c) If the rate is not existing in the schedule of rate but can be derived from<br />
analogous items existing in the schedule of rate, the rate will be derived accordingly.<br />
d) If the rate can not be derived as per above clauses mentioned at (a), (b) & (c),<br />
the rate for such items is to be arrived at by actual analysis taking into consideration<br />
the market value of materials and actual labour involved. 1o 1 / 2 % extra shall be<br />
allowed towards over head and profit.<br />
7. All the measurement shall be jointly taken by Contractor’s representative and<br />
Engineer-in-charge of the work at site and they shall be jointly signed. Any dispute<br />
arising out of this shall be referred to the Authorised Officer’s of the Corporation and<br />
his decision shall be binding on both the parties.<br />
8. Purchase vouchers of materials in original shall be produced for verification on<br />
demand by the Authorized Officer of the Corporation. Carriage or transport charges<br />
shall not be considered for the purpose of this payment.<br />
8. Any deviation between specifications, schedule of quantities and drawings found by<br />
the Contractor, the same shall be brought to the notice of the Authorized Officer of<br />
the Corporation immediately.<br />
10. In case of doubt regarding the meaning and scope of specifications of different items<br />
of works and in case of variation in the provisions of IS Specification, CPHEEO<br />
Manual National Building Code and Orissa Detailed Standard Specification and<br />
I.R.C., MORTH specification, the decision of the Managing Director, <strong>IDCO</strong> will be<br />
final and binding, and no extra claim over and above the accepted agreement, rules<br />
will be payable to the Contractor on this account.<br />
11. The Contractor shall carry out the electrical, sanitary and water supply through the<br />
agency as approved by the Corporation whose name shall be submitted to the<br />
authorized officer for approval. All works carried out shall comply with Rules, Byelaws,<br />
and regulations in force. All testing fees for materials as required shall be borne<br />
by the Contractor only.<br />
12 The work of plumbing and drainage shall be carried out by skilled plumbers in line<br />
and level as instructed and as per good engineering practice.<br />
13. The Corporation can omit or add item. Any extra item of to be carried out, the rate for<br />
the same shall be decided by the Authorized Officer of the Corporation as per item<br />
no-6.