Civil works : 527.68<br />

Electro Mechanical Works : 97.36<br />

Sub Total (Generation) : 625.04<br />

Transmission Works : 5.01<br />

Total (Hard Cost) : 630.05<br />

Interest During Construction : 69.75<br />

Grand Total : 699.80<br />

1.3.7 Financial Aspects<br />

9<br />

Preliminary Feasibility Report<br />

<strong>Lingza</strong> HE Project (3 x 40 MW)<br />

As indicated above, the <strong>Lingza</strong> HE project with an estimated cost <strong>of</strong> Rs. 699.80crores<br />

(including IDC <strong>of</strong> Rs. 69.75crores) and design energy <strong>of</strong> 477.51GWh in a 90%<br />

dependable year is proposed to be completed in a period <strong>of</strong> 4 years. The tariff has been<br />

worked out considering a debt-equity ratio <strong>of</strong> 70:30, 16% return on equity, annual interest<br />

rate on loan at 10% and 12% <strong>of</strong> energy as free power to Home State available after<br />

losses. The tariff for the first year and levellised tariff has been worked out Rs. 3.24/KWh<br />

& Rs. 2.62/KWh respectively.<br />

1.3.8 Conclusion<br />

The <strong>Lingza</strong> HE project involves simple civil works and could be completed in 4 years.<br />

The project would afford a design energy <strong>of</strong> 477.51 GWh in a 90% dependable year. The<br />

cost per MW installed work out Rs.5.21Crore. The Preliminary Feasibility Report<br />

indicates that the scheme merit consideration for taking up for Survey & Investigation<br />

and preparation <strong>of</strong> DPR.