />
Computation <strong>of</strong> X and Xo:<br />
X= (a*USR + b*SSR + c*SKR)/(a+b+c)<br />
Xo= (a*USRo + b*SSRo + c*SKRo) / (a+b+c)<br />
Where<br />
a= man days present by USW during the billing period<br />
b= man days present by SSW during the billing period<br />
c= man days present by SKW during the billing period<br />
USR= Revised RINL/VSP approved wage rate for USW at the time <strong>of</strong> billing<br />
SSR= Revised RINL/VSP approved wage rate for SSW at the time <strong>of</strong> billing<br />
SKR= Revised RINL/VSP approved wage rate for SKW at the time <strong>of</strong> billing<br />
TENDER No : 72211-0<br />
USRo= RINL/VSP approved wage rate for USW indicated in the Quote Sheet (Form G)/BOQ <strong>of</strong> the Tender<br />
Document.<br />
SSRo= RINL/VSP approved wage rate for SSW indicated in the Quote Sheet (Form G)/BOQ <strong>of</strong> the Tender<br />
Document.<br />
SKRo= RINL/VSP approved wage rate for SKW indicated in the Quote Sheet (Form G)/BOQ <strong>of</strong> the Tender<br />
Document.<br />
37. PAYMENT OF MINIMUM WAGES: Wages paid to the <strong>work</strong>men by the contractor should not be less than the rates<br />
notified by the Regional Labour Commissioner (Central), Hyderabad, from time to time with regard to the<br />
minimum wages applicable to the respective categories <strong>of</strong> <strong>work</strong>men plus the ad-hoc amount at the rate <strong>of</strong><br />
`.11.54ps as per <strong>work</strong>ing day per <strong>work</strong>man per category. Wages with ad-hoc amount to the <strong>work</strong>men should be<br />
paid on or before the 7 th <strong>of</strong> the subsequent month. if 7 th falls on a holiday or weekly <strong>of</strong>f day, the payment should<br />
be made one day prior to that. Payment <strong>of</strong> PF for the month, both the employer’s (in this case contractor) and<br />
employee’s (in this case <strong>work</strong>men employed by the contractor) contributions should be deposited in the bank in<br />
the permanent PF code number and challan obtained before the 15 th <strong>of</strong> the subsequent month and forwarded to<br />
the Engineer”. In case <strong>of</strong> failure <strong>of</strong> the contractor to comply with any <strong>of</strong> the above, the following action will be<br />
taken by VSP.<br />
9 <strong>of</strong> 39 Signature <strong>of</strong> the Tenderer
LAPSE ACTION BY VSP<br />
1. a) Payment <strong>of</strong> wages at rates less than<br />
those notified under the minimum<br />
wages.<br />
b) Non-payment <strong>of</strong> ad-hoc amount<br />
2. Non payment <strong>of</strong> wages<br />
3. Non Payment <strong>of</strong> PF<br />
4. Delayed Payment <strong>of</strong> PF<br />
38. The contract period can be extended at the discretion <strong>of</strong> V.S.P. up to 04 (Four) months at the existing Rates,<br />
Terms and conditions and the Contractor shall be bound to execute the <strong>work</strong> accordingly and the <strong>of</strong>fer <strong>of</strong> the<br />
Contractor is deemed to include this aspect.<br />
39. The tenderers shall note that in case <strong>of</strong> quoting above the Estimated Value <strong>of</strong> V.S.P. the L-1 party shall furnish<br />
logical / satisfactory explanation which V.S.P. may seek if felt necessary for quoting such high rates. If the<br />
explanation <strong>of</strong>fered by the L-1 party is not acceptable to V.S.P., the L-1 party may be recommended for<br />
disqualification while retendering the <strong>work</strong>.<br />
40. The contractor should clearly understand and comply with the Factories Act 1948 and relieve the FEMALE<br />
WORKERS from their <strong>work</strong> site within the restricted <strong>work</strong>ing hours prescribed therein under section 66(b).<br />
41. The following deductions per <strong>work</strong>man deployed category-wise shall be made from the bills/amounts due to the<br />
contractor as applicable for the <strong>work</strong> done and such deducted amounts shall be released as mentioned below:<br />
S.No Component<br />
Recovery amount per labour<br />
per every WORKING DAY (in Rs.) To be released when<br />
UN-SKILLED SEMI-SKILLED SKILLED<br />
01 Notice pay Rs.18.19ps Rs.20.59ps Rs.24.28ps After the Contractor makes<br />
02<br />
Retrenchment<br />
compensation<br />
Rs. 09.10ps Rs. 10.30ps Rs.12.14ps<br />
payment to the <strong>work</strong>men in<br />
the presence <strong>of</strong> Engineer<br />
I/C and CLC<br />
03<br />
Leave with<br />
wages<br />
Rs.11.19ps Rs.12.67ps Rs.14.94ps<br />
representatives, a certificate<br />
to this effect is to be<br />
enclosed with pre-final bill.<br />
(to be paid with pre-final<br />
bill)<br />
Sub-total Rs.38.48ps Rs.43.56ps Rs.51.36ps<br />
04 Bonus Rs.11.55ps Rs.11.55ps Rs.11.55ps<br />
TENDER No : 72211-0<br />
a) An amount equivalent to the differential amount<br />
between wages to be paid under minimum wages<br />
notification <strong>of</strong> the Govt. applicable for the period less<br />
actual wages paid shall be recovered from the bills as<br />
certified by the Engineer.<br />
b) As amount equivalent to actual payable towards ad-hoc<br />
amount to the <strong>work</strong>men engaged for relevant period shall<br />
be recovered from the bills as certified by the Engineer.<br />
An amount equivalent to wages payable by the contractor<br />
applicable for the relevant period shall be recovered from<br />
the bills as certified by the Engineer.<br />
Recovery <strong>of</strong> PF amount and an amount equivalent to<br />
maximum penalty leviable by Regional Provident Fund<br />
Commissioner for the delayed period under the provisions<br />
<strong>of</strong> EPF & MP Act and Rules for delayed remittance <strong>of</strong> PF<br />
contributions (both the employee’s and employer’s<br />
contribution), shall be recovered from the bills <strong>of</strong><br />
contractor as certified by Engineer.<br />
An amount equivalent to maximum penalty leviable by<br />
Regional provident Fund Commissioner for the delayed<br />
period under the provisions <strong>of</strong> EPF & MP Act and rules for<br />
delayed remittance <strong>of</strong> PF contributions (both the<br />
employee’s and employer’s contribution), shall be<br />
recovered from the bills <strong>of</strong> the contractor as certified by<br />
Engineer.<br />
After the Contractor makes<br />
payment to the <strong>work</strong>men in<br />
the presence <strong>of</strong> Engineer<br />
I/C and CLC<br />
10 <strong>of</strong> 39 Signature <strong>of</strong> the Tenderer
TENDER No : 72211-0<br />
representatives, a certificate<br />
to this effect is to be<br />
enclosed with RA bill / prefinal<br />
bill. (to be paid with<br />
RA bill / pre-final bill as<br />
and when paid by the<br />
Contractor)<br />
Grand total Rs.50.03ps Rs.55.11ps Rs.62.91ps<br />
10% towards pr<strong>of</strong>it and<br />
overheads <strong>of</strong> Contractor<br />
Rs.05.00ps Rs.05.51ps Rs.06.29ps<br />
Total recovery amount Rs.55.03ps Rs.60.62ps Rs.69.20ps<br />
Note:<br />
i) The above recovery rates are effective from 01/10/2011. In case <strong>of</strong> any statutory revision in minimum<br />
wages payable to contract <strong>work</strong>men as notified by the Regional Labour Commissioner (Central),<br />
Hyderabad from time to time, the above recovery amounts for <strong>work</strong>men category-wise will be revised by<br />
RINL/VSP and will be notified accordingly.<br />
ii) Payment against the above component is to be made to the <strong>work</strong>men based on effective wages <strong>of</strong> last<br />
drawn pay.<br />
42. PAYMENT MODE FOR BILL AMOUNTS:<br />
42.1 Following are the options available to the Contractors for availing e-payments.<br />
42.1.1 EFT System: Under this system Banks <strong>of</strong>fer their customers money Transfer service from account <strong>of</strong> any bank<br />
branch to any other Bank Branch. The EFT system presently covers all the branches <strong>of</strong> about 77 banks located at<br />
15 centers indicated below, where clearing houses are managed by RBI i.e.,<br />
i) New Delhi ii) Chandigarh iii) Kanpur iv) Jaipur v) Ahmedabad vi) Mumbai vii) Nagpur viii) Hyderabad<br />
ix) Bangalore x) Chennai xi) Trivendrum xii) Kolkata xiii) Bhubaneswar xiv) Guwahati xv) Patna.<br />
42.1.2 Direct Credit: Suppliers opting for this system may open Bank accounts with any one <strong>of</strong> the following banks.<br />
i) State Bank <strong>of</strong> India - <strong>Steel</strong> Plant Branch<br />
ii) Canara Bank - <strong>Steel</strong> Plant Branch<br />
iii) Bank <strong>of</strong> Baroda - <strong>Steel</strong> Plant Branch<br />
iv) State Bank <strong>of</strong> Hyderabad - <strong>Steel</strong> Plant Township Branch<br />
v) Andhra Bank - <strong>Steel</strong> Plant Township Branch<br />
vi) UCO Bank - <strong>Steel</strong> Plant Township Branch<br />
vii) IDBI - Visakhapatnam Branch<br />
42.2 The Successful tenderer shall agree that all the payment due and payable in terms <strong>of</strong> the contract will be paid<br />
direct to his bank account and he shall give the bank account number and the address <strong>of</strong> the Bank in which the<br />
money is to be deposited” as per the format given below:<br />
(1) Party Code :<br />
(2) Option : RTGS / EFT<br />
(3) Beneficiary Details<br />
a) Name <strong>of</strong> Beneficiary (Max.35 characters) :<br />
b) Bank Name (Max. 35 characters) :<br />
c) Branch Name (Max. 35 characters) :<br />
d) Account Number (Max. 35 characters) :<br />
e) Account type (Max. 35 characters) :<br />
(Savings / Current / Overdraft) [Mention Code No. also]<br />
f) Beneficiary Bank’s IFSC Code (Max. 11 characters):<br />
(For RTGS Mode only)<br />
g) Beneficiary Bank’s MICR Code (Max.09 characters):<br />
(For EFT Mode only)<br />
(Signature <strong>of</strong> the Party / Contractor)<br />
Name:<br />
Desgn:<br />
11 <strong>of</strong> 39 Signature <strong>of</strong> the Tenderer
CERTIFICATE<br />
Certified that the above particulars are found to be correct and matching with our records in respect <strong>of</strong> the above<br />
beneficiary.<br />
Sd/-……………<br />
(Signature <strong>of</strong> Branch Manager)<br />
Name :<br />
Seal <strong>of</strong> Bank :<br />
42.3 The contractor has to submit their bank account details in VSP format duly certified by Concerned Bank Manager<br />
for the purpose <strong>of</strong> making electronic payment before submission <strong>of</strong> First Running Account Bill, failing which the<br />
bill will not be processed.<br />
42.4. The Successful tenderer is required to give an undertaking to the Finance Department <strong>of</strong> VSP that the payment<br />
made by RINL/ VSP <strong>of</strong> any sum due to him by directly remitting the same in his bank, the address and the number<br />
