• Fields <strong>of</strong> the Wood should be closed as soon as possible to halt the $100,000 annual<br />
operating deficit. The property should either be sold or developed. In either case, action<br />
on its disposition should be delayed until real estate market conditions are thought to be<br />
improving.<br />
• Opportunities for generating revenue from the land asset at Tomlinson College campus<br />
should be reviewed as soon as possible. Priority action should reflect the window <strong>of</strong><br />
opportunity stimulated by the Cleveland/Bradley County market dynamics.<br />
• If an acceptable agreement cannot be reached for purchase <strong>of</strong> the International Offices<br />
campus, COGOP should budget funds as outlined in the report for upgrading mechanical<br />
systems and other building improvements.<br />
• Absent the sale <strong>of</strong> the headquarters building, COGOP should intensify efforts to sell or<br />
lease the VOS building, relocating staff housed there to the headquarters building.<br />
Similarly, rearrangement <strong>of</strong> COGOP staff should be examined to maximize the space<br />
available for lease in the White Wing Press building and bookstore.<br />
• Planning and development efforts regarding the Tomlinson College campus should<br />
proceed with the objective <strong>of</strong> using the site as a means <strong>of</strong> generating revenue.<br />