Project Close <strong>Out</strong>-Plan<br />
2 Inspection Strategy<br />
2.1 Architectural Inspections (BMJ)<br />
There was a pre-handover inspection on 19 December 2007. Interim inspections are<br />
continuing.<br />
In order to facilitate a smooth handover, the final architectural inspections will be phased as<br />
indicated on the schedule. Walter Lilly have provided a schedule of any outstanding works<br />
to BMJ which has been incorporated into their Defects Schedule – see Appendix C.<br />
Walter Lilly are to ensure that at the end of the final handover inspection BMJ are happy to<br />
confirm that the defects are down to a sufficiently low number that they would not prevent<br />
the Completion certificate from being signed. BMJ will then write to Arup to confirm this by<br />
18 February 08 or as soon thereafter as they are in a position to give that undertaking.<br />
2.2 M&E Inspections<br />
There was a pre-handover inspection on 19 December 2007. A final inspection has been<br />
booked for week commencing 11 th February 2008. Walter Lilly are to provide a schedule of<br />
outstanding works for this date. This is still outstanding.<br />
Walter Lilly are to ensure that at the end of the final handover inspection Banyards are<br />
happy to confirm that the defects are down to a sufficiently low number that they would not<br />
prevent the Completion certificate from being signed. Banyards will then write to Arup to<br />
confirm this by 18 February 08 or as soon thereafter as they are in a position to give that<br />
undertaking.<br />
2.3 Structural Supervisor<br />
Not applicable.<br />
2.4 Client Direct IT Installation<br />
Inspection of the ICL direct IT installation will be done by the relevant duty holder. It is not<br />
part of the main contract works.<br />
There is a requirement for some active equipment to be installed to allow for a connection to<br />
the NHS IT network. This is to be managed direct by ICL (SP/AB). It is not part of the main<br />
contract works.<br />
2.5 Duty Holders<br />
There was a pre-handover inspection on 19 December 2007. Final inspections are booked<br />
for the week commencing 11 February 08. Walter Lilly are to provide a schedule of<br />
outstanding works for this date so that the Duty Holders do not have to comment on known<br />
outstanding items.<br />
Final comments are to be submitted by the Duty Holders no later than the 15 February 08.<br />
Refer to separate schedule in Appendix D for details of planned inspection dates, comments<br />
received/responded to and final sign-offs by Duty Holders.<br />
2.6 Lifts<br />
Not applicable on this project.<br />
J:\119796-00\04-INTERNAL_PROJECT_DATA\4-05-REPORTS\HANDOVER<br />
PLAN\ISSUE 2\BDFO PROJECT CLOSE OUT PLAN - 08-02-15.DOC<br />
Page 4<br />
Ove Arup & Partners Ltd<br />
Issue 15 February 2008