1.2 ALLIED ACTIVITIES:<br />

1.2.1 Transportation of Materials : The materials required for executing the work entrusted to the<br />

contractors against a work order shall be made available at District Store Depot at Vyasarpadi,<br />

<strong>Chennai</strong>. In some cases the materials may be available at Divisional / Sub-divisional store<br />

godown. The contractor shall be responsible for transporting the materials, to be supplied by<br />

<strong>BSNL</strong> or otherwise to execute the work under the contract, to site at his/their own cost. The costs<br />

of transportation are subsumed in the standard Schedule Rates and therefore no separate charges<br />

are payable on this account.<br />

1.2.2 Disposal of Empty cable drums: The contractor shall be responsible to dispose of the<br />

empty cable drums after laying of the cables. The cost of various sizes of empty cable<br />

drums recoverable from the contractor has been fixed taking in to account the<br />

prevailing market rates as mentioned in this document.<br />

1.2.2.1 It shall be obligatory on part of the contractor to dispose of the empty cable<br />

drums at his/their level and the amount fixed for various empty cable drums<br />

shall be recovered from the bill for the work for which the drum(s) was/were<br />

issued or from any other amount due to the contractor or the Security Deposit.<br />

1.2.2.2 The contractor shall not be allowed to dump the empty cable drums in<br />

<strong>BSNL</strong>/Govt./Public place which may cause inconvenience to the<br />

department/public. If the contractor does not dispose of the empty cable drums<br />

within 3 days of becoming empty, <strong>BSNL</strong> shall be at liberty to dispose of the<br />

drums in any manner deemed fit and also recover the amount fixed in this<br />

contract from the bill/security deposit/any other amount due to the contractor.<br />

1.2.3 Supply of Materials: There are some materials required to be supplied by the contractor for<br />

execution of works under this contract like hard PVC water pipes, B-class GI pipes, Cement,<br />

Wire Mesh and Steel for protection, etc, besides using other consumables which do/don’t<br />

become the part of the asset. The contractor shall ensure that the materials supplied are of best<br />

quality and workmanship and shall be strictly in accordance with the specifications.<br />

2. VALUE OF WORK: The estimated cost of work is as mentioned in the Notice Inviting<br />

Tenders which has been worked out based on standard scheduled rates mentioned in this tender<br />

document. The actual value of work may vary based on the actual requirement but generally<br />

being limited to + 25% or – 25% of the indicated value.<br />

3. JURISDICTION OF CONTRACT: The jurisdiction of the contract shall be DGM-CPT(O<br />

& M)zone <strong>Chennai</strong> <strong>Telephones</strong>, comprising areas of Chengalpat, Marimalai Nagar and<br />

Maduranthagam External Divisions. If any additional telephone exchange is planned, the<br />

same shall be included in the <strong>Chennai</strong> <strong>Telephones</strong> South Zone in the vicinity of concerned<br />

exchange keeping in view the logistics of carrying out the work.<br />

CABLE LAYING AND REHABILITATION OF EXTERNAL PLANT<br />

SPECIFICATION<br />

The cable laying and rehabilitation Specifications will be issued along with the Work-Order. Detailed<br />

guidelines for various methods of internal sub-office fitting have been furnished at Section XVI<br />

Annexure E.<br />