<strong>of</strong> which is to be furnished, shall be in full discharge <strong>of</strong> the particular bill raised by him, and that he shall not<br />
have any claim in respect <strong>of</strong> the same”.<br />
42.5 In respect <strong>of</strong> payment made through Electronic Fund Transfer mechanism or Direct Credit to the<br />
supplier’s/contractor’s bank account, the supplier/contractor/receiver should intimate discrepancies, if any,<br />
within 10 days from the date <strong>of</strong> dispatch <strong>of</strong> intimation letter <strong>of</strong> payment to them to Finance Department <strong>of</strong> VSP<br />
failing which it shall be presumed that the funds have reached to their bank account and that no claims will be<br />
entertained after the said 10 days.<br />
43. CLAUSES CONCERNING CENVAT AGAINST EXCISE DUTY:<br />
a) The tenderer shall specify the percentage <strong>of</strong> CENVAT benefit on quoted price for which they shall furnish<br />
the duty paying documents.<br />
b) The successful tenderer shall take necessary steps to comply with the rules and provisions <strong>of</strong> central<br />
excise and service tax law facilitating VSP to avail CENVAT credit.<br />
c) The amount <strong>of</strong> CENVAT benefit declared shall be deducted from the tendered price for the purpose <strong>of</strong><br />
tender evaluation i.e. the evaluation shall be on the net <strong>of</strong> CENVAT benefit.<br />
d) The invoice raised by the Contractor should clearly mention VSP as the consignee (Consignee: RINL, VSP,<br />
A/c: Name <strong>of</strong> the contractor). It should be ensured that material has been delivered along with the<br />
duplicate for transporter copy <strong>of</strong> the invoice, based on which CENVAT credit is to be claimed.<br />
e) The duty paying documents shall be submitted as soon as the material is procured by the agency for<br />
incorporation in the <strong>work</strong>. The CENVAT benefit <strong>of</strong>fered by the agency will be deducted from each bill on<br />
the <strong>of</strong>fered percentage basis and will be released to the extent CENVAT benefit could be availed by VSP.<br />
The contractor shall extend all possible help to facilitate VSP to avail CENVAT benefit. If CENVAT benefit<br />
could not be availed by VSP due to reasons attributable to the contractor, such amount will not be<br />
released by VSP.<br />
f) In the event the CENVAT benefit realized by VSP (based on documents) is in excess <strong>of</strong> the CENVAT benefit<br />
<strong>of</strong>fered by the agency/contractor, the refund will be restricted to the benefit <strong>of</strong>fered by the agency. The<br />
excess amount realized from Excise Authorities will be to the credit <strong>of</strong> VSP only.<br />
g) Material once received in to the factory would not be allowed to go outside the factory premises for any<br />
reason. Excess/Rejected material will be allowed to be taken back after complying with the provisions <strong>of</strong><br />
CE Act.<br />
44. RINL reserves the right to reject the <strong>of</strong>fers <strong>of</strong> tenderers whose performance is poor in<br />
awarded / ongoing <strong>work</strong>s if any<br />
**********<br />
TENDER No : 72211-0<br />
12 <strong>of</strong> 39 Signature <strong>of</strong> the Tenderer
Proposal No 515061240100<br />
Work Desc :<br />
Cond No<br />
1<br />
2<br />
3<br />
4<br />
SCOPE OF WORK TENDER NO :<br />
TENDER No : 72211-0<br />
Common shutdown jobs, Capital repair jobs and Maintenance <strong>of</strong> Heat<br />
Exchangers in Utilities Department <strong>of</strong> VISAKHAPATNAM <strong>Steel</strong> Plant<br />
Cond Desc<br />
This contract specification covers the detailed <strong>scope</strong> <strong>of</strong> <strong>work</strong> for :<br />
1.0 Common shut down jobs <strong>of</strong> Utilities dept<br />
2.0 Annual Capital repair jobs <strong>of</strong> Utilities dept.<br />
3.0 Technological assistance for upkeep <strong>of</strong> heat exchangers<br />
1.0 CONTRACTOR's SCOPE OF WORK FOR COMMON SHUT DOWN JOBS<br />
1.1 Replacement <strong>of</strong> 200 NB & 300 NB VALVE ( Item no. 1 & 2 <strong>of</strong> BOQ )<br />
The job: Valve is to be replaced with new one<br />
a) Preparatory jobs:<br />
Valve is to be serviced, tested & kept ready<br />
Prefabrication <strong>of</strong> 200 NB & 300 NB spool pieces with flanges<br />
b) Jobs to be carried out during shut down :<br />
Removal <strong>of</strong> existing valve and placing them at designated location<br />
Cleaning <strong>of</strong> the flange surfaces<br />
Fixing <strong>of</strong> the spool pieces & valves<br />
1.2 Oxygen filter elements inspection/replacement at PRS-I (Item no.: 3 <strong>of</strong><br />
BOQ)<br />
The job:<br />
37 Nos. <strong>of</strong> oxygen filter elements <strong>of</strong> header-1/PRS-1 are to be removed,<br />
inspected & new elements are to be fixed where ever required within the<br />
shutdown period<br />
a)Preparatory jobs:<br />
Filter housing bolts are to be loosened & tightened one by one to<br />
facilitate easy removal <strong>of</strong> bolts during shutdown<br />
Shifting & keeping ready all the new filter elements at site<br />
b) Jobs to be carried out during shut down :<br />
Removal <strong>of</strong> filter housing by loosening the bolts and with the help <strong>of</strong><br />
mobile crane and kept it at a designated location<br />
Removal <strong>of</strong> elements one by one carefully, inspection & fixing the new ones<br />
where ever required<br />
1.3 Replacement <strong>of</strong> 500 NB,600 NB & 700 NB valve (item no. 4,5 <strong>of</strong> BOQ)<br />
The job:<br />
Removal <strong>of</strong> existing valve and fixing back the serviced valve in position<br />
within the shut down period, spool piece, pipe piece welding may be<br />
required to take care <strong>of</strong> the face to face length mismatch.<br />
a) Preparatory jobs:<br />
Spare valve to be kept ready after testing<br />
Making arrangements for removal & fixing the valve at site<br />
Making ready extra fasteners required<br />
Loosening & tightening <strong>of</strong> flange bolts one by one at site to facilitate<br />
easy removal <strong>of</strong> bolts during shut down<br />
b) Jobs to be carried out during shut down :<br />
13 <strong>of</strong> 39 Signature <strong>of</strong> the Tenderer
Work Desc :<br />
5<br />
6<br />
SCOPE OF WORK TENDER NO :<br />
TENDER No : 72211-0<br />
Common shutdown jobs, Capital repair jobs and Maintenance <strong>of</strong> Heat<br />
Exchangers in Utilities Department <strong>of</strong> VISAKHAPATNAM <strong>Steel</strong> Plant<br />
Removal <strong>of</strong> the existing valve and keeping at designated location<br />
Fixing the serviced valve in position & testing for leak tightness<br />
1.4 Scope <strong>of</strong> <strong>work</strong> for erection <strong>of</strong> new copper pipes at PRS-I (Item no.6<br />
<strong>of</strong> BOQ)<br />
a) Preparatory arrangements to be done before starting <strong>of</strong> the job as per<br />
the directions <strong>of</strong> VSP Engineer<br />
b) Obtain <strong>work</strong> permit / shut down & drop the quick shut <strong>of</strong>f valve,<br />
Pressure control valve, vent lines etc and the existing copper pipe<br />
carefully & place them at the location shown by VSP Engineer.<br />
c) The down stream & upstream flanges are to be isolated from the<br />
process as well as electrically by fixing the 350 NB cl-600 dummies, if<br />
required.<br />
d) The pipes are to be cut by grinding wheel/plasma cutting machine<br />
at the location shown by VSP Engineer. Plasma cutting machine may be<br />
supplied by VSP free <strong>of</strong> cost, de-pending upon availability.<br />
e) The pipe edges are to be prepared for high pressure pipe welding<br />
<strong>of</strong> radiography quality.<br />
f) The new pipe pieces along with flanges are to be tack welded by TIG<br />
welding.<br />
g) After matching <strong>of</strong> the flange holes with new pipe flanges, full<br />
welding <strong>of</strong> the joints to be carried out by TIG welding.<br />
h) The pipes are to be cleaned for oxygen service.<br />
i) The valves, pipes, quick shut <strong>of</strong>f valve, pressure control valve are to<br />
be degreased & fixed.<br />
j) The downstream & upstream valve flanges are to be tightened.<br />
k) The vent lines are to be fixed back.<br />
l) Then leak checking and rectification, radiography are to be carried<br />
out.<br />
m) Other than DC welding machine, equipment, consumables, DP test kit<br />
required for TIG welding is in VSP's <strong>scope</strong>.<br />
n) TIG welding & radiography is to be measured separately.<br />
1.5 Scope <strong>of</strong> <strong>work</strong> for oxygen service cleaning & degreasing <strong>of</strong> seamless<br />
piping size: 250 NB (item no.7 <strong>of</strong> BOQ)<br />
a) Each pipe length / pipe fitting is transported to cleaning site. To be<br />
cleaned thoroughly by brush/cloth and blown with ompressed air.<br />
b) The pipe length / fitting is to be taken to steam tapping point and<br />
to be cleaned it's internal & external surfaces thoroughly with steam.<br />
c) After steam cleaning, it shall be dried with nitrogen for atleast<br />
30minutes and <strong>of</strong>fered for inspection.<br />
d) Degreasing <strong>of</strong> pipe internal shall be done by CTC using polyester<br />
cloth only & then blown with nitrogen for atleast 30 minutes.<br />
14 <strong>of</strong> 39 Signature <strong>of</strong> the Tenderer
Work Desc :<br />
7<br />
8<br />
9<br />
SCOPE OF WORK TENDER NO :<br />
TENDER No : 72211-0<br />
Common shutdown jobs, Capital repair jobs and Maintenance <strong>of</strong> Heat<br />
Exchangers in Utilities Department <strong>of</strong> VISAKHAPATNAM <strong>Steel</strong> Plant<br />
e) After degreasing and inspection for quality <strong>of</strong> degreasing by engineer or<br />
his authorized representative end covers shall be properly sealed with<br />
polythene sheet and tape. Cleaned pipe length/fitting shall be transported<br />
to erection site carefully without damaging the sealings.<br />
f) Further cleaning & degreasing is to be done during erection after<br />
welding each pipe lengths/fitting as per requirement & instruction <strong>of</strong><br />
Engineer.<br />
1.6 Provision <strong>of</strong> 300 NB / 100 NB valve in existing pipe line ( Item no. 8<br />
/ item no. 54 <strong>of</strong> BOQ )<br />
The job:<br />
300 NB / 100 NB valve to be provided in the header / pipe line.<br />
a) Preparatory job:<br />
Valve to be serviced, tested & kept ready<br />
Prefabrication <strong>of</strong> 300 NB / 100 NB spool pieces with flanges welded at<br />
one end.<br />
b) Jobs to be carried out during shut down ( after obtaining valid permit<br />
to <strong>work</strong> / hot <strong>work</strong> permits) :<br />
Cutting the header / pipe line after marking & placing only the<br />
