QUARTERLY PROGRESS REPORT - Police Reform Programme
QUARTERLY PROGRESS REPORT - Police Reform Programme
QUARTERLY PROGRESS REPORT - Police Reform Programme
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
<strong>Police</strong> <strong>Reform</strong> <strong>Programme</strong> (Phase-II)<br />
Conclusion<br />
The majority of outcomes planned for this quarter were achieved although some delays were<br />
experienced due to unforeseen factors. Despite this PRP was able to reach several key<br />
outcomes and milestones.<br />
The return of the Draft <strong>Police</strong> Act by MoHA for revision and the formation of a <strong>Police</strong><br />
Committee to review the Draft Act pave the way to restart stalled legislative reform process.<br />
Finalisation and formal approval by the IGP of the Bangladesh <strong>Police</strong> Strategic Plan<br />
2012-2014 was a very significant milestone reached during the reporting period, providing the<br />
vision and strategic direction for the Bangladesh <strong>Police</strong> for the next 3 years. Another significant<br />
outcome was the inauguration of the very first day care center for Bangladesh <strong>Police</strong><br />
personnel.<br />
PRP continued to work in all project areas on developing the capacity and capability of the<br />
Bangladesh <strong>Police</strong>. Activities and achievements for this period include a review of the<br />
Bangladesh <strong>Police</strong> recruitment process, training needs assessments, a visit to the South<br />
African <strong>Police</strong>, women police participation in a development conference and training in Canada<br />
and Nepal, pilot implementation of ICT crime prevention and biometric identification systems<br />
and delivery of training to 634 participants on topics covering crime scene management, ToT,<br />
training needs assessment, community policing and model thana services. Over 900<br />
participants attended workshops organised by PRP on various issues.<br />
In the 4 th and final quarter of 2012 PRP will give emphasis to the completion of the activities<br />
planned for the year. Additionally, the project team will commence planning of the next year<br />
activities in line with the multi-year project plan.<br />
Quarterly Progress Report | July - September 2012<br />
15<br />