08.03.2014 Views

Geotechnical Desk Study - Islington Council

Geotechnical Desk Study - Islington Council

Geotechnical Desk Study - Islington Council

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

<strong>Geotechnical</strong> <strong>Desk</strong> <strong>Study</strong><br />

8. <strong>Geotechnical</strong> Considerations<br />

Based on the local boreholes, the ground conditions are indicated to comprise London Clay below<br />

a thin layer of Made Ground which is consistent with site observations of the cutting slopes.<br />

The railway cutting and terrace forming the Highbury Roundhouse site area appear to have been<br />

constructed before 1895. Based on the local borehole evidence from the site, the terrace was<br />

formed by cutting only, ie it was not formed by cut and fill operations. Therefore London Clay can<br />

be anticipated to lie beneath the tarmac or concrete covered area. However, this should be<br />

confirmed by a site specific ground investigation.<br />

Movement of the retaining wall along the western side has occurred and the telegraph pole is<br />

leaning significantly. Longitudinal cracking of the tarmac/concrete surfacing was observed.<br />

However, signs of instability of the slope below this area were not seen. The historical maps show<br />

a building along the top of the cutting perpendicular to the Youth and Community Centre in the<br />

area. Therefore it is unclear whether the cracking and structure movements have been caused by<br />

movement of the slope or as a result of previous structural loading. As stated above, the wall only<br />

retains a low height of material which does not seem to be responsible for the significant wall<br />

movements. As the wall and telegraph pole are likely to have shallow foundations they may have<br />

been affected by swelling and shrinking of the highly plastic London Clay rather than slope<br />

movement. Although, if the foundations are very shallow they may have been affected by soil<br />

creep within the cutting. This wall has suffered extensive structural damage and requires removal.<br />

This wall could be replaced by another wall or a suitably founded fence in combination with some<br />

local regrading of the crest of the slope.<br />

The eastern retaining wall has undergone significant movement and requires either remediation or<br />

replacement as discussed in Section 7.4.<br />

The walls of a number of properties have had to be tied back as a result of structural movement<br />

probably resulting from swelling and shrinkage of the clay.<br />

There is a risk of contamination due to previous uses of the terraced area. However, no evidence<br />

of contamination was observed in front of the west side retaining wall at the top of the cutting and<br />

in addition no fly tipping or other piles of material were observed on the cutting slopes. It is<br />

recommended that an assessment is made of the likely contamination that may have been caused<br />

by the glass bottle works and latterly by the packing case factory.<br />

Any new construction on the terraced area would need to be founded sufficiently back from the<br />

top of the cutting so that the loading would not cause instability of the railway cutting. Slope<br />

stability analysis should be carried out to asses this risk using the results of a site specific ground<br />

investigation. However, typically any shallow pad foundations are likely to be required to be<br />

located 3m back from the top of a cutting. The type and size of the footings would be dependent<br />

on the loading of the structure. For a relatively lightweight 2 storey structure, pad foundations are<br />

likely to be acceptable founded at least 1m below ground level in the London Clay or deeper if<br />

trees or other mature vegetation is present. Based on the existing geotechnical data, the allowable<br />

bearing pressure for pad foundations in the London Clay is likely to be 100kPa for a settlement not<br />

exceeding 25mm. For more heavier structures, piled foundations are likely to be required. As the<br />

load is taken on the piles to deeper levels, piled foundations can be located closer to the top of the<br />

cutting. The piled foundations would typically be 15 to 20m in length depending on the loads that<br />

they would be required to carry. The area of any new building would also be constrained by the<br />

eastern retaining wall and the replacement of this wall using piles in front of the existing wall is<br />

recommended (see Section 10.3 and the sketch in Appendix F.2) as this would avoid disruption to<br />

the existing wall.<br />

5044006/002 <strong>Geotechnical</strong> <strong>Desk</strong> <strong>Study</strong> (2).doc 18

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!