4<br />

2.5 A draft First Pass TRA is prepared by the PSTA at the earliest opportunity<br />

following the ORC to identify the potential technical risks <strong>and</strong> issues <strong>and</strong> to allow the<br />

project to develop appropriate treatment strategies for each identified risk 2 <strong>and</strong><br />

resolution strategies for any significant issues that have been identified. The risks<br />

<strong>and</strong> issues will be presented to the Capability Development Stakeholder Group<br />

(CDSG) for consideration <strong>and</strong> agreement of the treatment <strong>and</strong> resolution strategies<br />

prior to First Pass consideration. The First Pass TRA is approved by the LCOD prior<br />

to consideration of the project by the Capability Development Board (CDB).<br />

2.6 <strong>Technical</strong> <strong>Risk</strong> Certification. The CDS is required by Government to provide<br />

an independent assessment of the level of technical risk presented by a project at<br />

each Government consideration — primarily First <strong>and</strong> Second Pass Project Approval,<br />

but also when a submission is made to Government seeking an amended Project<br />

Approval, eg a Real Cost Increase for a change in scope. The <strong>Technical</strong> <strong>Risk</strong><br />

Certification (TRC) is the CDS’s statement on technical risk <strong>and</strong> issues <strong>and</strong> uses the<br />

TRA as guiding input. Following the CDB, the CDS will review the TRA <strong>and</strong> develop<br />

a draft TRC to inform <strong>Defence</strong> Capability Committee (DCC) consideration. Following<br />

DCC approval, the CDS will refine <strong>and</strong> approve the TRC for inclusion in the<br />

MINSUB/CABSUB as appropriate.<br />

First Pass<br />

CDSG Document<br />

Endorsement<br />

ORC CDB DCC<br />

Draft<br />

CABSUB/<br />

MINSUB<br />

CABSUB<br />

/MINSUB<br />

TRI<br />

DSTO<br />

<strong>Risk</strong> <strong>Assessment</strong><br />

Draft TRA<br />

TRA agreed<br />

by DSTO<br />

LCOD<br />

Draft TRC<br />

from TRA<br />

Approved<br />

TRC<br />

<strong>Technical</strong> <strong>Risk</strong> Issues raised<br />

Project <strong>Risk</strong> Management<br />

with CDG Project Manager<br />

Identify <strong>and</strong> record <strong>Risk</strong>s – for<br />

each option<br />

Identify Treatment Strategies<br />

<strong>and</strong> costs – for each option<br />

Treatment Plan - for each<br />

option (amend other plans<br />

<strong>and</strong> strategies as required)<br />

Note any<br />

changes <strong>and</strong><br />

adjust treatment<br />

plan<br />

Review <strong>and</strong> revise as necessary<br />

Review <strong>and</strong> revise as necessary<br />

Treat <strong>Risk</strong>s<br />

Figure1: <strong>Technical</strong> risk activities supporting First Pass Project Approval<br />

2.7 Figure 1 summarises the technical risk activities supporting First Pass<br />

consideration <strong>and</strong> Project Approval. Figure 1 also shows how the technical risk<br />

2 For low risks the default risk treatment is to monitor them.<br />