• Study <strong>of</strong> existing infrastructure.<br />

• Cost benefit and economic evaluation.<br />

1.3 RESULTS OF STUDIES AND INVESTIGATIONS<br />

1.3.1 Geology<br />

7<br />

Preliminary Feasibility Report<br />

<strong>Lingza</strong> HE Project (3 x 40 MW)<br />

The preliminary geological survey <strong>of</strong> the locations <strong>of</strong> all the structures on the ground was<br />

carried out after site visits. The site-specific geological data were got collected and<br />

utilized in the design <strong>of</strong> various components <strong>of</strong> the project. The geological survey <strong>of</strong> the<br />

near by area was also carried out to co-relate the geology <strong>of</strong> the project area. The dam<br />

location has been fixed after observing the rock exposures on both the banks and in the<br />

riverbed.<br />

1.3.2 Hydrology<br />

The river Ringpi drains a catchment area <strong>of</strong> about 198sq.km at the proposed dam site.<br />

The water availability for the project has been considered on the basis <strong>of</strong> 10-daily<br />

discharge series at Lachen for the period from 1976-1997. The water availability at the<br />

<strong>Lingza</strong> dam site has been derived from the above data on the basis <strong>of</strong> catchment area<br />

proportion and applying an overall reduction factor <strong>of</strong> 0.22. The computed inflow series<br />

works out has been utilized for <strong>Power</strong> Potential Studies. The design flood has been<br />

assessed as 940cumecs.<br />

1.3.3 <strong>Power</strong> Potential Studies<br />

The computed inflow series for 21 years viz June 1976 to May 97 has been considered in<br />

the assessment <strong>of</strong> a power benefits from the project. As per GOI notification for tariff the<br />

year 1976-77 corresponds to 90% dependable year. An installation <strong>of</strong> 120MW<br />

comprising 3 generating units <strong>of</strong> 40MW has been proposed. The energy availability from<br />

the project in a 90%dependable and an average year has been summarized below:<br />

Annual Energy Generatio n<br />

Annual Energy Generation (GWh) 477.51