10. INITIAL SECURITY DEPOSIT (ISD) :<br />
On receipt of formal order of acceptance of the tender and before execution of the<br />
agreement with the Corporation, the successful tenderer shall have to deposit a<br />
further amount as ISD, so that the EMD together with ISD will 2% of the value of<br />
order, in shape of crossed Bank Draft/Pay Order/Bankers Cheque from any<br />
Nationalised Bank drawn in favour of “Orissa Industrial Infrastructure Development<br />
Corporation” payable at Bhubaneswar. The same will be released after expiry of the<br />
guarantee period on application.<br />
11. EXECUTION OF AGREEMENT:<br />
The successful tenderer will have to execute an agreement with the Corporation<br />
within 10 (Ten) days of issue of formal order of acceptance of offer after deposited<br />
required amount of ISD failing which the EMD alongwith ISD will be forfeited.<br />
12. TIME OF COMPLETION:<br />
The time of completion of the work shall be 9( nine ) months from the date of issue<br />
of the work order/ Letter of Intent/ Acceptance.<br />
13. PAYMENT:<br />
13.1 Interim payment for the work done by the Contractor will be made on the basis of<br />
measurement of each item recorded in the measurement book by the Engineer incharge<br />
concerned.<br />
13.2 All such interim payments from time to time shall be treated as payment by way of<br />
advance against the final payment only.<br />
13.3 Final payment will be made after completion of the work in all respect and recorded<br />
in the measurement book by the concerned Engineer in-charge .<br />
14. TAX DEDUCTION:<br />
Recovery towards Income Tax, Sales Tax/ Work Contract Tax will be made from<br />
gross amount of each R/A bill at the rates fixed by Government from time to time.<br />
15. PENALTY:Failure to execute the order within the time schedule, tenderer is liable to<br />
pay penalty equal to ½ % (Half percent) of the value of order not executed per week