Preconstruction Preparation<br />
Existing conditions topographic survey<br />
Wetland and resource area delineation in accordance with Mass DEP regulations<br />
File Request for Determination <strong>of</strong> Applicability (RDA) under the Wetlands Protection Act for<br />
storm drain line cleaning<br />
Presentation <strong>of</strong> RDA to the <strong>Natick</strong> Conservation Commission; negative determination issued<br />
Storm drain line cleaning and television inspection<br />
Preparation <strong>of</strong> proposed reconstruction plans and pr<strong>of</strong>iles<br />
Review and coordination with <strong>Natick</strong> Engineering and DPW throughout design process<br />
Preparation and submittal <strong>of</strong> Notice <strong>of</strong> Intent to Mass DEP and <strong>Natick</strong> Conservation Commission<br />
Presentation <strong>of</strong> NOI to the <strong>Natick</strong> Conservation Commission, approval granted<br />
Preparation <strong>of</strong> <strong>Natick</strong> Land Disturbance Bylaw application; approval granted<br />
Presentation <strong>of</strong> Land Disturbance submittal to the <strong>Natick</strong> Conservation Commission; approval<br />
granted<br />
Solicitation and evaluation <strong>of</strong> project bids<br />
Road Construction<br />
Placement <strong>of</strong> erosion control measures along roadway, approximately 6,500 feet <strong>of</strong> hay bales and<br />
silt fence installed<br />
Pulverization <strong>of</strong> pre-existing roadway surface<br />
Installation <strong>of</strong> 25 new deep sump catch basins with oil/water separators<br />
Replacement <strong>of</strong> storm drain lines<br />
Repair and replacement to the domestic water system as directed by <strong>Natick</strong> DPW and<br />
Engineering Departments<br />
Replacement <strong>of</strong> all hydrants along Newfield Drive<br />
Epoxy lining <strong>of</strong> all existing sanitary sewer lines within Newfield Drive to eliminate ground water<br />
infiltration<br />
Epoxy lining <strong>of</strong> existing select sanitary sewer manholes to eliminate groundwater infiltration<br />
Road sub grade preparation and compaction<br />
Installation <strong>of</strong> Pavement binder course<br />
Installation <strong>of</strong> new bituminous concrete walkways and concrete handicap access ramps along<br />
entire Newfield Drive Right <strong>of</strong> Way<br />
Installation <strong>of</strong> pavement finish course<br />
Loam and seed road shoulders<br />
As built survey and preparation <strong>of</strong> as built drawings and street acceptance plans<br />
Close out order <strong>of</strong> conditions with Conservation Commission<br />
Page 46