prefabricated valve with spool piece tack welding.<br />
Removal <strong>of</strong> valve<br />
Full welding <strong>of</strong> pipe ends<br />
Fixing back <strong>of</strong> valve & tightening<br />
Note: All jobs as per Sl.nos. 1 to 5 (except item no. 3 are to be carried<br />
during common shut down day within 4/6 hours.)<br />
2.0CONTRACTOR'S SCOPE OF WORK FOR ANNUAL CAPITAL REPAIR JOBS OF UTILITIES<br />
DEPT.<br />
2.1 Technological assistance for upkeep <strong>of</strong> butterfly control valve<br />
(Item no. 9 & 10 <strong>of</strong> BOQ)<br />
Dropping <strong>of</strong> the valve completely from position after removing all bolts<br />
Dismantling <strong>of</strong> the actuator from the valve Handing over the valve &<br />
Actuator to the shop maintenance.<br />
Cutting <strong>of</strong> new gaskets<br />
Assembly <strong>of</strong> valve & actuator after repair by shop Mech<br />
Putting back the valve & Actuator assembly in position, fixing <strong>of</strong> new<br />
gaskets & tightening <strong>of</strong> bolts & leak checking & rectification if required.<br />
2.2 Technological assistance for upkeep <strong>of</strong> Globe control valves (Item<br />
no.: 11 <strong>of</strong> BOQ)<br />
Dropping <strong>of</strong> the valve completely from position after removing all bolts<br />
Handing over the valve & Actuator to the shop maint<br />
Cutting <strong>of</strong> new gaskets<br />
Putting back the valve & Actuator assembly in position, fixing <strong>of</strong> new<br />
15 <strong>of</strong> 39 Signature <strong>of</strong> the Tenderer
Work Desc :<br />
10<br />
11<br />
12<br />
13<br />
SCOPE OF WORK TENDER NO :<br />
Common shutdown jobs, Capital repair jobs and Maintenance <strong>of</strong> Heat<br />
Exchangers in Utilities Department <strong>of</strong> VISAKHAPATNAM <strong>Steel</strong> Plant<br />
gaskets & tightening <strong>of</strong> bolts & leak checking and rectification if<br />
required.<br />
2.3 Technological assistance for upkeep <strong>of</strong> demisters <strong>of</strong> E10/E11 towers<br />
(Item no.: 12 <strong>of</strong> BOQ)<br />
a) One no. <strong>of</strong> Nitrogen water tower & One no. Air water tower are installed<br />
in Air separation unit each <strong>of</strong> which one no. <strong>of</strong> demister. The demister<br />
consists <strong>of</strong> about 50 layers SS wire mesh bundled in SS flat grid.<br />
b) The job :<br />
Disassembly <strong>of</strong> the demister from the position, dropping them<br />
Removal <strong>of</strong> individual layer <strong>of</strong> wire mesh<br />
Mechanical cleaning with hand<br />
Chemical/hot water cleaning <strong>of</strong> wire meshes<br />
Assembly back <strong>of</strong> the mesh into the grid after cleaning<br />
Putting back the demister in position after obtaining clearance<br />
Any repair on grid or grid supporting structure if required shall be<br />
carried out by the contractor<br />
2.4 Technological assistance for upkeep <strong>of</strong> Air water tower/Nitrogen<br />
water tower E10/E11<br />
2.4.1 Sl no. 13 & 14 <strong>of</strong> BOQ (Dismantling & fixing back <strong>of</strong> trays <strong>of</strong> E-10/E-<br />
11) opening <strong>of</strong> man hole covers:<br />
Arrangement <strong>of</strong> lighting & air hose connections from the nearest air<br />
& power connection (Hoses, hand lamp with cable/distributor board will<br />
be provided by VSP)<br />
Arrangement <strong>of</strong> platform for removal <strong>of</strong> the bottom most tray<br />
Removal <strong>of</strong> inspection covers <strong>of</strong> all trays<br />
Marking <strong>of</strong> each trays <strong>of</strong> individual layer with suitable unique<br />
identification number Removal <strong>of</strong> all trays <strong>of</strong> all the layers (9 layers for<br />
E-10 & 7 layers for E-11)<br />
Fixing back <strong>of</strong> the trays as per the marking<br />
Fixing back man hole covers with new gaskets<br />
2.4.2 Sl no. 15 <strong>of</strong> BOQ (cleaning <strong>of</strong> trays <strong>of</strong> E-10/E-11)<br />
a) Mechanical cleaning: Mechanical cleaning will be done in case trays<br />
are not dismantled. The trays in each layer are to be cleaned with wire<br />
brush for removal <strong>of</strong> scales/dust etc<br />
b) Chemical cleaning: In case all the trays are dismantled from position<br />
then chemical cleaning has to be carried out. The trays are to be<br />
immersed in about 5% sulphamic acid solution bath for a period <strong>of</strong> 6 to 8<br />
hours & then blown with steam to remove scale. If required cleaning with<br />
air/brush shall be done.<br />
2.4.3 Sl no. 16 <strong>of</strong> BOQ (internal cleaning <strong>of</strong> E-10/E-11)<br />
TENDER No : 72211-0<br />
16 <strong>of</strong> 39 Signature <strong>of</strong> the Tenderer
Work Desc :<br />
14<br />
SCOPE OF WORK TENDER NO :<br />
TENDER No : 72211-0<br />
Common shutdown jobs, Capital repair jobs and Maintenance <strong>of</strong> Heat<br />
Exchangers in Utilities Department <strong>of</strong> VISAKHAPATNAM <strong>Steel</strong> Plant<br />
Arrangement for rope ladder scaffolding etc, dismantling drains.<br />
Cleaning <strong>of</strong> internal surface <strong>of</strong> E-10/E-11 towers<br />
Removal <strong>of</strong> all dust/dirt etc from bottom <strong>of</strong> tower & cleaning<br />
Cleaning <strong>of</strong> man hole cover flange surface<br />
Cleaning <strong>of</strong> trays supporting angle<br />
Fixing outlet drain line with new gaskets<br />
Note: Cleaning shall be done with the help <strong>of</strong> wire brush & power<br />
buffing.<br />
2.5 Technological assistance for upkeep <strong>of</strong> Safety valves (Item no.: 17<br />
<strong>of</strong> BOQ)<br />
The safety valves are installed in different locations in the cold box at<br />
various heights up to +30 M level. All valves are threaded type or<br />
flanged type.<br />
Safety valves are to be dropped from location after taking necessary<br />
permits & are to be handed over to Shop maint.<br />
To assist in Shop maint. while testing/servicing if required<br />
Preparing & keeping ready gaskets if required<br />
Collecting back the tested valve from Shop maint & fixing back in position<br />
Note: All Cryo/Oxygen side valves are to be handled carefully & while<br />
handling these valves during assembly, the hands <strong>of</strong> the man shall be oil<br />
free & cleaned in CTC. All tools shall also be cleaned with CTC. CTC<br />
shall be provided by VSP. Necessary instructions <strong>of</strong> VSP site Engineer in<br />
this aspect shall be followed. This clause is applicable to item no.:<br />
1.06, 1.07 & 3.04 <strong>of</strong> BOQ in particular & other areas concerning oxygen<br />
valves in general.<br />
2.6 Technological assistance for upkeep <strong>of</strong> Driers (Item no.18 <strong>of</strong> BOQ)<br />
a) 2 Nos. adsorbers <strong>of</strong> approx size 130 M3 (4 Mtr dia X 20 Mtr<br />
long) are installed in each Air separation unit. The inside <strong>of</strong> drier is<br />
grid & mesh structure placed on flats & beams.<br />
b)The job :<br />
inspection <strong>of</strong> the complete grid structure<br />
Job to be started after removing <strong>of</strong> adsorbents<br />
Cleaning <strong>of</strong> drier inside<br />
Removal <strong>of</strong> grids<br />
Repair welding by placing flats & ensuring the closing <strong>of</strong> all gaps<br />
Placing <strong>of</strong> grids back in position<br />
Replacement <strong>of</strong> gland rope between grids<br />
Bolting back the grids .<br />
2.7 Technological assistance for removing, repair/replacement & fixing<br />
<strong>of</strong> SS mesh<br />
between adsorbent beds (Item no. 19 <strong>of</strong> BOQ)<br />
17 <strong>of</strong> 39 Signature <strong>of</strong> the Tenderer
Work Desc :<br />
15<br />
16<br />
SCOPE OF WORK TENDER NO :<br />
TENDER No : 72211-0<br />
Common shutdown jobs, Capital repair jobs and Maintenance <strong>of</strong> Heat<br />
Exchangers in Utilities Department <strong>of</strong> VISAKHAPATNAM <strong>Steel</strong> Plant<br />
After removing the molecular sieves, the mesh is to untied by removing the<br />
SS wires at the edges.<br />
The mesh, then, carefully rolled without folding, from one end and to be<br />
removed from the drier bottle.<br />
The mesh is to be placed at the location shown by VSP Engineer and<br />
the damages, if any are to be repaired.<br />
As decided by VSP engineer, either repaired (or) new mesh is to be fixed<br />
back. Supply <strong>of</strong> new mesh is in VSP <strong>scope</strong>.<br />
While filling the mesh, ensure that there are no foldings or damages to<br />
the mesh. The mesh are to be tied to the bed carefully by SS wire at the<br />
ends.<br />
2.8 Technological assistance for upkeep <strong>of</strong> Manual valves (15 NB to 200<br />
NB) (Item no.20 to 23 <strong>of</strong> BOQ)<br />
Removal <strong>of</strong> valves from position (valves are installed in different<br />
locations in ASU at different heights ranging from ground level up to<br />
height <strong>of</strong> 30 meters)<br />
Shifting <strong>of</strong> valve to maint. area, dismantling <strong>of</strong> valve, cleaning <strong>of</strong><br />
internals<br />
Replacement <strong>of</strong> packing, bonnet gaskets etc<br />
Lapping <strong>of</strong> valve seat if required<br />
Assembling back <strong>of</strong> valve & greasing <strong>of</strong> spindle wherever required<br />
Putting back the valve in position after changing the flange gaskets (new<br />
gaskets are to be cut & replaced)<br />
Leak checking<br />
2.9 Scope <strong>of</strong> <strong>work</strong> for strl./sheeting repair (item no 24 & 25 <strong>of</strong> BOQ)<br />
Contractor shall dismantle the damaged sheetings <strong>of</strong> the cold boxes <strong>of</strong> Air<br />
Separation Units and replace it with new ones. Contractor shall erect<br />
approach ladders, <strong>work</strong>ing platforms and walkways for safe operation and<br />
maint. <strong>of</strong> indifferent units <strong>of</strong> Utilities dept. Most <strong>of</strong> the structural &<br />
sheeting mainly consists <strong>of</strong> light structural (including GC sheets).<br />
Old structures shall be dismantled where ever necessary. All the welding<br />
joints and sheeting wherever necessary shall be painted immediately after<br />
repair. The painting shall be one coat <strong>of</strong> red oxide primer plus two<br />
finish coats <strong>of</strong> synthetic enamel. The entire <strong>work</strong> shall be done as per<br />
the instructions <strong>of</strong> Engineer-in-charge or his authorised representative.<br />
Contractor shall provide for adequate manpower to complete the job<br />
with a qualified supervisor. The job involves <strong>work</strong>ing at different<br />
