CLAUSE : 23 : JURISDICTION IN THE EVENT OF DISPUTE :<br />
That the purpose of the jurisdiction in the event of dispute if any the contract should<br />
be deemed to have entered into within the jurisdiction of Civil Court situated at Bhubaneswar<br />
State of Orissa and it is agreed that neither party to this agreement will be competent to<br />
bring a suit in regard to the matters converted by this contract at any place outside Orissa.<br />
CLAUSE : 24 : INSPECTION OF SCAFFOLDING :<br />
The Engineer-in-charge and /or his subordinate Engineer-in-charge will have the right<br />
to inspect the scaffolding any centering etc. made for the work and can reject partly or fully<br />
such structure if found defective in his/their opinion.<br />
CLAUSE : 25 : LIGHTING AND SANITARY ARRANGEMENT :<br />
Lighting and Sanitary arrangement and supply of drinking water will be made by the<br />
Contractor at his own cost for his labour camp.<br />
CLAUSE: 26 : PAYMENT OF TAXES :<br />
The Contractor shall bear all taxed including Sales Tax both State & Central Income<br />
Tax, Royalties, Octroi Tax, Fair Weather Charges and tillage where necessary.<br />
CLAUSE : 27 : SITE CLEARANCE :<br />
After the work is finished or completed, surplus materials and debris are to be<br />
removed by the Contractor at his own cost and preliminary works such as vast, mixing<br />
platforms, level pillars, temporary sheds and godowns etc. are to be dismantled and all such<br />
materials removed from site. The site involved in the construction activities should be<br />
cleared properly.<br />
CLAUSE –28: FAIR WAGE CLAUSE:-<br />
The contractor shall abide by the fair wage clause as introduced by the State<br />
Government and emended from time to time. Orissa PWD/Electricity Department<br />
Contractor’s labour regulations shall also be applicable to the Contractor . These shall form a<br />
part of the contract.<br />
CLAUSE –29: CONTRACTOR TO SUPPLY PLANT, LADDERS, SCAFFOLDING ETC,:<br />
The Contractor shall supply at his own cost all materials ( except such special<br />
materials, if any, as may in accordance with the contract be supplied by the Corporation ,<br />
plants, machineries tools, appliances implements , ladders , cordage , tackles scaffolding ,<br />
instrument and temporary work requisite for the proper execution of the work whether