19.11.2014 Views

ANNUAL REPORT 2002 - Skanska

ANNUAL REPORT 2002 - Skanska

ANNUAL REPORT 2002 - Skanska

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

The impossible made possible<br />

Over the past two years, <strong>Skanska</strong> has received contracts<br />

for almost 100 percent of the power plants built in the<br />

New York area – an achievement based on extraordinary<br />

trust and performance.<br />

For Mike Lembo, President of the<br />

Slattery <strong>Skanska</strong> Power Group, it is<br />

easy to explain how <strong>Skanska</strong> carved<br />

out the leading position as a builder<br />

of power plants in the New York City<br />

area. ”We took on an unbelievable<br />

task, and we delivered on what we<br />

promised,” he says.<br />

It was December 2000. New York<br />

Power Authority (NYPA) had stepped in<br />

to solve an emergency situation. “They<br />

were predicting a shortfall of 400–600<br />

megawatts of power,” Mr. Lembo<br />

explains. “And in New York, if you have<br />

blackouts, that’s a serious problem.”<br />

With the summer heat waves only<br />

five months away, NYPA needed to<br />

build no fewer than eleven power units<br />

at seven locations. So John Grzan,<br />

Senior Project Manager at NYPA,<br />

turned to <strong>Skanska</strong> for help.<br />

“They trusted us. They knew that if<br />

we made a promise, we would make<br />

the end date,” Mr. Lembo explains.<br />

“And we knew that if we did it, we<br />

would truly be helping the people of<br />

New York.”<br />

Both <strong>Skanska</strong> and NYPA agreed<br />

from the start that the project would<br />

have to be run in an unconventional<br />

way. <strong>Skanska</strong> began working before<br />

the design and scope of the project<br />

were approved.<br />

“We talked constantly and came<br />

to agreements. We had to trust each<br />

other, and do whatever it took. NYPA’s<br />

effort was Herculean. Our teams<br />

worked day and night, seven days a<br />

week for at least three of those five<br />

months – we were faxing in the designs<br />

and running with them out to the<br />

field,” Mr. Lembo continues.<br />

<strong>Skanska</strong> used the first site as a way<br />

to speed the process. “The Hell Gate<br />

site in the Bronx was always three to<br />

four weeks ahead of the others. So<br />

we’d have meetings at 5 or 6 a.m. and<br />

talk about any potential problems<br />

and share knowledge,” Mr. Lembo<br />

explains. And with three specialized<br />

<strong>Skanska</strong> companies – Slattery, Gottlieb<br />

and Underpinning – working together<br />

far into overtime, <strong>Skanska</strong> got the<br />

job done, right on time, despite an<br />

impossible schedule.<br />

Mr. Lembo recalls the completion of<br />

the first unit with pride: “It was 1 a.m.<br />

when we started it up, and there were<br />

people there whose shifts were long<br />

over. They weren’t getting paid, but they<br />

wouldn’t have missed it for the world.”<br />

Then word of <strong>Skanska</strong>’s achievement<br />

spread. In <strong>2002</strong>, KeySpan Energy<br />

Development Corporation and Calpine<br />

Corporation awarded Slattery <strong>Skanska</strong><br />

contracts to construct a total of five<br />

power units using the same aggressive<br />

construction schedule. All of them were<br />

completed profitably and were delivered<br />

on schedule. In the past two years,<br />

<strong>Skanska</strong> has built a total of 19 plants<br />

of varying capacity for four different<br />

customers in the New York area.<br />

“It’s a small community. Your<br />

reputation, honesty and ability to<br />

deliver what you promise are vital –<br />

almost more important than the price,”<br />

says Mike Lembo. “And we have that<br />

kind of attitude. Our customers mean<br />

everything to us – when we make a<br />

commitment to them, we live up to it.”<br />

The impossible made possible – <strong>Skanska</strong> Annual Report <strong>2002</strong> 25

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!