heights ranging from +4.0m to +30.0m. The contractor shall make<br />
arrangements for necessary scaffoldings etc.<br />
2.10 Scope <strong>of</strong> <strong>work</strong> for piping replacement jobs(item nos: 26 to 31, 55 <strong>of</strong><br />
18 <strong>of</strong> 39 Signature <strong>of</strong> the Tenderer
Work Desc :<br />
17<br />
SCOPE OF WORK TENDER NO :<br />
TENDER No : 72211-0<br />
Common shutdown jobs, Capital repair jobs and Maintenance <strong>of</strong> Heat<br />
Exchangers in Utilities Department <strong>of</strong> VISAKHAPATNAM <strong>Steel</strong> Plant<br />
BOQ )<br />
The contractor shall carry out replacement <strong>of</strong> new pipe lines inclusive <strong>of</strong><br />
fitting, valves, flanges, fasteners etc & wherever required dismantling<br />
<strong>of</strong> old lines has to be done by the contractor<br />
All pipe lines supports & clamps shall be provided by the contractor at<br />
site as per requirement. Necessary steel for the same shall be provided<br />
free <strong>of</strong> cost by VSP.<br />
After root run, thorough cleaning <strong>of</strong> the weld point shall be done & only<br />
then additional layers shall be built. Welds shall be built up by multiple<br />
leads and complete fusion & penetration shall be ensured<br />
Hydraulic testing <strong>of</strong> the pipe lines shall be done as per requirement &<br />
all points shall have to pass the test. Test equipment required to carry<br />
out the testing shall be pro-vided by VSP free <strong>of</strong> cost.<br />
Welding <strong>work</strong> shall be done by qualified welders having experience in piping<br />
<strong>work</strong>.<br />
For TIG welding jobs contractor shall deploy highly qualified and<br />
experienced welder. All TIG welding joints shall be 100% radiographed<br />
after welding. Any re<strong>work</strong>ing <strong>of</strong> TIG welding joint after radiography on<br />
account <strong>of</strong> poor <strong>work</strong>man-ship shall be to contractor's account and such<br />
reweldings will not be accounted for measurements. TIG welding &<br />
radiography are to be measured separately.<br />
Fabrication <strong>of</strong> necessary bends / Tees required shall be carried out by the<br />
contractor at site for higher sizes pipings.<br />
All the jobs shall be carried out to the satisfaction <strong>of</strong> Engineer-in-charge<br />
& he shall be the final authority for deciding the completion <strong>of</strong> job.<br />
2.11 Scope <strong>of</strong> <strong>work</strong> for technological upkeep <strong>of</strong> ASU cold box<br />
structures(item no 32 <strong>of</strong> BOQ)<br />
a) All the cold box column beams and walkways structures to be inspected<br />
thoroughly for each Air Separation Unit(ASU) once in 3 months and following<br />
activities to be done.<br />
b) The job :<br />
Thorough cleaning if required manual/power brushing to be done.<br />
All the water passage holes to be cleaned.<br />
2.12Scope <strong>of</strong> <strong>work</strong> for TIG welding <strong>of</strong> SS / CS piping & radiography <strong>of</strong> piping<br />
(item no. 33 & 34 <strong>of</strong> BOQ)<br />
For item no.33 :<br />
a) Welding <strong>work</strong> shall be done by qualified welders having experience in<br />
piping <strong>work</strong>.<br />
b) All TIG welding joints shall be 100 % radiographed. After welding if any<br />
re<strong>work</strong>ing <strong>of</strong> TIG welding joint after radiography on account <strong>of</strong> poor<br />
<strong>work</strong>manship shall be to contractor's account and such rewelding will not be<br />
19 <strong>of</strong> 39 Signature <strong>of</strong> the Tenderer
Work Desc :<br />
18<br />
SCOPE OF WORK TENDER NO :<br />
TENDER No : 72211-0<br />
Common shutdown jobs, Capital repair jobs and Maintenance <strong>of</strong> Heat<br />
Exchangers in Utilities Department <strong>of</strong> VISAKHAPATNAM <strong>Steel</strong> Plant<br />
accounted for measurement.<br />
c) Price estimate is based on 2 nos <strong>of</strong> weld runs ( viz root run and build<br />
up run ) <strong>of</strong> a joint. If more than 2 weld runs are to be made on a joint ,<br />
accounting shall be done on prorata basis.<br />
d) All the jobs shall be carried out to the satisfaction <strong>of</strong> the Engineer -in<br />
-- charge and he shall be the final authority for deciding completion <strong>of</strong><br />
job.<br />
For item no.34 :<br />
a)Party has to carry out radiography <strong>of</strong> weld joints as per the instructions<br />
<strong>of</strong> Engineer-I/C or his representative<br />
b)Party shall take approval <strong>of</strong> Engineer-I/C before selecting external<br />
agency for radiography jobs<br />
c)Party shall submit films & reports <strong>of</strong> radiographed joint within 2 days<br />
(maximum) <strong>of</strong> taking <strong>of</strong> radiography<br />
Scope <strong>of</strong> <strong>work</strong> for item no. 35 & 36 :<br />
For item no. 35 : Ultra sonic thickness measurement is to be carried out<br />
for pipelines, structures, equipment as per the direction <strong>of</strong> VSP engineer.<br />
Machine will be provided by VSP.<br />
For item no.36 : Power brushing <strong>of</strong> sheeting / structurals / vessels /<br />
piping etc to be done as per direction <strong>of</strong> VSP Engineer. Power brushing<br />
machine , consumables ( buffing wheels ), safety appliances like gloves,<br />
goggles etc are in contractor's <strong>scope</strong>.<br />
3.0 TECHNOLOGICAL ASSISTANCE FOR UPKEEP OF HEAT EXCHANGERS OF UTILITIES<br />
DEPT.<br />
3.1 General :<br />
The objective <strong>of</strong> the repair contract is to carry out the chemical<br />
cleaning <strong>of</strong> the exchangers <strong>of</strong> centrifugal turbo-compressors, motor<br />
coolers and chillers <strong>of</strong> utilities dept as per the detailed<br />
<strong>scope</strong>/specification given herein.<br />
3.2 Introduction :<br />
3.2.1 Centrifugal turbo-compressors <strong>of</strong> different makes/capacities are<br />
installed in utilities department handling various fluids like air,<br />
nitrogen, oxygen. Each compressor is equipped with shell and tube type<br />
heat exchangers for inter stage cooling and oil coolers for cooling<br />
lubricating oil.<br />
3.2.2 The compressor motors are provided with motor cooler (shell and tube<br />
type exchanger).<br />
3.2.3 Chillers <strong>of</strong> voltas/ Sulzer make are installed and these are<br />
equipped with condensers/evaporators.<br />
3.2.4 The compressors and motors are enclosed in noisehood arrangement from<br />
acoustic point <strong>of</strong> view. The noisehood arrangement consists <strong>of</strong> panels and<br />
20 <strong>of</strong> 39 Signature <strong>of</strong> the Tenderer
Work Desc :<br />
19<br />
20<br />
SCOPE OF WORK TENDER NO :<br />
TENDER No : 72211-0<br />
Common shutdown jobs, Capital repair jobs and Maintenance <strong>of</strong> Heat<br />
Exchangers in Utilities Department <strong>of</strong> VISAKHAPATNAM <strong>Steel</strong> Plant<br />
its associated structure (both sides and top) with the panels either<br />
clamped / bolted. The noisehood panels are to be completely removed<br />
before the coolers are to taken out for chemical cleaning.<br />
3.3 Scope <strong>of</strong> <strong>work</strong> :<br />
3.3.1 For item no 37 and 38 <strong>of</strong> BOQ:<br />
The noisehood panels and its supporting structure are to be<br />
completely removed. (EOT crane with operator will be provided by VSP).<br />
However in case <strong>of</strong> exigency the contractor shall have to arrange his own<br />
crane operator.<br />
3.3.2 For item nos. 39 to 49 <strong>of</strong> BOQ:<br />
a) Follow the detailed procedure for chemical cleaning <strong>of</strong> heat<br />
exchangers given in annexure-1A . Analysis <strong>of</strong> chemical strength is to be<br />
carried out if required as per the direction <strong>of</strong> engineer or his authorized<br />
representative. Cleaning/blowing <strong>of</strong> the tube outsides for all finned<br />
exchangers with air & water assisting VSP personnel in repair <strong>of</strong> water<br />
jackets, tube puncture and tube sheets like brushing, cleaning etc <strong>of</strong> tube<br />
sheet & end cover. Thorough cleaning <strong>of</strong> exchanger shell, before fixing<br />
back the tube bundle is to be carried out. If required, the shell is<br />
to be flushed with water to remove chockage in drain valves etc.<br />
Collection & disposal <strong>of</strong> used chemicals shall be in the <strong>scope</strong> <strong>of</strong><br />
contractor.<br />
b) Assisting VSP persons with man power <strong>of</strong> all categories and equipments<br />
required for all jobs related to the repair and preservation shall be in<br />
contractor's <strong>scope</strong>. VSP will provide supervisor , co ordination and<br />
consumables required for such repairs /preservations.<br />
3.3.3 For item no 50 <strong>of</strong> BOQ :<br />
a) Demister pad is to be dropped from position by removing SS bolts after<br />
cooler bundle removal from the shell and is to be brought outside.<br />
b) Demester pad is to be cleaned by dry air , water jet or by tapping with<br />
wooden hammer as per the instructions <strong>of</strong> the site in charge and the<br />
cleaning may be for number <strong>of</strong> cycles as per the condition <strong>of</strong> demester , as<br />
directed by the site in charge.<br />
c) After cleaning, demister is to be fixed back in position with SS J<br />
bolts.<br />
d) Demester seating area is to be repaired by buffing,painting and welding<br />
as per the instructions <strong>of</strong> the site in charge.<br />
4.1.1 For chemical cleaning jobs , chemicals and tanks with heaters are in<br />
VSP <strong>scope</strong>. Pumps with hoses and fittings are in contractors <strong>scope</strong>.<br />
Contractor should be able to deploy suficient no. <strong>of</strong> people, pumps etc to<br />
carry out chemical cleaning activities simultaneously at 3 different<br />
locations.Contractor has to deploy qualified and experienced <strong>work</strong>men &<br />
21 <strong>of</strong> 39 Signature <strong>of</strong> the Tenderer
Work Desc :<br />
21<br />
22<br />
SCOPE OF WORK TENDER NO :<br />
TENDER No : 72211-0<br />
Common shutdown jobs, Capital repair jobs and Maintenance <strong>of</strong> Heat<br />
Exchangers in Utilities Department <strong>of</strong> VISAKHAPATNAM <strong>Steel</strong> Plant<br />
supervisors.<br />
5.1.1 Contractor to deploy Man power to carry out the job in all the 3<br />
shifts (round the clock operation as per instructions <strong>of</strong> engineeri/c.<br />
5.1.2 Cutting <strong>of</strong> gaskets:- all gaskets to be cut & kept ready. Material<br />
will be provided by VSP.<br />
