Ho Chi Minh City Metro Rail System Project <strong>Final</strong> <strong>Report</strong> - Revised<br />

Management Authority for Urban Railways Chapter 6 – Estimated Capital and O&M Costs<br />

6.3 Operating and Maintenance Cost Estimates<br />

6.3.1 Introduction<br />

151. The annual operating and maintenance (O&M) cost estimates for Line 2 have been estimated<br />

for 2015, 2025 and 2035.<br />

152. The O&M cost is the sum of the following two main categories of costs:<br />

Staff costs: cost estimation for the whole staff: administrative, operation, maintenance and<br />

engineering;<br />

External costs such as cost of electricity, materials and consumables.<br />

6.3.2 Personnel Costs<br />

153. The annual personnel cost is calculated following the organization and staffing described in<br />

Appendix E. The organization is a simple structure with a General Management (including counselling<br />

and quality control) and three line departments: Operations, Maintenance and Administration. The<br />

total estimated manpower requirements for operations and maintenance are 780, 800 and 814 for<br />

2015, 2025 and 2035 respectively.<br />

154. For the purpose of staff cost estimation, the staff was split in the following 6 categories<br />

(estimated annual salary in US$ in early 2008 in parenthesis):<br />

Employees in managing position (US$6,485)<br />

Administrative and managerial clerks, OCC supervisors, engineers (US$5,650)<br />

Drivers (US$5,089)<br />

Station supervisors, skilled workers ((US$3,724)<br />

Secretaries, drivers, platform ticket controller, security staff(US$2,767)<br />

Unskilled workers (US$2,523).<br />

6.3.3 External Costs<br />

155. The electricity consumption is based on trains (traction and auxiliary on-board equipment),<br />

stations and depot consumptions. The onboard auxiliary equipment consumption is function of the<br />

time when trains are switched on. It was considered 15 hours a day for each train and 50kWh for the<br />

auxiliary consumption. For underground stations, the required power supply was estimated in 950 kW.<br />

For elevated stations, the required power supply was estimated in 270 kW. For depot, it was<br />

considered a total power consumption of 1 MWh.<br />

156. The electricity price, considering it will be supplied by a voltage of 110 KW, is determined in<br />

early 2008 as the following:<br />

Table 6.3-1: Cost of Electricity<br />

With voltage supplied<br />

of more than 110 KW<br />

785 VND/KWH<br />

425 VND/KWH<br />

1590 VND/KWH<br />

Offpeak hours<br />

04:00 to 18:00<br />

Low hours<br />

22:00 to 04:00<br />

Peak hours<br />

18:00 to 22:00<br />

157. The consumables category includes all the necessary material and fluids to operate and<br />

maintain the system: lubricant materials, sand, water and detergents. This category also includes the<br />

power supply for administrative and maintenance buildings (lighting, power, air conditioning). Based<br />

on experience, this cost item is assumed to be 15% of staff cost.<br />

158. This materials category includes all the material pieces to be bought for the maintenance<br />

activity, the outsourced maintenance for specific equipment such as electronic parts, optical fiber<br />

components or computers, with 70% considered of foreign source and 30% of local source. The<br />

6-5