BILLS OF QUANTITIES - Name of Project<br />
CONSULTANT: Name of Office DATE:APR. 2008<br />
BILL No. (01/1) EXCAVATION AND BACK FILLING (SEC - 01)<br />
ITEM<br />
RATE<br />
AMOUNT<br />
DESCRIPTION UNIT QUANTITY<br />
NO. US$ CENT US$ CENT<br />
1.5<br />
(SECTION NO. ' 1 ‘)<br />
Excavation, Back filling and Site Works.<br />
Provisional Supply and spread 20 cm thick base coarse<br />
after compaction. Price to include leveling, watering and<br />
compacting to 95 % field density. Complying with<br />
Modified AASHTO Density Test T-80.<br />
TOTAL<br />
TOTAL CARRIED TO SUMMARY<br />
M.S 1<br />