5.1.3 Any other item not mentioned but required for satisfactory<br />
completion <strong>of</strong> job shall be in Contractor's <strong>scope</strong>.<br />
6.0 SPECIAL CONDITIONS<br />
6.1 For common S/D jobs<br />
6.1.1 Deployment <strong>of</strong> welding machines/cutting set/grinding machines<br />
Common shut down jobs:- Item sl no. 1 to 8 & 31 <strong>of</strong> BOQ are common shut<br />
down jobs to be carried on the shut down day within the shut down period<br />
<strong>of</strong> 4 to 8 hours as the case may be. For these jobs, contractor shall<br />
mobilise minimum following numbers <strong>of</strong> equipments (which are minimum<br />
estimates) on the shut down day to carry out all the shut down jobs.<br />
Welding machines: 6 Nos. <strong>of</strong> which minimum 3 nos. shall be DC machines<br />
Gas cutting sets : 4 nos.<br />
Grinding machines 4 nos.<br />
Sufficient manpower commensurate with the jobs on that day including 6<br />
welders & 4 fitters shall be deployed.<br />
6.1.2 For job sl.no: 5,6 & 31 <strong>of</strong> BOQ, TIG welder with radiography<br />
grade welding shall be deployed. The welder will be tested at site by<br />
Engineer-in-charge or his representative<br />
6.2 For Capital repair jobs<br />
6.2.1 For all the jobs <strong>of</strong> capital repairs, the contractor shall ensure<br />
availability <strong>of</strong> minimum 3 nos. <strong>of</strong> welding machines <strong>of</strong> which one shall be<br />
DC. During ASU capital repairs minimum 4 nos. welding machines, 4 welders<br />
and 3 fitters are to be ensured.<br />
6.3 For Chemical cleaning jobs<br />
6.3.1 Contractor shall deploy minimum 3 sets <strong>of</strong> pumps & hoses arrangement<br />
so as to carry out chemical cleaning <strong>of</strong> 3 exchangers simultaneously at<br />
different locations.<br />
6.3.2 The contractor shall ensure that the pumps & tank set up shall be<br />
sufficient to take care <strong>of</strong> all exchangers as per boq.<br />
6.3.3 The contractor shall employ competent persons for the purpose <strong>of</strong><br />
analysis if needed & shall be approved by engineer i/c.<br />
6.3.4 The entire <strong>work</strong> shall be inspected by Engineer-I/c or his<br />
representative for completion <strong>of</strong> descaling operation, passivation, testing,<br />
lining up and same shall be entered in the format and necessary signatures<br />
obtained.<br />
22 <strong>of</strong> 39 Signature <strong>of</strong> the Tenderer
Work Desc :<br />
23<br />
24<br />
25<br />
26<br />
SCOPE OF WORK TENDER NO :<br />
TENDER No : 72211-0<br />
Common shutdown jobs, Capital repair jobs and Maintenance <strong>of</strong> Heat<br />
Exchangers in Utilities Department <strong>of</strong> VISAKHAPATNAM <strong>Steel</strong> Plant<br />
7.0 SAFETY<br />
7.1 FOR CAPITAL REPAIR JOBS AND COMMON SHUT DOWN JOBS OF CR-2008-09<br />
7.1.1 All <strong>work</strong>men shall be sent to safety department for safety<br />
induction training programs and only the qualified persons shall be<br />
allowed to <strong>work</strong> at site.<br />
7.1.2 The use <strong>of</strong> all safety appliances required(helmets, goggles, safety<br />
belts, boots, gloves etc.) and precautions required shall be ensured by the<br />
contractor.<br />
7.1.3 Only fully insulated electrode holders must be used by the welders<br />
for welding <strong>work</strong> involved.<br />
7.1.4 All <strong>work</strong>men shall possess valid height pass.<br />
7.1.5 Daily <strong>work</strong> permit should be taken from shift-in-charge before<br />
starting the job.<br />
7.1.6 Permit to <strong>work</strong> at height shall be obtained when <strong>work</strong>ing above 3.0<br />
m height.<br />
7.1.7 Smoking is strictly prohibited with in the premises <strong>of</strong> Air<br />
Separation Plant &Acetylene plant.<br />
7.2 For technological assistance for upkeep <strong>of</strong> heat exchangers <strong>of</strong><br />
utilities dept.<br />
7.2.1 Contractor personnel shall have to undergo safety induction training<br />
arranged by safety engg department before starting the job.<br />
7.2.2 The contractor shall comply with all the safety rules <strong>of</strong> VSP for<br />
contract personnel and shall also follow the safety instructions given<br />
by engineer in-charge from time to time.<br />
7.2.3 The contractor shall take all necessary precautions to protect the<br />
nearby equipment from chemicals etc.<br />
8.0 GENERAL:<br />
8.1 All jobs from sl.no: 1 to 8 are shut down jobs during the common shut<br />
down day. Piping jobs (sl no 26 to 31 is also expected during common s/d<br />
day)<br />
8.2 All jobs from sl.no 9 to 38 are to be carried out when the ASU is<br />
taken for C.R. for a period <strong>of</strong> 20 days. All the jobs shall be done with<br />
in the C.R period. The start <strong>of</strong> C.R will be intimated one week in<br />
advance for mobilisation <strong>of</strong> man power.<br />
8.3 Each motor cooler will have one pair (2 nos. Of coolers)<br />
8.4 Any deviations from the proposed procedure shall be spelt out clearly.<br />
8.5 Technical details <strong>of</strong> heat exchangers, if required can be taken from VSP<br />
engineer.<br />
PROCEDURE FOR CHEMICAL CLEANING OF HEAT EXCHANGERS( ITEM NOS 39 TO 49 )<br />
9.1.0 Obtain the <strong>work</strong> permit for <strong>work</strong>ing on the heat exchanger to be<br />
23 <strong>of</strong> 39 Signature <strong>of</strong> the Tenderer
Work Desc :<br />
27<br />
SCOPE OF WORK TENDER NO :<br />
Common shutdown jobs, Capital repair jobs and Maintenance <strong>of</strong> Heat<br />
Exchangers in Utilities Department <strong>of</strong> VISAKHAPATNAM <strong>Steel</strong> Plant<br />
cleaned.2.1 For all heat exchangers wherein the chemical cleaning is to be<br />
done in position, the water inlet,outlet bends removal & blanking <strong>of</strong> water<br />
headers in the upstream side is to be done by the Contractor.<br />
9.2.0 For exchangers wherein the exchangers cleaning is not done in<br />
position the Contractor shall assist VSP in shifting the tube bundles.<br />
9.3.0 Open both the end covers.<br />
TENDER No : 72211-0<br />
9.4.0 Inspect the exchanger tubes in presence <strong>of</strong> VSP engineer. Based on the<br />
inspection,<br />
VSP engineer will confirm the procedure to be followed for chemical<br />
cleaning i.e. as per procedure -1 or Procedure-2 ( More fouled tubes will<br />
be cleaned as per procedure-1 and less fouled tubes will be cleaned as<br />
per procedure-2)<br />
9.5.0 After inspection and confirmation <strong>of</strong> the procedure to be followed,<br />
clean the tubes mechanically and get them inspected & cleared for putting<br />
back end covers by VSP engineer.<br />
9.6.0 Put back the end covers and connect the chemical cleaning set-up to<br />
the heat exchanger.<br />
9.7.0 Calculate the hold up volume <strong>of</strong> heat exchangers i.e. say ' M ' m3<br />
with the help <strong>of</strong> technical data available with Engineers or his authorised<br />
representative.<br />
9.8.0 Fill the chemical cleaning tank with water and start water<br />
circulation with pump. Continue the addition <strong>of</strong> water till the total<br />
quantity <strong>of</strong> water added is 'M' m3. Ensure that there are no water<br />
leakages in the circulating water system.<br />
9.9.0 Break the lumps <strong>of</strong> sulphamic acid into small pieces. Add sulfamic<br />
acid 100 X M Kgs slowly (1/2 hour approx.)<br />
9.10.0 Raise the temperature <strong>of</strong> the sulfamic acid solution to 50 to 60 C<br />
9.11.0 Minimum level <strong>of</strong> solution in the tank is to insured to protect<br />
electric heater elements. Steam can be used for heating, wherever<br />
available.<br />
9.12.0 Period <strong>of</strong> circulation<br />
24 <strong>of</strong> 39 Signature <strong>of</strong> the Tenderer
Work Desc :<br />
28<br />
SCOPE OF WORK TENDER NO :<br />
TENDER No : 72211-0<br />
Common shutdown jobs, Capital repair jobs and Maintenance <strong>of</strong> Heat<br />
Exchangers in Utilities Department <strong>of</strong> VISAKHAPATNAM <strong>Steel</strong> Plant<br />
9.12.1 Procedure-1<br />
If the scaling is more and the engineer decides to add more sulfamic acid,<br />
add 20 X M kgs <strong>of</strong> sulphamic acid after 6 hours <strong>of</strong> circulation and continue<br />
circulation for 3 hours more after addition <strong>of</strong> sulphamic acid (total 9<br />
hours).<br />
9.12.2 Procedure-2<br />
If the scaling is not more & the engineer decides not to add sulfamic acid<br />
after 6 hrs, continue circulation for another 3 hrs (total 9 hours).<br />
9.13.0 Then drain the sulfamic acid, clean the tank with fresh water.<br />
Residues <strong>of</strong> all foreign materials are to be removed from the tank and<br />
connecting piping.<br />
9.14.0 Fill the circulation tank with fresh water & circulate fresh water<br />
through heat exchanger.Continue the operation till the system is clean.<br />
Addition and draining <strong>of</strong> water is to be done during circulation for better<br />
cleaning <strong>of</strong> system.<br />
9.15.0 Clean the tank with fresh water. Fill the tank with fresh<br />
water and start water Circulation with pump. Continue the addition <strong>of</strong><br />
water till the total quantity <strong>of</strong> water added is 'M' m3. Add slowly 0.5 X M<br />
Kgs sodium hydroxide into the water in the circulation tank. Continue the<br />
circulation for 4 hrs after addition <strong>of</strong> sodium hydroxide. Ensure that<br />
there are no leaks in the circulation system before addition <strong>of</strong> sodium<br />
hydroxide.<br />
9.16.0 Drain the sodium hydroxide solution and clean the tank with fresh<br />
water. Residues <strong>of</strong> all foreign materials are to be removed from the tank &<br />
connecting piping. Fill the tank with fresh water and start circulation <strong>of</strong><br />
water with pump. Continue the addition <strong>of</strong> water till the total quantity <strong>of</strong><br />
water added is 'M' m3. Add slowly 0.5 X M Kgs Trisodium phosphate into the<br />
water in the circulation tank.<br />
9.17.0 Circulate this solution for 8 hrs into the heat exchanger for<br />
passivation <strong>of</strong> all surfaces.Minimum level <strong>of</strong> solution in the tank is to<br />
be ensured to protect electric heater elements.Steam can be used for<br />
heating ,wherever available.<br />
9.18.0 End covers are to be opened for inspection ,manually cleaned/blown<br />
with compressed air to dislodge loose scales and are to be boxed up after<br />
inspection as per requirement <strong>of</strong> VSP engineer.<br />
9.19.0 Hydraulic testing <strong>of</strong> exchanger is to be carried out as per<br />
directions and instruction <strong>of</strong> VSP engineer.<br />
