46<br />

c) If the rate is not existing in the schedule of rate but can be derived from<br />

analogous items existing in the schedule of rate, the rate will be derived accordingly.<br />

d) If the rate can not be derived as per above clauses mentioned at (a), (b) & (c),<br />

the rate for such items is to be arrived at by actual analysis taking into consideration<br />

the market value of materials and actual labour involved. 1o 1 / 2 % extra shall be<br />

allowed towards over head and profit.<br />

7. All the measurement shall be jointly taken by Contractor’s representative and<br />

Engineer-in-charge of the work at site and they shall be jointly signed. Any dispute<br />

arising out of this shall be referred to the Authorised Officer’s of the Corporation and<br />

his decision shall be binding on both the parties.<br />

8. Purchase vouchers of materials in original shall be produced for verification on<br />

demand by the Authorized Officer of the Corporation. Carriage or transport charges<br />

shall not be considered for the purpose of this payment.<br />

8. Any deviation between specifications, schedule of quantities and drawings found by<br />

the Contractor, the same shall be brought to the notice of the Authorized Officer of<br />

the Corporation immediately.<br />

10. In case of doubt regarding the meaning and scope of specifications of different items<br />

of works and in case of variation in the provisions of IS Specification, CPHEEO<br />

Manual National Building Code and Orissa Detailed Standard Specification and<br />

I.R.C., MORTH specification, the decision of the Managing Director, <strong>IDCO</strong> will be<br />

final and binding, and no extra claim over and above the accepted agreement, rules<br />

will be payable to the Contractor on this account.<br />

11. The Contractor shall carry out the electrical, sanitary and water supply through the<br />

agency as approved by the Corporation whose name shall be submitted to the<br />

authorized officer for approval. All works carried out shall comply with Rules, Byelaws,<br />

and regulations in force. All testing fees for materials as required shall be borne<br />

by the Contractor only.<br />

12 The work of plumbing and drainage shall be carried out by skilled plumbers in line<br />

and level as instructed and as per good engineering practice.<br />

13. The Corporation can omit or add item. Any extra item of to be carried out, the rate for<br />

the same shall be decided by the Authorized Officer of the Corporation as per item<br />

no-6.