H-<strong>SAF</strong> Project Plan 2.0, October 2007 - Update PP-2.2, 10 April 2008 - Chapter 2 (From the Development Proposal) Page 34<br />

The Steering Group supervises the progress of the <strong>SAF</strong> Development and provides guidelines to ensure<br />

that the <strong>SAF</strong> objectives are met, and that a proper coordination of technical, financial and<br />

scientific/meteorological/hydrological aspects is performed.<br />

The H-<strong>SAF</strong> Steering Group is the programmatic authority that may decide on changes of the project<br />

planning as well as the corresponding adjustment of the payment plan.<br />

The <strong>SAF</strong> Project Team is the executive body of the Steering Group. It is chaired by the Project<br />

Manager, who also serves as Executive Secretary of the Steering Group. The composition of the Project<br />

Team reflects that one of the Steering Group, i.e. the nominal members are from Italy, Austria, Finland,<br />

Poland, ECMWF and Turkey. However, attendance to Project Team meetings is open to supporting<br />

experts from both inside and outside the Consortium, as appropriate.<br />

The H-<strong>SAF</strong> Project Scientist coordinates the scientific aspects of the H-<strong>SAF</strong> activities, including<br />

management of the Visiting Scientist programme and possible inter-<strong>SAF</strong> collaborations.<br />

Possible conflicts that could arise in the course of the Development Phase will be solved, in priority<br />

level of attempt:<br />

• by the Cluster leader, if internal to one Cluster<br />

• by the Project Team if the conflict is across Clusters or it was not possible to solve it at Cluster level<br />

• by the Steering Group in case of lack of solution at lower level.<br />

2.9 Programme schedule, Review meetings, documentation<br />

As mentioned, this Project Plan is intended to provide forecast of which user requirement can be met at<br />

specific points in time during the project (thus to provide input to the User Requirements Document)<br />

and to constitute a tool for monitoring work progress. Therefore, the work programme must be solidly<br />

anchored to the verification points along the Development Phase. The verification points and their<br />

relevance are recorded in Table 7, and follow the Review meetings structure.<br />

Table 7 - Events providing anchor points for the work schedule<br />

EVENT<br />

Date<br />

KOM Kick Off Meeting T0 + 00 Start of the Project - Start of Phase 1 (Preparatory phase).<br />

RR Requirements Review T0 + 06 <strong>Version</strong> 1.0 of this Project Plan and of the URD approved.<br />

PDR Preliminary Design Review T0 + 12<br />

All problems relative to satellite data acquisition and availability of baseline<br />

processing methods should be cleared. Prototype products should be<br />

available for early evaluation.<br />

WS-1 1 st Workshop T0 + 18<br />

Consolidated products definition, including:<br />

- Precipitation products<br />

- Soil moisture products<br />

- Snow products<br />

- Calibration/validation plan<br />

- Hydrological validation plan.<br />

CDR Critical Design Review T0 + 24<br />

Phase 1 Report, including:<br />

- Status of the product generation chains<br />

- Status of preparation of demonstrational products<br />

- Status of valisation activities<br />

- Status of preparation of the Hydrological validation programme.<br />

Approval of PP-2.0, URD-2.0, ATDD-1.0.<br />

Authorisation to release demonstrational products.<br />

Start of Phase 2 (Demonstration phase).<br />

SIRR System Integration Readiness Review T0 + 36<br />

Evaluation of the results of the product validation activity.<br />

Evaluation of early results of the Hydrological validation programme.<br />

STRR System Test Results Review T0 + 42 Authorisation to release pre-operational products.<br />

WS-2 2 nd Workshop T0 + 48<br />

Preliminary results of the Hydrological validation programme.<br />

Release of recommendations for products tuning/improving.<br />

SVRR System Validation Results Review T0 + 54<br />

Consolidation and evaluation of results from impact studies.<br />

Consolidation of products and their characterisation from validation.<br />

Definition of the proposal for a possible Operational Phase.<br />

ORR Operations Readiness Review T0 + 60<br />

Demonstration of the final operational version of the products.<br />

End of the H-<strong>SAF</strong> Development Phase.