8.3 Site Order Book: The site order book is one of the primary records to be maintained by the<br />
JTO supervising the work during the course of execution of works. The noting made by<br />
officers as well as contractors, will form as basis for operation of many contractual clauses.<br />
The contractor shall remove all the defects pointed out by <strong>BSNL</strong> in the Site order book<br />
(Section XVI Annexure B). The site order book is to be maintained in the prescribed format.<br />
The contractor or their authorized representatives shall also be at liberty to note their<br />
difficulties etc. in these books. The site order books shall invariably be consulted at the time<br />
of making final payments to the contractor.<br />
8.4 Testing and Acceptance Testing<br />
For attending to cable fault tracing work and cable maintenance work, the Acceptance Testing<br />
shall not be applicable. However, the Acceptance Testing shall be applicable for Cable<br />
Laying & Rehabilitation work. The Acceptance Testing procedure is as under:<br />
The work shall be deemed to have been completed only after the same has been accepted by<br />
the A.T. Officer for conducting test checks without any extra payment. The contractor shall<br />
restore the pits after test measurements to its original shape. The contractor shall be<br />
responsible to provide test/measurement tools and testers for conducting various tests.<br />
Scope of Acceptance Testing: The purpose of Acceptance testing is to verify integrity of<br />
measurement and quality of work done. The A.T. officer shall not be responsible for<br />
recording of measurements for the purpose of billing and contractual obligations. However, if<br />
the measurements taken by A.T. officer are found to be lesser than the measurements<br />
recorded by the officer responsible for recording the measurements, the measurement taken<br />
by A.T. Officer shall prevail without prejudice to any punitive action against the contractor as<br />
per provisions of the contract and the officer recording the measurements. The contractor<br />
shall be obligated to remove defects/deficiencies pointed out by the A.T. officer without any<br />
additional cost to <strong>BSNL</strong>-CHENNAI TELEPHONES.<br />
Offering the work for Acceptance Testing: The Sub Divisional Engineer responsible for<br />
construction, after having satisfied himself of completion of work ready for A.T., shall offer<br />
the work to A.T. Officer for conducting Acceptance Testing within 15 days of completion.<br />
The work shall be offered for A.T. as soon as work of cable laying and rehabilitation are<br />
completed in all respects. The work against any work order can be offered for A.T. in a<br />
number of such stages. The contractor shall provide labour, if demanded by the A/T officer<br />
for digging of test pits and other necessary infrastructure for carrying out the A/T work. No<br />
extra payment will be made for the digging of test pit.<br />
9. WARRANTY:<br />
9.1 The contractor, wherever he supplies the materials, shall warrant that the material supplied for<br />
the work shall be new and free from all defects and faults in material, workmanship and<br />
manufacture and shall be of the highest grade and consistent with the established and<br />
generally accepted standards for materials of the type ordered and shall perform in full<br />
conformity with the specifications and drawings. The contractor shall be responsible for any<br />
defects that may develop under the conditions provided by the contract and under proper use,<br />
arising from faulty materials, design or workmanship such as corrosion of the equipment,<br />
inadequate quantity of materials etc. and shall remedy such defects at his own cost when<br />
called upon to do so by <strong>BSNL</strong> who shall state in writing in what respect the stores are faulty.<br />
This warranty shall survive inspection or payment for, and acceptance of goods, but shall<br />
expire except in respect of complaints notified prior to such date, twelve months after the<br />
successful completion of Acceptance Testing (wherever applicable).<br />
Page 22 of 80<br />
Signature of Bidder with seal