<strong>Procurement</strong> Regulations<br />

(e) The architectural-engineering contract shall be<br />

awarded with reasonable promptness by written notice<br />

to the responsive and responsible bidder whose bid was<br />

either the lowest bid price or the lowest evaluated bid<br />

price.<br />

5.2.5 When the contract is for the rendition of professional<br />

services, and the architectural-engineering firm shall be<br />

selected on the basis of noncompetitive negotiations, the<br />

following selection procedure shall be followed:<br />

(a) The Executive Director of Facilities and Transportation<br />

shall make a written determination that competitive<br />

bidding procedures are not practicable for the selection<br />

of an architectural-engineering firm and that the procurement<br />

is for the services of an licensed professional<br />

and the grounds therefor;<br />

(b) The criteria for selection of the architectural-engineering<br />

firm shall be developed in accordance with paragraphs<br />

5.1.3 and 5.2.3;<br />

(c) The criteria for selection shall be mailed or distributed<br />

electronically, with a request for proposals, to all<br />

architectural-engineering firms which have complied<br />

with the standards set forth for prequalification in Article<br />

XII of these regulations. The criteria shall set a date<br />

and time for the submission of proposals, and no proposals<br />

shall be accepted subsequent to the date and time so<br />

designated;<br />

(d) A committee consisting of at least three persons shall<br />

be appointed by the Superintendent or his designee and<br />

shall evaluate the proposals submitted and select a list<br />

of at least three firms for each project, all of which are<br />

considered by the committee as qualified to do the work<br />

in question. The committee shall recommend to the Superintendent<br />

the firm to be awarded the contract, and<br />

shall rank the other firms in order of recommendation.<br />

Upon approval by the Superintendent, the Executive Director<br />

of Facilities and Transportation shall then enter<br />

into negotiations with the recommended firm and shall<br />

attempt to enter into a contract with the firm for the rendition<br />

of architectural-engineering services. In the event<br />

that the recommended firm does not enter into a contract<br />

with the Board, the Executive Director of Facilities and<br />

Transportation shall terminate the negotiations with the<br />

recommended firm and enter into negotiations with the<br />

next recommended firm.<br />

(e) When negotiations are completed, the proposed contract<br />

with the recommended architectural-engineering<br />

firm shall be submitted to the Superintendent for final<br />

approval.<br />

5.3 Special Approval of Selections<br />

5.3.1 When the estimated cost of a contract for architectural-engineering<br />

professional services exceeds $100,000, the<br />

selection shall require the approval of the Superintendent<br />

or his designee.<br />

5.3.2 When a firm, to which the Board has previously<br />

awarded contracts totaling over $100,000 during the current<br />

calendar year, has been selected for an additional<br />

award to be made by the same contracting office, the selection<br />

shall require, prior to negotiation with the architectural-engineering<br />

firm, the approval of the Superintendent<br />

or his designee.<br />

5.3.3 When supplemental work to be added to an existing<br />

contract will cause the total contract cost to exceed<br />

$100,000 or exceed seven percent (7%) of the total contract<br />

cost, the selection for such work shall require the prior approval<br />

of the Superintendent or his designee.<br />