25 <strong>of</strong> 39 Signature <strong>of</strong> the Tenderer
Work Desc :<br />
29<br />
30<br />
SCOPE OF WORK TENDER NO :<br />
TENDER No : 72211-0<br />
Common shutdown jobs, Capital repair jobs and Maintenance <strong>of</strong> Heat<br />
Exchangers in Utilities Department <strong>of</strong> VISAKHAPATNAM <strong>Steel</strong> Plant<br />
9.20.0 Assisting in repair <strong>of</strong> end covers partition walls before starting<br />
chemical cleaning, if required.<br />
9.21.0 End covers gaskets are to be replaced before starting chemical<br />
cleaning / after chemical cleaning depending on condition.<br />
9.22.0 Special protective paints if any are to be applied before / after<br />
chemical cleaning as per direction <strong>of</strong> VSP engineer, necessary surface<br />
cleaning / power buffing is to be done. Application <strong>of</strong> special protective<br />
paints is to be arranged by VSP.<br />
9.23.0 End covers, connecting piping is also to be cleaned thoroughly<br />
before boxing up.<br />
9.24.0 Quantities <strong>of</strong> descalent (sulphamic acid), Sodium hydroxide, trisodium<br />
phosphate to be added are to be decided by the VSP engineer each<br />
time based on the holdup volume <strong>of</strong> system which includes the following<br />
a) Circulation tank capacity and level to which the tank will be filled.<br />
b) Volume <strong>of</strong> suction and discharge connections between pump, circulation<br />
tank and exchanger to be cleaned.<br />
c) Volume <strong>of</strong> exchanger tubes, dished end etc..<br />
9.25.0 System is to be inspected for every 1/2 hour for leakages <strong>of</strong> water<br />
and chemical solutions and inspected leakages are to be attended<br />
immediately.<br />
9.26.0 During fresh water circulation deaeration <strong>of</strong> exchanger is to be<br />
ensured. After deaeration only, chemicals to the circulation tank shall be<br />
added.<br />
9.27.0 Cleaning procedure and quantity <strong>of</strong> chemicals etc,. may be ammended<br />
based on the technical requirement at the discretion <strong>of</strong> the Engineer -in -<br />
charge.<br />
10.0 For item no.56 : Technological assistance for manual cleaning <strong>of</strong> heat<br />
exchangers<br />
Centrifugal turbo-compressors <strong>of</strong> different makes/capacities are installed<br />
in utilities department handling various fluids like air, nitrogen, oxygen.<br />
Each compressor is equipped with shell and tube type heat exchangers for<br />
inter stage cooling and oil coolers for cooling lubricating oil.<br />
The compressor motors are provided with motor cooler (shell and tube type<br />
exchanger).<br />
Chillers <strong>of</strong> Voltas/Sulzer/York/Carrier make are installed in Chilled Water<br />
Plants / ASP and these are equipped with condensers/evaporators.<br />
The <strong>scope</strong> <strong>of</strong> <strong>work</strong> for this item covers all the heat exchangers mentioned<br />
26 <strong>of</strong> 39 Signature <strong>of</strong> the Tenderer
Work Desc :<br />
31<br />
32<br />
SCOPE OF WORK TENDER NO :<br />
TENDER No : 72211-0<br />
Common shutdown jobs, Capital repair jobs and Maintenance <strong>of</strong> Heat<br />
Exchangers in Utilities Department <strong>of</strong> VISAKHAPATNAM <strong>Steel</strong> Plant<br />
above.<br />
10.1 After taking shutdown, end covers are to be dropped and all tubes<br />
chokage to be assessed in presence <strong>of</strong> VSP personnel. Tubes chokage to be<br />
cleaned by manual brushing with nylon / metal brushes <strong>of</strong> suitable size(<br />
brushes in VSP <strong>scope</strong> ) and all tubes opening to be made through with no<br />
visible block / chokage. This is to be followed by air / water jet cleaning<br />
<strong>of</strong> all tubes taking due care to avoid splashing <strong>of</strong> water etc on surrounding<br />
equipment / panels /people etc. After confirming tubes cleaning is done to<br />
the satisfaction <strong>of</strong> VSP personnel , the end covers are to be boxed up with<br />
new gaskets. System normalistion / water charging will be done in<br />
coordination with VSP personnel and leaks, if any, are to be rectified.<br />
11.0 For item no. 57 : Technological assistance for leak identification in<br />
heat exchangers and rectification by tubes blanking.<br />
The <strong>scope</strong> <strong>of</strong> <strong>work</strong> for this item is applicable to the heat exchangers<br />
mentioned below.<br />
a) Gas and oil coolers <strong>of</strong> centrifugal turbo-compressors <strong>of</strong> different<br />
makes/capacities installed in Utilities department handling various fluids<br />
like air, nitrogen, oxygen. Each compressor is equipped with shell and tube<br />
type heat exchangers for inter-stage cooling and oil coolers for cooling<br />
lubricating oil.<br />
b) Motor coolers (shell and tube type exchanger) <strong>of</strong> the main motors <strong>of</strong><br />
various centrigugal gas compressors <strong>of</strong> Utilities dept<br />
c) Condensers / evaporators <strong>of</strong> Chillers <strong>of</strong> Voltas/Sulzer/York/Carrier make<br />
installed in Chilled Water Plants / ASP.<br />
11.1 After obtaining necessary <strong>work</strong> permit, the tube bundles <strong>of</strong> the heat<br />
exchangers are to be removed from their shells and both sides end covers<br />
are to be opened. All tubes are to be checked if they are are through or<br />
not and if required to be made through by manual cleaning. The tube bundle<br />
is to be placed on the testing bed for leak identification and all tubes<br />
are to be tested one by one by pressurising each tube with air and<br />
observing for any bubbles in the bundle kept immersed in water on the bed.<br />
If any leak is identified the tube is to be marked for rectification. After<br />
all tubes are tested in the presence <strong>of</strong> VSP personnel, the identified<br />
leaking tubes are to be plugged on both sides with correct size copper<br />
plugs ( supplied by VSP ) taking due care not to damage the adjacent tubes<br />
while plugging the leaking tubes.<br />
After plugging the damaged tubes , it is to be leak tested again in the<br />
presesnce <strong>of</strong> VSP personnel and confirmed that no tube leaks are existing.<br />
Hydraulic test at the pressure told by Engineer / his representative is to<br />
27 <strong>of</strong> 39 Signature <strong>of</strong> the Tenderer
Work Desc :<br />
33<br />
34<br />
SCOPE OF WORK TENDER NO :<br />
TENDER No : 72211-0<br />
Common shutdown jobs, Capital repair jobs and Maintenance <strong>of</strong> Heat<br />
Exchangers in Utilities Department <strong>of</strong> VISAKHAPATNAM <strong>Steel</strong> Plant<br />
be done and the pressure is to be held for the requisite period as<br />
suggested by the Engineer without any drop. This will be witnessed by VSP<br />
personnel. The end covers are to be then boxed up using new gaskets and<br />
tube bundle to be inserted into the shell <strong>of</strong> the heat exchanger.<br />
12.0 For item no.58 : Technological assistance for cleaning <strong>of</strong> impellers <strong>of</strong><br />
PAC's <strong>of</strong> CH-2<br />
12.1 The job involves preparation / grinding <strong>of</strong> special tools required for<br />
impeller cleaning, cleaning <strong>of</strong> impellers <strong>of</strong> all 4 stages and all back<br />
plates manually using the special tools to the satisfaction <strong>of</strong> Engineer /<br />
his representative.<br />
13.0 The following equipment along with accessories / materials shall be<br />
arranged by contractor for the purpose <strong>of</strong> carrying out the specified<br />
contractual jobs and shall be taken back by them on completion <strong>of</strong> the<br />
contract.<br />
Welding machines,cables, welding shields, gas cutting sets , regulators<br />
Grinding machines, machines for power brushing . All tools and tackles<br />
including chain pulley blocks , slings etc required for carrying out the<br />
jobs.<br />
Ropes , ladders , hacksaw frames. All safety appliances like safety shoes<br />
, helmets, goggles, safety belts, safety nets, gloves , welding shields,<br />
nose masks, ear plugs etc, Pump sets, pipes, fittings, flanges, hoses etc<br />
for chemical circulation and necessary tools & tackles. All<br />
instruments/accessories like ph meter, ph paper, Chemical balance, burette,<br />
pipette, test tubes, beakers etc as per requirement.<br />
14.0 Sales tax Clause :<br />
The <strong>scope</strong> <strong>of</strong> materials supply and consumables supply in the present<br />
proposal are as follows :<br />
a) Materials to be supplied by VSP ( free <strong>of</strong> cost ) :<br />
14.1.1 Structural steel and sheetings<br />
14.1.2 Fasteners , CTC, Lubricants, Filters and Mechanical Spares<br />
14.1.3 All pipes , pipe fittings ,flanges,valves,dummies and gaskets.<br />
14.1.4 Paints<br />
14.1.5 The equipment for hydraulic testing.<br />
14.1.6 All welding equipment , accessories required for TIG welding ( other<br />
than DC welding machine)<br />
14.1.7 Drilling machines<br />
14.1.8 Plasma cutter with accessories<br />
14.1.9 SS wire mesh for dryer repair<br />
14.1.10 SS wire brush for SS welding<br />
14.1.11 Chemicals required for carrying out chemical cleaning <strong>of</strong> heat<br />
exchangers<br />
28 <strong>of</strong> 39 Signature <strong>of</strong> the Tenderer
Work Desc :<br />
35<br />
SCOPE OF WORK TENDER NO :<br />
Common shutdown jobs, Capital repair jobs and Maintenance <strong>of</strong> Heat<br />
Exchangers in Utilities Department <strong>of</strong> VISAKHAPATNAM <strong>Steel</strong> Plant<br />
14.1.12 Tanks with heaters for chemical cleaning<br />
14.1.13 Polythene sheet<br />
b) Consumables to be supplied by VSP ( free <strong>of</strong> cost ) :<br />
14.2.1 Compressed air , water , oxygen and DA gas<br />
14.2.2 Welding electrodes<br />
14.2.3 Consumables required for TIG welding<br />
14.2.4 Drill bits<br />
c) Materials to be supplied by contractor : Nil<br />
TENDER No : 72211-0<br />
d) Consumables to be supplied by Contractor : Nil<br />
14.3.0 The deduction <strong>of</strong> sales tax shall be done as per the rules<br />
prevailing from time to time.<br />
14.4.0 The contractor shall provide manpower to collect steel /pipes /<br />
spares etc from VSP(dept) stores and for return <strong>of</strong> unused materials to VSP<br />
( dept ) stores.<br />
29 <strong>of</strong> 39 Signature <strong>of</strong> the Tenderer
REPORT ID:<br />
RASHTRIYA ISPAT NIGAM LIMITED<br />
VISAKHAPATNAM STEEL PLANT<br />
BOQ REPORT<br />
TENDER NO :<br />
Page 1 TENDER <strong>of</strong> 9 No : 72211-0<br />
-----------------------------------------------------------------------------------------<br />
1<br />
2<br />
3<br />
4<br />
5<br />
6<br />
DEPT NAME : UTILITIES ENGG DIVN : MECHANICAL<br />
