<strong>NASA</strong>-STD-8739.4 with Change 6<br />
k. Inspect that solder sleeve terminations were fabricated <strong>and</strong> installed as directed by<br />
engineering documentation.<br />
l. Verify installation processes <strong>and</strong> acceptance/rejection criteria for solder sleeve termination<br />
devices were defined <strong>and</strong> approved.<br />
m. Verify that other processes such as potting <strong>and</strong> molding, necessary to fabricate a cable or<br />
harness, are defined by the engineering documentation <strong>and</strong> approved. This shall include<br />
accept/reject criteria (Requirement).<br />
20.2 Magnification Aids<br />
Inspection optics shall conform to the requirements of paragraph 6.7 (Requirement). Visual<br />
inspection shall be aided by magnification between 4X <strong>and</strong> 10X (Requirement). Additional<br />
magnification shall be used, as necessary, to resolve suspected anomalies or defects<br />
(Requirement).<br />
20.3 Documentation Verification<br />
Quality Representatives shall verify that all required documentation is current <strong>and</strong> approved.<br />
The documentation shall include:<br />
20.3.1 Records (Requirement):<br />
a. Results of the visual examination as per paragraph 5.2-1.<br />
b. Evidence of operator <strong>and</strong> inspector certification as per paragraph 5.5.<br />
c. Production <strong>and</strong> inspection tool calibration as per paragraph 6.3.<br />
d. Tensile testing as per paragraphs 12.3.4 <strong>and</strong> 13.7.5<br />
e. Torque requirements as per paragraph 13.5.<br />
f. Contact retention test records as per paragraph 13.8.2<br />
g. Connector mate/demate log <strong>and</strong> bent pin log as per paragraph 17.2-9.<br />
h. Results of all acceptance testing as per paragraph 18.2-3.<br />
20.3.2 Procedures (Requirement):<br />
a. Cabling <strong>and</strong> harnessing program as per paragraphs 4.4 <strong>and</strong> 5.1.<br />
b. Training <strong>and</strong> certification program as per paragraph 5.4-3.b.<br />
c. Tooling <strong>and</strong> equipment operation as per paragraph 6.3-1.e.<br />
d. Calibration system as per paragraph 6.3-2.c.<br />
e. Electrostatic Discharge Control Program as per paragraph 6.4.<br />
f. In-process storage <strong>and</strong> h<strong>and</strong>ling as per paragraph 6.5.