19.11.2014 Views

14.7 - Fault and Protection Schedule - EDF Hinkley Point

14.7 - Fault and Protection Schedule - EDF Hinkley Point

14.7 - Fault and Protection Schedule - EDF Hinkley Point

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

PRE-CONSTRUCTION SAFETY REPORT<br />

CHAPTER 14: DESIGN BASIS ANALYSIS<br />

SUB-CHAPTER : <strong>14.7</strong><br />

PAGE : 3 / 48<br />

Document ID.No.<br />

UKEPR-0002-149 Issue 02<br />

The main subsequent additions to the FRATEC 01 approach were linked to changes in “design<br />

rules” (e.g. SFC, i.e. redundancy requirement at the component level) shifting to “safety analysis<br />

rules” (e.g. the requirement to assume an “aggravating failure” i.e. a redundancy requirement at<br />

the function level). Other examples were extension of the scenario duration through the operator<br />

action phase, <strong>and</strong> the introduction of additional event combinations involving Loss Of Offsite<br />

Power (LOOP).<br />

Changes to the list of events were made related to the experience feedback <strong>and</strong> changes in<br />

system design options.<br />

EPR specific options led to transients being added or excluded from the Design Basis<br />

Assessment (DBA) list that was used for in service French Nuclear Power Plants (NPP). The<br />

changes were in three main categories as follows:<br />

1) Changes resulting from EPR constitutive options, such as:<br />

• consideration of transients occurring in the different plant states led to PCC events<br />

for outages being introduced as design basis accidents (these were considered as<br />

beyond design basis accidents in previous French NPPs, <strong>and</strong> consequently<br />

analysed using less stringent rules);<br />

• consideration of transients in auxiliary buildings, which led to the introduction of fuel<br />

pool transients, <strong>and</strong> transients in the effluent treatment building <strong>and</strong> the nuclear<br />

auxiliary building.<br />

2) Changes due to design improvements in the EPR that had a direct impact on the list of<br />

design basis faults. An example was application of the break preclusion principle that led to the<br />

exclusion of 2-A LOCA from the PCC list. LOCA outside the containment was added to the DBA<br />

list to address the specific EPR design of the residual heat removal system function, which is<br />

provided by the safety injection system.<br />

3) Changes due to the application of PSA early in the design process, which impacted on the<br />

justification of the list itself <strong>and</strong> on the way transients were arranged into the different PCC<br />

categories.<br />

The use of PSA also impacted the list of RRC-A events considered, as mentioned below.<br />

1.3. CORE-MELT RISK REDUCTION CATEGORY (RRC-A EVENTS)<br />

The origin of the list of scenarios involving multiple failures (called RRC-A sequences in the EPR<br />

approach) was a French Safety Authority (ASN) request for consideration of design extension<br />

conditions representative of the total loss of main redundant systems (power supply, heat sink,<br />

SG feedwater, long term RIS [SIS] <strong>and</strong> reactor trip through Anticipated Transients Without<br />

Scram). PCC-4 criteria were imposed, but less stringent rules were accepted.<br />

Later on, other scenarios were added at the request of the ASN, generally to illustrate the<br />

robustness of the defence in the EPR design (drainage of two SGs, initially corresponding to the<br />

SFC exception on main steam isolation valves; multiple SGTRs combined with Main Steam Line<br />

Break).

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!