PROPOSAL NO : 515061240100<br />
Work Desc :<br />
Item<br />
No.<br />
Item Description<br />
Replacement <strong>of</strong> 200 NB<br />
valves<br />
Replacement <strong>of</strong> 300 NB<br />
valves<br />
Inspection/replacement<br />
<strong>of</strong> Oxygen filter<br />
elements <strong>of</strong> PRS-1<br />
Replacement <strong>of</strong> 500 NB<br />
valves<br />
Replacement <strong>of</strong> 600 NB /<br />
700 NB valves<br />
Dismantling,<br />
modification & erection<br />
<strong>of</strong> PRS-1 branch piping<br />
RESP CODE :<br />
516001<br />
Common shutdown jobs, Capital repair jobs and Maintenance <strong>of</strong> Heat<br />
Exchangers in Utilities Department <strong>of</strong> VISAKHAPATNAM <strong>Steel</strong> Plant<br />
The BOQs are prepared on the basis <strong>of</strong> following rates.<br />
Min.Wage Rate VSP Rate<br />
UnSkilled<br />
212.00 359.40<br />
SemiSkilled<br />
240.00 402.75<br />
Skilled<br />
283.00 464.25<br />
Unit<br />
Desc.<br />
NUMBER<br />
NUMBER<br />
NUMBER<br />
NUMBER<br />
NUMBER<br />
NUMBER<br />
Quantity<br />
2.000<br />
2.000<br />
2.000<br />
2.000<br />
3.000<br />
1.000<br />
Rate<br />
(Rs.)<br />
2528.48<br />
3790.00<br />
6517.40<br />
6097.83<br />
7566.82<br />
27257.10<br />
Amount<br />
(Rs.)<br />
5056.96<br />
Rupees Two thousand five hundred twenty-eight<br />
and paise forty-eight Only<br />
7580.00<br />
Rupees Three thousand seven hundred ninety<br />
Only<br />
13034.80<br />
Rupees Six thousand five hundred seventeen<br />
and paise forty Only<br />
12195.66<br />
Rupees Six thousand ninety-seven and paise<br />
eighty-three Only<br />
22700.46<br />
Rupees Seven thousand five hundred sixty-six<br />
and paise eighty-two Only<br />
27257.10<br />
Rupees Twenty-seven thousand two hundred<br />
fifty-seven and paise ten Only<br />
30 <strong>of</strong> 39 Signature <strong>of</strong> the Tenderer
REPORT ID:<br />
RASHTRIYA ISPAT NIGAM LIMITED<br />
VISAKHAPATNAM STEEL PLANT<br />
BOQ REPORT<br />
TENDER NO :<br />
Page 2 TENDER <strong>of</strong> 9 No : 72211-0<br />
-----------------------------------------------------------------------------------------<br />
7<br />
8<br />
9<br />
10<br />
11<br />
12<br />
13<br />
14<br />
15<br />
Oxygen service cleaning<br />
& degreasing <strong>of</strong> seamless<br />
piping size: 250 NB<br />
Provision <strong>of</strong><br />
800nb/1000nb valve<br />
Technological assistance<br />
for upkeep <strong>of</strong> butterfly<br />
control valves size<br />
350NB to 500NB<br />
Technological assistance<br />
for upkeep <strong>of</strong> butterfly<br />
control valves size<br />
600NB to 700NB<br />
Technological assistance<br />
for upkeep <strong>of</strong> globe<br />
control valves<br />
Technological assistance<br />
for upkeep <strong>of</strong> demister<br />
<strong>of</strong> E10/E11 towers<br />
Dismantling & fixing<br />
back <strong>of</strong> trays <strong>of</strong> Air<br />
water tower E10<br />
Dismantling & fixing<br />
back <strong>of</strong> trays <strong>of</strong><br />
Nitrogen water tower E11<br />
Cleaning <strong>of</strong> trays <strong>of</strong><br />
E10/E11<br />
METRE<br />
NUMBER<br />
NUMBER<br />
NUMBER<br />
NUMBER<br />
NUMBER<br />
NUMBER<br />
NUMBER<br />
NUMBER<br />
60.000<br />
1.000<br />
2.000<br />
2.000<br />
3.000<br />
2.000<br />
1.000<br />
1.000<br />
2.000<br />
160.27<br />
9820.81<br />
5595.50<br />
6994.36<br />
1750.63<br />
5595.50<br />
9428.53<br />
6734.67<br />
3039.69<br />
9616.20<br />
Rupees One hundred sixty and paise twentyseven<br />
Only<br />
9820.81<br />
Rupees Nine thousand eight hundred twenty and<br />
paise eighty-one Only<br />
11191.00<br />
Rupees Five thousand five hundred ninety-five<br />
and paise fifty Only<br />
13988.72<br />
Rupees Six thousand nine hundred ninety-four<br />
and paise thirty-six Only<br />
5251.89<br />
Rupees One thousand seven hundred fifty and<br />
paise sixty-three Only<br />
11191.00<br />
Rupees Five thousand five hundred ninety-five<br />
and paise fifty Only<br />
9428.53<br />
Rupees Nine thousand four hundred twentyeight<br />
and paise fifty-three Only<br />
6734.67<br />
Rupees Six thousand seven hundred thirty-four<br />
and paise sixty-seven Only<br />
6079.38<br />
Rupees Three thousand thirty-nine and paise<br />
31 <strong>of</strong> 39 Signature <strong>of</strong> the Tenderer
REPORT ID:<br />
RASHTRIYA ISPAT NIGAM LIMITED<br />
VISAKHAPATNAM STEEL PLANT<br />
BOQ REPORT<br />
TENDER NO :<br />
Page 3 TENDER <strong>of</strong> 9 No : 72211-0<br />
-----------------------------------------------------------------------------------------<br />
16<br />
17<br />
18<br />
19<br />
20<br />
21<br />
22<br />
23<br />
Cleaning <strong>of</strong> internals <strong>of</strong><br />
E10/E11<br />
Technological assistance<br />
for upkeep <strong>of</strong> safety<br />
valves<br />
Technological assistance<br />
for repair <strong>of</strong> adsorbed<br />
beds <strong>of</strong> R01/R02 driers<br />
Technological assistance<br />
for removing,<br />
repair/replacement &<br />
fixing <strong>of</strong> SS mesh<br />
between adsorbent beds<br />
<strong>of</strong> driers R01/R02<br />
Technological assistance<br />
for upkeep <strong>of</strong> manual<br />
valves size 15/20/25 mm<br />
Technological assistance<br />
for upkeep <strong>of</strong> manual<br />
valves size 40/50/65 mm<br />
Technological assistance<br />
for upkeep <strong>of</strong> manual<br />
valves size 80/100 mm<br />
Technological assistance<br />
for upkeep <strong>of</strong> manual<br />
valves size 150 NB/200<br />
NUMBER<br />
NUMBER<br />
NUMBER<br />
NUMBER<br />
NUMBER<br />
NUMBER<br />
NUMBER<br />
NUMBER<br />
2.000<br />
30.000<br />
2.000<br />
2.000<br />
30.000<br />
30.000<br />
15.000<br />
5.000<br />
1519.86<br />
87.49<br />
16606.58<br />
4908.47<br />
218.83<br />
291.77<br />
437.66<br />
891.53<br />
sixty-nine Only<br />
3039.72<br />
Rupees One thousand five hundred nineteen and<br />
paise eighty-six Only<br />
2624.70<br />
Rupees Eighty-seven and paise forty-nine Only<br />
33213.16<br />
Rupees Sixteen thousand six hundred six and<br />
paise fifty-eight Only<br />
9816.94<br />
Rupees Four thousand nine hundred eight and<br />
paise forty-seven Only<br />
6564.90<br />
Rupees Two hundred eighteen and paise eightythree<br />
Only<br />
8753.10<br />
Rupees Two hundred ninety-one and paise<br />
seventy-seven Only<br />
6564.90<br />
Rupees Four hundred thirty-seven and paise<br />
sixty-six Only<br />
4457.65<br />
Rupees Eight hundred ninety-one and paise<br />
32 <strong>of</strong> 39 Signature <strong>of</strong> the Tenderer
REPORT ID:<br />
RASHTRIYA ISPAT NIGAM LIMITED<br />
VISAKHAPATNAM STEEL PLANT<br />
BOQ REPORT<br />
TENDER NO :<br />
Page 4 TENDER <strong>of</strong> 9 No : 72211-0<br />
-----------------------------------------------------------------------------------------<br />
24<br />
25<br />
26<br />
27<br />
28<br />
29<br />
30<br />
NB<br />
Dismantling ,<br />
fabricating and erecting<br />
<strong>of</strong> structural sheeting<br />
in air separation units<br />
etc.,<br />
Dismantling, fabricating<br />
& erecting <strong>of</strong> structural<br />
in Air separation plant<br />
Dismantling & erecting<br />
<strong>of</strong> 15/20/25 NB MS/ GI<br />
piping for Chilled<br />
water/air service<br />
Dismantling & erecting<br />
<strong>of</strong> 40 NB MS piping for<br />
water/air service<br />
Dismantling & erecting<br />
<strong>of</strong> 50/65 NB MS/ SS<br />
piping for oil/air/water<br />
service<br />
Dismantling & erecting<br />
<strong>of</strong> 80 NB MS piping for<br />
Chilled water service<br />
Taking delivery <strong>of</strong><br />
material from dept.<br />
stores.Provision <strong>of</strong><br />
utility lines by<br />
erection & fixing in<br />
position at<br />
allelevations <strong>of</strong><br />
towers,trusels,bridges,b<br />
METRIC<br />
TONNE<br />
METRIC<br />
TONNE<br />
Running<br />
Meter<br />
Running<br />
Meter<br />
Running<br />
Meter<br />
Running<br />
Meter<br />
Running<br />
Meter<br />
2.000<br />
15.000<br />
300.000<br />
300.000<br />
150.000<br />
52.000<br />
50.000<br />
5587.86<br />
4474.33<br />
26.93<br />
38.80<br />
47.25<br />
75.47<br />
205.98<br />
fifty-three Only<br />
11175.72<br />
Rupees Five thousand five hundred eightyseven<br />
and paise eighty-six Only<br />
67114.95<br />
Rupees Four thousand four hundred seventyfour<br />
and paise thirty-three Only<br />
8079.00<br />
Rupees Twenty-six and paise ninety-three Only<br />
11640.00<br />
Rupees Thirty-eight and paise eighty Only<br />
7087.50<br />
Rupees Forty-seven and paise twenty-five Only<br />
3924.44<br />
Rupees Seventy-five and paise forty-seven<br />
Only<br />
10299.00<br />
Rupees Two hundred five and paise ninetyeight<br />
Only<br />
33 <strong>of</strong> 39 Signature <strong>of</strong> the Tenderer
REPORT ID:<br />
RASHTRIYA ISPAT NIGAM LIMITED<br />
VISAKHAPATNAM STEEL PLANT<br />
BOQ REPORT<br />
TENDER NO :<br />
Page 5 TENDER <strong>of</strong> 9 No : 72211-0<br />
-----------------------------------------------------------------------------------------<br />
31<br />
uildings etc. in open<br />
yard within the shop and<br />
underground<br />
tunnels,pipes <strong>of</strong><br />
different sizes for<br />
utility service complete<br />
with fittings like<br />
bends,reducers,flanges,e<br />
xpansions loops,drain<br />
pots ,drains,trap<br />
stations ,vents,flow<br />
mwters etc.including<br />
dismantling <strong>of</strong> existing<br />
pipe lines as<br />
required.Jinting with<br />
all jointing materials<br />
,securing to supports<br />
with suitable clamps<br />
,hanger saddles ,sprig<br />
supports,u bolts etc.<br />
all as specified.all<br />
material<br />
,,tools,tackles,labour<br />
complete as per <strong>scope</strong> <strong>of</strong><br />
<strong>work</strong> .size:150 nb pipes<br />
Taking delivery <strong>of</strong><br />
material from dept.<br />
stores.Provision <strong>of</strong><br />
utility lines by<br />
erection & fixing in<br />
position at<br />
allelevations <strong>of</strong><br />
towers,trusels,bridges,b<br />
uildings etc. in open<br />
yard within the shop and<br />
underground<br />
tunnels,pipes <strong>of</strong><br />
different sizes for<br />
utility service complete<br />
with fittings like<br />
bends,reducers,flanges,e<br />
xpansions loops,drain<br />
pots ,drains,trap<br />
stations ,vents,flow<br />
mwters etc.including<br />
METRIC<br />
TONNE<br />
7.000 6528.59 45700.13<br />
Rupees Six thousand five hundred twenty-eight<br />
and paise fifty-nine Only<br />
34 <strong>of</strong> 39 Signature <strong>of</strong> the Tenderer
REPORT ID:<br />
RASHTRIYA ISPAT NIGAM LIMITED<br />
VISAKHAPATNAM STEEL PLANT<br />
BOQ REPORT<br />
TENDER NO :<br />
Page 6 TENDER <strong>of</strong> 9 No : 72211-0<br />
