34<br />
thereof or using the same by the corporation . Only the final certificate will relieve the<br />
contractor from the contract obligations<br />
. Except the certificate no other certificate or<br />
payment against the certificate shall be taken to be an admission by the corporation of the<br />
performance of contract .<br />
CLAUSE-7: PAYMENT<br />
Interim payment for the work done by the contractor A bill shall be submitted by the<br />
Contractor each month or before the date fixed by the Corporation for all works executed in<br />
the previous month and the authorized officer of the Corporation or his subordinate shall<br />
take the requisite measurement for the purpose of having the same verified and the claim as<br />
far as admissible, adjusted if possible, before the expiry of ten days from the presentation of<br />
the bill. If the Contractor does not submit the bill within the time fixed as aforesaid, the<br />
authorized officer of the Corporation or his subordinate shall measure up the said work in the<br />
presence of the Contractor whose counter signature to the measurement list shall be<br />
sufficient warrant and the authorized officer of the Corporation or his subordinate shall<br />
prepare a bill from such list which shall be binding on the Contractor in all respects. Provided<br />
that, if any balance of the 7% (seven percent),security is outstanding from each such<br />
payment shall be deducted so mush not exceeding 5% as may be necessary to make up the<br />
balance of the security. All such intermediate payments to the Contractor shall be regarded<br />
as payments by way of advance against the final payment only and not as payments for<br />
work actually done and completed and shall not preclude the requiring of bad, unsound and<br />
imperfect or unskilled work to be removed and taken away and reconstructed or re-erected,<br />
or be considered as an admission of the due performance of the contract , or any part<br />
thereof in any respect, or the accrual of any claim nor shall it condoled, determine of effect in<br />
any way the powers of the Corporation under these conditions or any of them as to the final<br />
settlement or adjustment of the accounts or otherwise, or in any other way vary or affect the<br />
contract.<br />
5% (Five percent) of the value of each Running Account Bill and the final bill<br />
prepared shall be retained withheld towards security deposit as further security over the 2%<br />
(Two percent) I.S.D. & E.M.D for the defect liability period. Deduction towards Income tax<br />
and work contract/Sales Tax for each will be made from each bill and the amount will be<br />
credited to the concerned authority at the rates fixed from time to time.<br />
Final Payment:<br />
The Contractor shall receive the final payment of entire of all the money due to payable to<br />
him under or by virtue of the Contract except the Security Deposit of (Ten percent) of the<br />
gross value deducted from each R/A & final bill as further security over the E.M.D. & I.S.D.<br />
comprising 2% (Two percent) of the tender amount.The contractor shall submit the final bill