1<br />

2<br />

ARCMASTER <strong>400</strong> S<br />

SECTION 6:<br />

SEQUENCE OF OPERATION<br />

NOTE: Scroll Buttons are used to select the parameters to be set. The LED’s show which function<br />

is being adjusted on the weld sequence graph. Refer to Symbols Table located in the front of the<br />

manual for Symbol descriptions.<br />

1. Scroll Buttons – used to select the parameter to be set.<br />

The LED’s show which function is being adjusted on the<br />

Sequence Graph.<br />

2. Digital LED display – Welding amperage and parameter<br />

values are displayed in this window. Internal warnings<br />

such as over temperature, low or high input voltage<br />

applied are signaled to the operator by a warning sound<br />

and error message on the screen.<br />

3. Control knob – allows the operator to adjust the output<br />

amperage within the entire range of the power source,<br />

also used to set each parameter value.<br />

4. Process Button – This button selects between STICK or<br />

Lift TIG mode.<br />

5. Contactor function – Pressing this buttons enables<br />

Contactor functions.<br />

6. Remote Current function – Pressing this buttons enables<br />

remote current functions.<br />

6.01 Stick Welding<br />

• Connect work lead to negative terminal<br />

• Connect electrode lead to positive terminal<br />

• Switch machine on<br />

• Set Contactor<br />

• Connect remote control device if required<br />

3<br />

Figure 7 – <strong>400</strong> S Front Panel<br />

Use the Scroll Buttons to move to the parameter to be set.<br />

The LED will show which function is being adjusted on the<br />

weld sequence graph. Use the control knob to adjust each<br />

parameter.<br />

• Set HOT START<br />

• Set WELD current<br />

• Set Arc Control<br />

Commence welding<br />

6.02 DC LIFT TIG Welding<br />

• Connect work lead to positive terminal<br />

• Connect TIG torch to negative terminal<br />

• Switch machine on<br />

• Set weld current.<br />

• Connect remote control device if desired<br />

Use the Scroll Buttons to move to the parameter to be set.<br />

The LED will show which function is being adjusted on the<br />

weld sequence graph. Use the control knob to adjust each<br />

parameter.<br />

• Set WELD current<br />

Commence welding<br />

March 31, 2006 6-1<br />

5<br />