-----------------------------------------------------------------------------------------<br />
32<br />
33<br />
34<br />
35<br />
36<br />
37<br />
dismantling <strong>of</strong> existing<br />
pipe lines as<br />
required.Jinting with<br />
all jointing materials<br />
,securing to supports<br />
with suitable clamps<br />
,hanger saddles ,sprig<br />
supports,u bolts etc.<br />
all as specified.all<br />
material<br />
,,tools,tackles,labour<br />
complete as per <strong>scope</strong> <strong>of</strong><br />
<strong>work</strong> .size:above 200nb<br />
and pto 600 nb pipes<br />
Technological upkeep <strong>of</strong><br />
ASU cold box structural<br />
& walk ways<br />
TIG WELDING OF SS/CS<br />
PIPING.<br />
Radiography <strong>of</strong> CS/SS<br />
piping<br />
Ultrasonic thickness<br />
measurement<br />
Power buffing (brushing)<br />
<strong>of</strong> sheeting/ structural<br />
on tank done/ vessels/<br />
piping etc.<br />
Dismantling & fixing<br />
back <strong>of</strong> motor noise hood<br />
arrangement<br />
NUMBER<br />
INCH<br />
Running<br />
Meter<br />
NUMBER<br />
SQ.<br />
METRE<br />
NUMBER<br />
6.000<br />
85.000<br />
3.000<br />
765.000<br />
120.000<br />
12.000<br />
3221.00<br />
21.33<br />
1229.52<br />
32.31<br />
88.79<br />
1914.65<br />
19326.00<br />
Rupees Three thousand two hundred twenty-one<br />
Only<br />
1813.05<br />
Rupees Twenty-one and paise thirty-three Only<br />
3688.56<br />
Rupees One thousand two hundred twenty-nine<br />
and paise fifty-two Only<br />
24717.15<br />
Rupees Thirty-two and paise thirty-one Only<br />
10654.80<br />
Rupees Eighty-eight and paise seventy-nine<br />
Only<br />
22975.80<br />
Rupees One thousand nine hundred fourteen and<br />
paise sixty-five Only<br />
35 <strong>of</strong> 39 Signature <strong>of</strong> the Tenderer
REPORT ID:<br />
RASHTRIYA ISPAT NIGAM LIMITED<br />
VISAKHAPATNAM STEEL PLANT<br />
BOQ REPORT<br />
TENDER NO :<br />
Page 7 TENDER <strong>of</strong> 9 No : 72211-0<br />
-----------------------------------------------------------------------------------------<br />
38<br />
39<br />
40<br />
41<br />
42<br />
43<br />
44<br />
45<br />
46<br />
Dismantling & fixing<br />
back <strong>of</strong> compressor<br />
noise hood arrangement<br />
Chemical cleaning <strong>of</strong> FAC<br />
gas cooler<br />
Chemical cleaning <strong>of</strong> NC<br />
gas cooler<br />
Chemical cleaning <strong>of</strong> OC<br />
gas cooler<br />
Chemical cleaning <strong>of</strong> CH-<br />
1 PAC gas cooler<br />
Chemical cleaning <strong>of</strong> oil<br />
coolers <strong>of</strong> FAC, NC, OC<br />
Chemical cleaning <strong>of</strong> oil<br />
coolers <strong>of</strong> CH-1 PACI<br />
Chemical cleaning <strong>of</strong><br />
motor coolers <strong>of</strong> FAC,<br />
NC, OC & PAC CH-1/II<br />
Chemical cleaning <strong>of</strong> X01<br />
condenser<br />
NUMBER<br />
NUMBER<br />
NUMBER<br />
NUMBER<br />
NUMBER<br />
NUMBER<br />
NUMBER<br />
PAIR<br />
NUMBER<br />
12.000<br />
8.000<br />
12.000<br />
5.000<br />
4.000<br />
22.000<br />
6.000<br />
6.000<br />
2.000<br />
1914.65<br />
16306.07<br />
9078.95<br />
6952.39<br />
11581.96<br />
6952.39<br />
6336.16<br />
12915.76<br />
12915.76<br />
22975.80<br />
Rupees One thousand nine hundred fourteen and<br />
paise sixty-five Only<br />
130448.56<br />
Rupees Sixteen thousand three hundred six and<br />
paise seven Only<br />
108947.40<br />
Rupees Nine thousand seventy-eight and paise<br />
ninety-five Only<br />
34761.95<br />
Rupees Six thousand nine hundred fifty-two<br />
and paise thirty-nine Only<br />
46327.84<br />
Rupees Eleven thousand five hundred eightyone<br />
and paise ninety-six Only<br />
152952.58<br />
Rupees Six thousand nine hundred fifty-two<br />
and paise thirty-nine Only<br />
38016.96<br />
Rupees Six thousand three hundred thirty-six<br />
and paise sixteen Only<br />
77494.56<br />
Rupees Twelve thousand nine hundred fifteen<br />
and paise seventy-six Only<br />
25831.52<br />
Rupees Twelve thousand nine hundred fifteen<br />
and paise seventy-six Only<br />
36 <strong>of</strong> 39 Signature <strong>of</strong> the Tenderer
REPORT ID:<br />
RASHTRIYA ISPAT NIGAM LIMITED<br />
VISAKHAPATNAM STEEL PLANT<br />
BOQ REPORT<br />
TENDER NO :<br />
Page 8 TENDER <strong>of</strong> 9 No : 72211-0<br />
-----------------------------------------------------------------------------------------<br />
47<br />
48<br />
49<br />
50<br />
51<br />
52<br />
53<br />
Chemical cleaning <strong>of</strong> X01<br />
evaporator<br />
Chemical cleaning <strong>of</strong><br />
Chiller evaporator<br />
Chemical cleaning <strong>of</strong><br />
chiller condenser<br />
Technological assistance<br />
for upkeep <strong>of</strong> demesters<br />
<strong>of</strong> FAC cooler<br />
Misc repair jobs during<br />
capital repair <strong>of</strong> ASU,<br />
during common s/d,heat<br />
exchanger tube leak<br />
identification/<br />
rectification<br />
activities, temporary<br />
fixing etc. by providing<br />
man power skilled<br />
Misc repair jobs during<br />
capital repair <strong>of</strong> ASU,<br />
during common s/d,heat<br />
exchanger tube leak<br />
identification/<br />
rectification<br />
activities, temporary<br />
fixing etc. by providing<br />
man power semi skilled<br />
Misc repair jobs during<br />
capital repair <strong>of</strong> ASU,<br />
during common s/d,heat<br />
exchanger tube leak<br />
NUMBER<br />
NUMBER<br />
NUMBER<br />
NUMBER<br />
MAN DAY<br />
MAN DAY<br />
MAN DAY<br />
2.000<br />
2.000<br />
2.000<br />
12.000<br />
375.000<br />
100.000<br />
500.000<br />
12915.76<br />
14611.02<br />
14611.02<br />
1948.48<br />
464.25<br />
402.75<br />
359.40<br />
25831.52<br />
Rupees Twelve thousand nine hundred fifteen<br />
and paise seventy-six Only<br />
29222.04<br />
Rupees Fourteen thousand six hundred eleven<br />
and paise two Only<br />
29222.04<br />
Rupees Fourteen thousand six hundred eleven<br />
and paise two Only<br />
23381.76<br />
Rupees One thousand nine hundred forty-eight<br />
and paise forty-eight Only<br />
174093.75<br />
Rupees Four hundred sixty-four and paise<br />
twenty-five Only<br />
40275.00<br />
Rupees Four hundred two and paise seventyfive<br />
Only<br />
179700.00<br />
Rupees Three hundred fifty-nine and paise<br />
forty Only<br />
37 <strong>of</strong> 39 Signature <strong>of</strong> the Tenderer
REPORT ID:<br />
RASHTRIYA ISPAT NIGAM LIMITED<br />
VISAKHAPATNAM STEEL PLANT<br />
BOQ REPORT<br />
TENDER NO :<br />
Page 9 TENDER <strong>of</strong> 9 No : 72211-0<br />
-----------------------------------------------------------------------------------------<br />
54<br />
55<br />
56<br />
57<br />
58<br />
identification/<br />
rectification<br />
activities, temporary<br />
fixing etc. by providing<br />
man power un skilled<br />
PROVISION OOF NEW VALVE<br />
IN EXISTING PIPE LINE<br />
SIZE:100NB<br />
DISMANTLING AND ERECTION<br />
OF 100NB MS PIPING FOR<br />
CHILLED WATER/GAS/OIL<br />
Technological assistance<br />
for manual cleaning <strong>of</strong><br />
heat exchangers<br />
Technological assistance<br />
for leak identification<br />
in heat exchangers and<br />
rectification by tubes<br />
blanking.<br />
Technological assistance<br />
for cleaning <strong>of</strong><br />
impellers <strong>of</strong> PACs <strong>of</strong><br />
Compressor House-2<br />
NUMBER<br />
METRE<br />
NUMBER<br />
NUMBER<br />
NUMBER<br />
3.000<br />
50.000<br />
5.000<br />
3.000<br />
3.000<br />
1107.90<br />
87.01<br />
1672.23<br />
4170.17<br />
3386.10<br />
3323.70<br />
Rupees One thousand one hundred seven and<br />
paise ninety Only<br />
4350.50<br />
Rupees Eighty-seven and paise one Only<br />
8361.15<br />
Rupees One thousand six hundred seventy-two<br />
and paise twenty-three Only<br />
12510.51<br />
Rupees Four thousand one hundred seventy and<br />
paise seventeen Only<br />
10158.30<br />
Rupees Three thousand three hundred eightysix<br />
and paise ten Only<br />
1672545.79<br />
Rupees Sixteen lakh seventy-two thousand five<br />
hundred forty-five and paise seventy-nine<br />
Only<br />
Signature <strong>of</strong> I/C Signature <strong>of</strong> HOD<br />
38 <strong>of</strong> 39 Signature <strong>of</strong> the Tenderer
FORM’G’<br />
RASHTRIYA ISPAT NIGAM LIMITED<br />
VISAKHAPATNAM STEEL PLANT<br />
WORKS CONTRACTS DEPARTMENT<br />
BILL OF QUANTITIES (BOQ)<br />
Name <strong>of</strong> the <strong>work</strong> : Common shutdown jobs, capital repair jobs and<br />
Maintenance <strong>of</strong> Heat Exchangers in Utilities<br />
Department <strong>of</strong> Visakhapatnam steel plant .<br />
1. The quantities indicated are approximate and may vary to a wide range. Payment shall be made as per the<br />
actual <strong>work</strong> carried out at corresponding accepted rate.<br />
2. Wherever old items are replaced for fixing new items, all related connections are to be made good for proper<br />
functioning <strong>of</strong> new items. Dismantled / old items are to be handed over to the stores.<br />
No. DESCRIPTION UNIT QTY. RATE (`.) AMOUNT (`.)<br />
1.<br />
As per t he d etailed B ill o f<br />
Quantities(BOQ) enclosed in<br />
09( Nine ) pages.<br />
ESTIMATED VALUE …………<br />
( RUPEES SIXTEEN LAKHS<br />
SEVENTY TWO THOUSAND FIVE<br />
HUNDRED FORTY FIVE PAISE<br />
SEVENTY NINE ONLY )<br />
TOTAL AMOUNT QUOTED IN FIGURES: Rs. _________________________________<br />
`.16,72,545=79<br />
TOTAL AMOUNT QUOTED IN WORDS: Rs. ___________________________________________________<br />
______________________________________________________________________________ only.<br />
Note: 1. Tenderer shall write their quoted <strong>of</strong>fer both in WORDS and FIGURES. The quoted <strong>of</strong>fer in<br />
WORDS shall be in CAPITAL / BLOCK letters.<br />
2. If there is discrepancy between the amount mentioned in FIGURES and the amount<br />
mentioned in WORDS, the amount as mentioned in WORDS only shall be taken as the<br />
quotation <strong>of</strong> the tenderer.<br />
3. THE ESTIMATE OF THIS TENDER IS BASED ON THE RINL / VSP APPROVED W AGE RATES,<br />
CONSEQUENT T O IMPLEMENTATION O F MINIMUM W AGE O F CO NTRACT W ORKER AS NO TIFIED B Y<br />
THE RE GIONAL L ABOUR COMMISSIONER (CENTRAL), HY DERABAD, W HICH IS G IVEN B ELOW. I N<br />
CASE RE VISION I N T HE MINIMUM W AGES OF CONTRACT LABOUR TAKES PL ACE, ESC LATION DU E<br />
TO T HIS SH ALL B E P AYABLE T O THE CO NTRACT LABOUR AS PE R T HE ESC ALATION F ORMULA<br />
INDICATED IN THE SPECIAL CONDITIONS OF CONTRACT :<br />
RINL/VSP APPROVED RATE (IN RUPEES)<br />
MINIMUM W AGES AS N OTIFIED BY T HE RL C<br />
(CENTRAL), HYDERABAD<br />
(IN RUPEES)<br />
UNSKILLED<br />
WORKER<br />
SEMI-SKILLED<br />
WORKER<br />
TENDER No : 72211-0<br />
TENDER NO: 72211-0<br />
SKILLED<br />
WORKER<br />
359=40 402=75 464=25<br />
212=00 240=00 283=00<br />
39 <strong>of</strong> 39 Signature <strong>of</strong> the Tenderer