24.12.2014 Views

IHD Engineering Awards submission - Fremantle Ports

IHD Engineering Awards submission - Fremantle Ports

IHD Engineering Awards submission - Fremantle Ports

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

Mandatory Judging Criteria<br />

Criteria 6:<br />

Contribution to sustainable development<br />

The material to be dredged underwent extensive testing,<br />

showing that the sediments would not pose a risk to the<br />

environment or human health. Similarly excavated material<br />

was only reused for the Rous Head reclamation works after<br />

testing confirmed its suitability.<br />

The works were undertaken in compliance with projectspecific<br />

Environmental Management Plans addressing<br />

environmental risks specific to each component of<br />

construction activities. Weekly environmental inspections<br />

were performed and all incidents were recorded and<br />

followed up.<br />

Efficient use of natural resources while<br />

providing for beneficial use<br />

A strong emphasis was given to waste minimisation and<br />

material reuse. Total dredging volumes were minimised<br />

through detailed planning studies and temporary site<br />

facilities were designed and located to provide a longerterm<br />

benefit to future operations. Independent water<br />

quality monitoring was undertaken throughout the project<br />

beyond the requirements of the environmental approval<br />

conditions. The monitoring involved frequent water testing<br />

at more than 30 sites as well as regular aerial photography,<br />

seagrass and coral monitoring.<br />

About 480,000 tonnes of limestone and granite were used<br />

to construct a seawall extension at Rous Head. Some of<br />

the rock was reused from an existing seawall. Rock grading<br />

was carefully specified to maximise quarry yields and<br />

reduce waste.<br />

Dredge material from the deepening, material stockpiled<br />

at Rous Head from previous dredging campaigns and<br />

excavated material from the berth works were used to<br />

create 27 hectares of land for port purposes. Dredged<br />

material was placed hydraulically to avoid the need<br />

to import engineered fill and to limit the amount of fill<br />

requiring energy intensive soil improvement works.<br />

A design modification to the berth works reduced the<br />

diameter and thickness of piles used to allow for local<br />

manufacture. This reduced the tonnage of steel required<br />

as well as transportation distances.<br />

Using precast concrete elements also allowed for the<br />

combined steel and timber moulds to be reused.

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!